51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题
Transcript of 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 1/42
2012年 9 月 PMP认证模拟考试一试卷 200
题
1 . A manufacturing ptoject has a schedule performance index (SPI) of 0.89 and a cost
performance index (PI) of 0.91 .!enerall",#hat is the $%S& explanation for #h" this
occurred'
A) &he scope #as changed.
$) A supplier #ent out of usiness and a ne# one needed to e found.
) Additional euipment needed to e purchased.
*) A critical path acti+it" too, longer and needed more laor hours to complete.
某个制造项目的进度绩效指数 (SPI) 是 0.89;成本绩效指数 (PI) 是 0.91。一!",#$
%&'()的*+的,是'
A) -./0。
$) 12345,6789的。
) :;的<=67>?。
*) @ABC的DEFG,670HIEJKLMN成。
-.
*uring the completion of #or, pac,ages,
the sponsor as,s the project manager to report onho# the project is going.In order to prepare the report,the project manager as,s all the team
memers #hat percent complete their #or, is.&here is one team memer #ho has een hard
to manage from the eginning.In response to eing as,ed #hat percent complete he is ,the
team memer as,s,Percent complete of #hat'/$eing tired of such comments ,the project
manager reports to the team memers oss that the team memer is not cooperating .hich
of the follo#ing is li,el" to e the real prolem'
A) &he project manager did not get u"Oin from the manager for the resources on the project.
$) &he project manager did not create an adeuate re#ard s"stem for team memers to impro+e
their cooperation.
) &he project manager should ha+e had a meeting #ith the team memers oss the first time
the team memer caused troule.
*) &he project manager does not ha+e #or, pac,ages.
PN成QRSTL,(UV7W项目XYZ[项目进\。]^_=[`,项目XY7W
ab的cd成efgQRN成的hij。b个cd成eklmnopqY,rstuQ
RN成hijK,ufvwx是N成hij'/y]z{$|#},项目XY~cd成
e的•€[`f$个成e‚R。ƒ„…个0†‡ˆ的s题'
A) 项目XY‰bkUŠqY‹Œ‡ˆ]项目ŽUŠ。
$) 项目XY‰b‘‚’的“”–M—进cd成e的‚R。
) 项目XY2˜™cd成e的•€l个š,Pcd成e›一œžŸK。
*) 项目XY‰bQRS。
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 2/42
2.hich is not a goal in oth project management and ualit" management'
A) Pre+ention o+er inspection. $) ustomer satisfaction.
) 3anagement responsiilit". *) &riple constraint.
ƒ„…个是项目qY™¡qY的¢£目¤'
A) ¥¦§¨©ª。 $) «¬®。 ) qY¯°±。 *) ²³´µ¶。4.hich of the follo#ing $%S& descries the +erif" scope process'
A) It pro+ides assurances that the deli+erale meets the specifications,is an input to the project
management plan.and is an output of perform ualit" control.
$) It ensures that the deli+erale is completed on time and gets customer acceptance,and sho#s
that the deli+erale meets specifications.
) It ensures customer acceptance , sho#s that the deli+erale meets specifications , and
pro+ides a chance for differences of opinion to come to light.
*) It is an output of perform ualit" control,occurs efore define scope,and ensures customer
acceptance.
ƒ„…项*+·¸¹^º»-.¼½'
A) ¾¿1成ÀÁ‚ÂÃ的Ä证,是项目qYÅÆ的ÇÈ,是ÉÊ¡Ë制的Ç(。
$) ¾ÌÄ成ÀÍKN成Ît«¬ÏÐ,Ñg成ÀÁ‚ÂÃ7W。
) ¾ÌÄ«¬ÏÐ,ÒÓ成ÀÁ‚ÂÃ7W,¿1ÔšÍKÕ)ÖP的s题。
*) ¾是ÉÊ¡Ë制的Ç(,P×Ø-.ÙÚ(),ÌÄ«¬ÏÐ。
5 . A project has the follo#ing earned +alue data assessed v A Û 6470007000 ; Û 6 O
5007000;SPIÛl.1-;$AÛ 697507000.hat is the earned +alue of the project'
A) 6270007000. $) 6275007000.) 6474807000. *) 657507000.
