A FGHANISTAN RESHNA HERKAT DABS PRESENTATION Afghanistan Energy Sector Overview · PDF...
Transcript of A FGHANISTAN RESHNA HERKAT DABS PRESENTATION Afghanistan Energy Sector Overview · PDF...
DDAA AAFGHANISTAN FGHANISTAN BBRESHNARESHNA SSHERKATHERKATDABSDABS PRESENTATIONPRESENTATION
Afghanistan Energy Sector OverviewAfghanistan Energy Sector Overview
www.dabs.af1
2
DA AFGHANISTAN BRESHNA SHERKAT
شرکت ناښبر دافغانستان
Contains;Afghanistan Energy Sector And DABS Organizational Structure
Afghan Power Grid
DABS Operational Zones In Afghanistan
Afghanistan On Grid Power Plants / Transmission Lines 2013
DABS Nation-wide Growth Of Customers
Energy Generation A & Import For 1392
DABS Financial Plan 1392 (Core Operation)
DABS - Project Management Office
Da Afghanistan Breshna Sherkat
3
Afghanistan Energy Infrastructure, generation, transmission and distribution were almost destroyed over the past three decades due to the war and conflict. The government of Afghanistan corporatized the National electricity service department Da Afghanistan BreshnaMossasa (DABM) into an independent state owned utility as such, all assets, staff and other Rights and Obligations of (DABM) were transferred to (DABS) on May 2008.
DABS’ shares are owned by the Government, voted on by Government representatives. As per the Articles of Incorporation, the Initial capital shall be AFS 25 billion; the ultimate capital shall be AFS 100 billion
AFGHANISTAN ENERGY SECTOR
DA AFGHANISTAN BRESHNA SHERKATشرکت ناښبر نادافغانست
Da Afghanistan Breshna Sherkat
4
AFGHAN POWER GRID Essentially the Afghan Power Infrastructure is categorized into 4 general networks:
I. North East Power System; (NEPS) consisting of a grid linking 17 load centres (Kabul, Mazar-i-Shariff, Jalalabad, etc) with Uzbekistan and Tajikistan (220kv, 110kv)
II. South East Power System (SEPS) consisting of Khandar, etc linking Kajaki (110kv)
III. Herat system linking the Herat Zone with Iran (132, 110kv)
IV. Turkmanistan system linking Herat, Aqina, Andkhoi East/West, ShirinTagab, Mimana, Khoja Doko, Sarepul, Shibirghan, Mazar (110kv)
DA AFGHANISTAN BRESHNA SHERKATشرکت ناښبر نادافغانست
Da Afghanistan Breshna Sherkat
DABS Operational Zones in Afghanistan
DA AFGHANISTAN BRESHNA SHERKATشرکت ناښبر نادافغانست
5Da Afghanistan Breshna Sherkat
6
Afghanistan on Grid Power Plants / Transmission Lines 2013
Plants Installed Capacity in MWHydro 254
Thermal (Fuel Diesel/HFO) 203 Diesel Generator (Gen.Set) 65
Total 522
Transmission Lines Installed Capacity, Max in MW Republic of Uzbekistan 305.00 Islamic Republic of Iran 164.00
Republic of Tajikistan 322.00 Republic of Turkmenistan 50.04
Total 841.04
DA AFGHANISTAN BRESHNA SHERKATشرکت ناښبر نادافغانست
7
DABS Nation-wide Growth Of Customers
CATEGORIES 1389 1390 1391 Household 715,742 91.01% 814,585 91.95% 901,287 92.10%
Commercials 65,886 8.38% 65,940 7.44% 71,533 7.31%
Governmental 4,821 0.61% 5,360 0.61% 5,829 0.59%
Total 786,449 885,885 978,649
DA AFGHANISTAN BRESHNA SHERKATشرکت ناښبر نادافغانست
8
DABS ENERGY Plan / FORECAST 1392(21-Mar-2013 to 20-Mar-2014)
22%
Da Afghanistan Breshna Sherkat
شرکت برښنا دافغانستان 1392 سال مالی پالن 1392 Financial Plan for Da Afghanistan Breshna Sherkat
1391 1392
1. Revenue - -a) Sale of electricity 10,991,320 14,000,000 b) Other Revenue 300,000 300,000
11,291,320 14,300,000 - -
2. Power Generation-Fuel 1,369,952 909,883 3. Power Imported 6,683,287 9,525,857 4. Operation & Maintenance Cost 400,000 450,000
8,453,240 10,885,740 - -
5. Operational expenditure - -a) Employee costs 1,583,872 1,583,872 b) Contingency - -c Depreciation 1,500,000 1,500,000 d Tax 210,636 295,000 e Interest expense 5,705 7,200 f Other Administrations costs 300,000 368,755
3,600,213 3,754,827
12,053,453 14,640,568 - -
6 Financial Deficit (762,133) (340,568)
7 Subsidy from MoF (Diesel Fuel) 1,000,000 500,000
8 Financial Deficit 237,867 159,432 9
DABS Financial Plan 1392 (21-Mar-2013 to 20-Mar-2014)
DA AFGHANISTAN BRESHNA SHERKATشرکت ناښبر نادافغانست
Da Afghanistan Breshna Sherkat
10
22%
DA AFGHANISTAN BRESHNA SHERKATشرکت ناښبر نادافغانست
Da Afghanistan Breshna Sherkat
The first installment of the project (Tranche 1)
DABS - Project Management Office
11
List of projects - ABD;
1-1 Extension of 220 KV transmission line from Kunduz to Taluqan proximate within 65.68 km1-2 Tranche 4 subprojects preparation.1-3 Distribution Network of Kunduz and Baghlan1-4 Emergency tools for O&M o f (NEPS 220 KV)1 -5 Small hydro System in Badakhshan and Bamiyan.
The second installment of Project (Tranche 2)
1-2 Transmission line of 220 kV from the Chimtala substation to Kabul South Westsubstation
2-2 Construction of the new substation 220 kV at South West of Kabul.2-3 Distribution network extension in the South West for approximately 40,000 families (Dasht Barchi & arghandi)2-4 Procurement of Distribution Transformers (100 Nos.).
DA AFGHANISTAN BRESHNA SHERKATشرکت ناښبر نادافغانست
Da Afghanistan Breshna Sherkat
The third installment of Project (Tranche 3)
1-3 Rehabilitation Greshk hydropower plant and its distribution network .
12
The fourth installment of Project (Tranche 4)
1-4 500 kv transmission line from the border of Turkmenistan to Andkhoy and Sheberghan..2 -4 220 kv transmission line from Sheberghan to Mazar.3 -4 Construction of 220 kv substations at Sheberghan and Andkhoy.4 -4 Expansion of 220 kv substation at Mazar.5 -4 Distribution network in Logar and gardez.6 -4 implementation consultant.
DABS - Project Management OfficeList of projects - ADB;