项目»)Ü数ÝÞƒvAÛ470007000 ßà;ÛO5007000 ßà;SPIÛ1.1-;$AÛ
97507000 ßà。á %Û 。A) 270007000 ßà $) 275007000 ßà ) 474807000 ßà *) 57507000 ßà
.At the eginning of project execution,"ou notice different opinions et#een team memers
relating to project #or, and deli+erales and to the le+el of o+erall complexit" .hat should
"ou do right no#'
A) !i+e "our team memers some time to de+elop a common understanding of the project scope
and product scope.:pcoming interface prolems ma" e resol+ed later .
$) :se the ris, management processes to identif" and assess ris,s caused " misunderstandings
and de+elop a plan #ith measures in order to respond to them.
) ;rgani<e meetings to identif" and resol+e mlsunderstandings et#een team memers in
order to earl" a+oid interface prolems,disintegration and costl" re#or, .
*) :se inter+ie#s in pri+ate #ith each indi+idual team memer to inform them of "our
expectations and "our reuirements in an atmosphere of confidence.
P项目ÉÊâT,ãä®t项目cd成e#项目QR™成À的åæ½度b£的çè。ã
)P2˜éwx'
A) êcd成eëKL,ì‘í#项目-.™îï-.的¢£Yð,ñò()的Ïós题
ôõö÷šðø。
$) ùúûüqY¼½Mýþ™ÿ估由¨误ð引Õ的ûü,编写个ÅÆM衡¡Î回2¾们。
)组织š议Mýþ、ðøcd成eÙL的误ð,ì便尽早避免Ïós题,减少返Q成本。
*)私ƒš见每个cd成e,P互相信±的氛.ƒ`诉u们ã的T望™ã的7W。= . $eing the project manager in a soft#are project #hich is currentl" initiated , "ou #ant to
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 3/42
assess high le+el ris,s.hat should "ou do'
A) *e+elop a preliminar" scope statement and document initiall" identified ris,s in this
document.
$) Identif" and anal"<e ris, e+ents using ualitati+e and uantitati+e techniues.
) *e+elop contingenc" plans and fallac, plans in case the original plan pro+es #rong.*) *iscuss the ris,s documented in "our ris, register #ith the project ,e" sta,eholders.
ã是个项目XY,刚刚E一个!"项目,ã#ÿ估*$¯œ的ûü,ã2˜éwx'
A)编写â%-.fg&,'(ƒM*âýþ的ûü。
$) ùú×)™×¡*+ýþ™i,ûü-"。
)编写2.ÅÆ™õ=ÅÆì¦/M的ÅÆ()0误。
*) ™项目172V#ãûü3'45的ûü进Ê67。
8.hat is not a reason for companies to organi<e lessons learned'
A) >essons learned dataases are an essential element of the organi<ational process assets.
$) >essons learned should focus on identif"ing those accountale for errors and failures.
) >essons learned sessions should ring aout recommendations to impro+e future performance
on projects.
*) Phase end lessons learned sessions pro+ide a good team uilding exercise for project staff
memers.
ƒ„…一项是85组织X9:;的/y'
A) X9:;数Ý<是组织¼½Uî的=7à>。
$) X9:;?@A5¨ýþ0误™BC的°±。
) X9:;š议2˜¿(‘议ì¿$项目DM的绩效。
*)EFX9:;š]项目成e¿1^o+的cd‘<GH。
9.?o# should change management e planned for' A) hanges are generall" not predictale,therefore planning for change management cannot e
sensile.
$) Planning for change management should e done #hile the +arious change control processes
are eing applied.
) hange management can e planned in a set of management plans or a specific change
management plan.
*) hanges are a sign of ad planning . ;ne should a+oid changes during a project thus
eliminating the need to manage them.
/0qY˜ÞIÅÆ'
A) /0JK是ö¥L的,yMÂÆ/0qYgN。
$) rb£的/0Ë制¼½O2úK,?@7ÂÆ/0qY。
) /0qYöìPQ一„qYÅÆ!ÂÆ,RöìST进ÊÂÆ。
*) /0是ÂÆR+的信U,2˜P项目ÉÊ5避免/0,RnVW^qY¾们的6
7。
10.hich of the follo#ing documents is not used as input for product acceptance'
A) &he project scope statement,it descries the acceptance criteria.
$) &he project scope management plan,it descries the acceptance process.
) &he #or, rea,do#n structure ($S) ,it descries the deli+erales for acceptance.
*) &he @AI matrix,it descries accountallities in case of product rejection. ƒ„…个XY是îïÏÐ的ÇÈ'
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 4/42
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 5/42
A) 2º»×Ø的ab¼½组的¼½ŒN成,M;¶项目EF
$) 2Ì×项目的îïO®·N成
) 项目qYÅÆO项目(UVV
*) 9的/0ŽWOE
1 . Bou ha+e recentl" appointed a project manager to handle a critical prolect in "our organi<ation .Bou #ant to pro+ide the project manager #ith authorit" to appl" organi<ational
resources to project acti+ities.hich document should "ou use'
A) @esouree authori<ation document. $) or, rea,do#n structure.
) project charter . *) Project scope statement.
ã*指×^某个项目XY°ã组织的@A项目,ã#ê项目XY‚‘2ú组织U
Št项目DEe。ã2˜ùú…个XY'
A) UŠ€XY。 $) QRið;Z。 ) 项目z½。 *) 项目-.fg&。
1=.Bou are the project manager of a ne# project ,#hich #ill construct a ridge on the @i+er
Cile in %g"pt.$efore initiating the project,"ou should .
A) create a scope management plan to document ho# the project scope #ill e
defined,+erified and controlled
$) de+elop a project management plan
) determine specific acti+ities that need to e performed to produce the +arious project
deli+erales
*) facilitate the formal authori<ation to start a ne# project
ã是9项目的项目XY,P’Í“”e‘<O–—˜。P项目EÙÚ,ã2 ̃DD 。
A) ‘-.qYÅÆM'(项目的-.ÞIO×Ø、º»™Ë制
$) lÕ项目qYÅÆ
) Ì×™š的DEúMÉÊî`£的项目成À *)›Eˆ•€,E9项目
18 . As a project manager , project plan de+elopment is an important element of managing
projects. hich phase of the project management >ife c"cle does project plan de+elopment
elong to'
A) Initiation process. $) Planning process. ) %xecution process. *) ontrolling
process.
R]项目XY,项目ÅÆlÕ是qY项目œK17的à>,ƒ„…个项目qY`aTEF
S项目ÅÆ编制'
A)E¼½组。 $) ÂƼ½组。 ) Éʼ½组。 *) Ë制¼½组。
19.A customer informed "ou that it is preferale to change a certain aspect of the project .hat
should "ou do first'
A) &al, #ith team memers to understand implications of the change.
$) ommunicate the change to the management to get their inputs.
) ;pen up a change control.
*) *o si<ing for the change and communicate to the customer .
«¬`诉ã*+/0项目某个žŸ。ã¡2˜éwx'
A) ™cd成e¢£Yð$个/0的vw。
$) n$个/0™qY¯¤Jtu们的ÇÈ。
) lm/0Ë制。*) i,/0¥Š,™«¬进Ê¢£。
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 6/42
-0 . In "our project , "ou #ant to monitor and control project processes associated #ith
initiating, planning,executing and closing.&his #ill help "ou ta,e correcti+e or pre+enti+e
action to control project performance.In this context,#hat should "ou do first'
A) @e+ie# all project forecasts.
$) *etail all the acti+ities of project team memers in+ol+ed in executing administrati+e closurefor the project.
) @e+ie# the project management plan and #or, performance information for "our project.
*) 3anage project ris,s.
Pã的项目5,ã#„Ë项目E、ÂÆ、ÉÊ、cd¦¼½,$ò§¨ã>©ˆª«¬
¥¦ª«MË制项目绩效。P$%&'ƒ,ã¡2˜éwx'
A)回ab项目¥L。
$) PÉÊqYcdK®¯ab项目cd的DE。
)回项目qYÅÆ™项目的QR绩效信°。
*) qY项目ûü。
-1 . Bou recentl" joined as the project manager of A$ ompan" . &he outgoing project
manager mentioned that of late , she had een facing se+eral issues #ith ne# change
reuests.&he customers #ere located in the same office and the" interacted directl" #ith the
project team and,at times,informall" as,ed for some changes in the projects product.If the
changes #ere small,the project team memers usuall" agreed to do the changes .&he project
manager found it difficult to prioriti<e acti+ities and ensure that tas,s are done as per
schedule. &he project had 50 team memers and there #as some discontent amongst them
aout the #or, the" #ere supposed to do.hat should e "our first priorit" in this project'
A) reate a detailed project scope statement.
$) Align the project ojecti+es #ith the organi<ational goals. ) %nsure proper project scope control.
*) all a meeting of all the project sta,eholders to determine and resol+e an" outstanding
issues.
ã*±Èt A$²³é项目XY。ñò´µ的项目XY¿t,*Õ¶^·个9的/0
ŽW。«¬¸¨£¹的º²»,öì¼Ï™项目cd进Ê¢互,bKšœˆ•·¿(îï
的9/0。ÞÀ/0j½Š,项目cd成eJK£®$ë/0。项目XYÕ)$¹opÌ
×DE的¾¡¿,ÌÄ每个进度Ñ的±~ON成。$个项目b 50 个cd成e,bë#À
Á的QR。ã¡2˜éwx'
A) ‘®¯的项目-.fg&。
$) ù项目目¤™组织目¤一Â。
) ÌÄ‚’的项目-.Ë制。
*)Ãlab2Vš议MÌ×™ðø*gÒ的s题。
--.In a recent jo inter+ie# ,"ou #ere as,ed to define the most important characteristic of a
project manager .hich of the follo#ing #ill e "our est ans#er'
A) Suject matter expert. $) Integrator . ) reati+e person. *) @is, minimi<er .
*Ÿ试QR,ãO7W×Ø项目XY*17的fÄ,ƒ„…个是ã*+的ÅÆ'
A) Ê5ÇÈ。 $)É‚‹。 ) 造‹。 *) ûüÊ估‹。
-2.hich of the follo#ing is not a project management ,no#ledge area'
A) Project integration management. $) Project procurement management. ) Project configuration management. *) Project communications management.
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 7/42
ƒ„…项是项目qYËýÌÍ'
A) 项目ÉšqY。 $) 项目>?qY。 ) 项目ÎÏqY。 *) 项目¤JqY。
-4.hen deciding #hich project to select. .
A) select the project #ith higher life c"cle cost $) select the project #ith lo#er life c"cle cost
) select the project #ith higher sun, cost *) select the project #ith lo#er sun, cost røÐÑÒ项目K, 。
A)ÑÒ$`aT成本的项目 $)ÑÒÊ`aT成本的项目
)ÑÒ™b$Ó‰成本的项目 *)ÑÒ™bÊÓ‰成本的项目
-5.hile doing ualit" inspection,fe# defects #ere identified in the product.After rectif"ing
the defects,the repaired items #ere reinspected and accepted .Suseuentl",a notification
#as issued,#hich can also e referred to as .
A) +alidated defect repair $) product acceptance ) ualit" audit *) appro+ed change
reuest
rR¡©ªK,îï的少数BCOýþ。PÔå$ëBCõ,Ôå项O19©ª™ÏÐ。
Põ,一个JËOÕ¶,$个JËOÕ] 。
A)BCÔåÌ认 $) îïÏÐ ) ¡ÖÅ *)×_的/0ŽW
- . Project integration management includes the proeesses and acti+ities needed to
identif" , define , comine , unif" and coordinate the +arious processes and project
management acti+ities.Eor successful project integration management, "ou should definitel"
ha+e (select the est option) .
A) a strong matrix organi<ational structure in "our compan"
$) a good communication management *lan
) good project selection techniues
*) positi+e sta,eholders #ho support the project项目ÉšqYS一ë¼½™DE,úMýþ、×Ø、É‚、ØÙ£¼½™项目qYDE。
]^成Ú·N成项目ÉšqY,ã2˜™= (ÑÒ*+的Ñ项) 。
A)Û[\组织;Z $)Ü+的¤JqYÅÆ )Ü+的项目ÑÒ*+ *) ˆŸÝ†项
目的2V
-= . Bou ha+e een gi+en a high priorit" tas, that needs to e completed #ithin a short time
frame.Since "ou ,no# #hat has to e done."ou assign tas,s to the different team memers
and tell them #hen and ho# the tas,s should e done . &he management st"le that "ou are
follo#ing is .
A) directing $) laisse< faire ) delegating *) tas,Foriented
ã刚Ž$¾¡¿的±~,67PoÞ的KLbN成。y]ãËßwx67ON成,ãi
α~ê£的cd成e,`诉u们wxK_、ÞIN成±~。$%qYûÃ是 的。
A) 指àá $)À由• )âãá *)Ÿ~±~
-8.As a project manager ,"ou ad+ocate acti+e participation of "our teaill memers O this is
ecause "ou elie+e in .
A) theor" B (3c!regor model) $) theor" G (3c!regor model)
) 3aslo#s hierarch" of needs *) referent po#er
R]项目XY,ãä望ã的cd成eåæçè,$是y]ã相信
A) B Y7 (éêÃë模á) $) G Y7 (éêÃë模á) )ìí6Wf *)
ç考J-9.ost *erformance measurement is $%S& done through #hich of the follo#ing'
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 8/42
A) As,ing for a percent complete from each team memer and reporting that in the monthl"
progress report.
$) alculating earned +alue and using the indexes and other calculations to report past
performance and forecast future performance.
) :sing the 5050 rule and ma,ing sure the life c"cle cost is less than the project cost. *) Eocusing on the amount expended last month and #hat #ill e expended the follo#ing
month.
成本绩效衡¡*+J¼ƒ„…项M»)'
A) s每个成e进度N成的hijÎP月度[`5[`。
$) Åx%,ùú指数™tuÅx;ÀM[`项目¼‘的绩效™#DM绩效的¥L。
) ùú 5050 Âá,ÌÄ`aT成本少¨项目成本。
*)A5Pe个月的ïð™ƒ个月òïðH少e。
20 . &he $S , estimates for each #or, pac,age , and the net#or, diagram are
completed.hich of the follo#ing #ould e the C%G& thing for the project manager to do'
A) Seuence the acti+ities.
$) erif" that the" ha+e the correct scope.
) reate a preliminar" schedule and get the teams appro+al.
*) omplete ris, management.
$S每个QRS的估x™ñòóôŒXN成。σM项目XY2˜éwx'
A) DEõö。 $) ©ª-.是÷ˆÌ。
) ‘â%的进度ÑÎŽcd成e认ö。 *) N成ûüqY。
21 . A project management plan should e realistic in order to e used to manage the
project.hich of the follo#ing is the $%S& method to achie+e a realistic project management
plan'A) Sponsor creates the project management plan ased on input from the projcot manager .
$) Eunctional manager creates the project management plan ased on input from the project
manager .
) Project manager creates the project management plan ased on input from senior
management.
*) Project manager creates the project management plan ased on input from the team.
项目qYÅÆ?@Á‚»øk!MqY项目。ƒ„…项是*+的žèMŽù»öÊ的项
目qYÅÆ'
A) (UVú¨项目XY的ÇÈ‘项目qYÅÆ。
$)µ÷XYú¨项目XY的ÇÈ‘项目qYÅÆ。
) 项目XYú¨UûqY¯的ÇÈ‘项目qYÅÆ。
*) 项目XYú¨cd的ÇÈ‘项目qYÅÆ。
2-.*uring project execution,the customer authori<es and funds a scope change #hich
reuires a major change in the schedule.&he aseline schedule .
A) no# ecomes the ne# schedule , including the changes , and the original aseline is
disregarded
$) is still the original aseline ut annotated to refleet that a change has ta,en place
) is amended to reflect the scope change, ut the original aseline is still maintained for postO
project re+ie# *) is meaningless since e+er" schedule update changes the aseline
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 9/42
P项目Éʼ½5,ú¬€/0-.ÎÙÉ^Uü,由MýM^项目进度的¥的/0。
á项目进度ú_ ,
A) /]9的进度Ñ,S^/0,/进度ú_þ’ú
$)ÿ然是/进度ú_,但7ê(ä,ì反映ŒXÕ`的/0
) 67ÙÉì反映-./0,但/进度ú_ÿ2维护ì=项目õÖª *) ‰b±I®Ø,y]每一œ进度的09ôš—/进度ú_
22.All technical #or, is completed on the project.hich of the follo#ing remains to e done'
A) erif" scope. $) @is, response plan. ) Staffing management plan. *) >essons
learned
项目ab*+QRôN成^,σMéwx'
A) º»-.。 $) ÂÆûü2#。 )µeqYÅÆ。 *) X9:;
24 . 3ajor difficulties arise #hen multiple projects need to e managed in the functional
organi<ational structure ecause of .
A) the le+el of authorit" of the project manager
$) conflicts o+er the relati+e priorities of different projects in competition for limited resources
) project team memers #ho are focused on their functional specialt" rather than on the project
*) the need for the project manager to >lSe interpersonal s,ills to resol+e conflicts informall"
rH个项目67Pµ÷á组织;Z5进ÊqY的K_,š()o¥的困p,y] DD 。
A) 项目XY的‚b‚
$) £的项目P竞争b‚的UŠ¼½5šÕ`冲突
) 项目Š组成e0@äµ÷l门的本µQR!是è项目b@的QR
*) 67项目XYˆú个V¢ø÷Jœˆ•·ðø冲突
25.hich of the follo#ing is included in a project charter'
A) Identification of ris,s. $) or, pac,age estimates. ) *etailed fesource estimates. *) &he usiness need for the project.
ƒ„…项S含P项目z½b'
A) ýþ的ûü。 $) QRS估x。 )®¯的U料估x。 *) 项目356W。
2.Bou ha+e een #or,ing on a +er" large soft#are de+elopment project that has made use of
o+er -20 people.Einall",all the scope of #or, is completed,it #ould e $%S& to .
A) thro# a part" for the team memers $) ma,e sure the project is integrated #ith other
projects
) egin to focus on "our other projects *) anal"<e project S:%SS or failure
ãçè^一个œK¥á的!"lÕ项目,˜项目涉Í超¼ -20 V。*õ,QR-.5的a
bQRôN成^,$K*+2 ̃ 。
A) ]项目组成el个ã# $) Ì认Oƒ$个项目是£tu项目A成P一起的
) lm@äã的tu项目 *) i,项目的成Úè失败
2=.&he project is not completed until .
A) the project scope is completed.administrati+e closure is completed and pa"ment is recei+ed
$) formal acceptance is recei+ed。and an" other reuirenlents for project closure as stated in the
contract are met
) the customer is satisfied and final pa"ment is recei+ed
*) lessons learned are completed
项目还‰bN成,¼t 。 A) 项目-.N成,qYcdRN成,Ý付的ðúŒct
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 10/42
$)ŒOˆ•ÏÐ,‚£5tu项目cd的6WôŒXO足
) «¬®,*终的ðúŒXct
*) X9:;ON成
28.A1l of the follo#ing #ould occur during the closure of the project %G%P& .
A) creating lessons learned $) formal acceptance ) reducing resource spending *) performing enefit cost anal"sis
ƒ„ô是项目cdKÕ`的,W^ 。
A) ‘X9:; $) ˆ•ÏÐ )减少UŠùú *) ÉÊc益成本i,
29.An output of close project is the creation of .
A) project archi+es $) a prolect charter ) a project management plan *) a ris, anal"sis
plan
cd项目的Ç(Ù一是 。
A) 项目YÆ $) 项目z½ ) 项目qYÅÆ *) ûüi,ÅÆ
40 .A project manager has just een assigned to a ne# project and has een gi+en the project
charter .&he EI@S& thing the project manager must do is .
A) create a project scope statement
$) confirm that all the sta,eholders ha+e had input into the scope
) anal"<e project ris,
*) egin #or, on a project management plan
项目XY刚刚OiÎt9项目Ît^项目z½,σM项目XY¡2˜ 。
A) ‘项目-.fg& $) Ì认ab2V¿1ÇÈt-.
) i,项目ûü *) lm编制项目qYÅÆ
41.A project manager is managing a fixed price (EP) contract.She thin,s that a large customerF
reuested change might impact the schedule of the project.hat should she do EI@S&' A) 3eet #ith the sta,eholders.
$) 3eet #ith the team.
) @enegotiate the remainder of the contract.
*) Eollo# the change control s"stem.
项目XYPqY一个固×价£,她认]«¬o¥的/0ŽWòvwt项目进度。她
¡2˜éwx'
A) š见2V。 $) š见cd成e。 ) n09的‚£19谈判。 *)遵循/0Ë制–。
4-.&he client demands changes to the product specification that #ill add onl" t#o #ee,s to the
critical path.hich of the follo#ing is the est thing for the project manager to do'
A) ompress the schedule to reco+er the t#o #ee,s.
$) ut scope to reco+er the t#o #ee,s.
) 0nsuIt #ith the sponsor efore ta,ing an" action.
*) Ad+ise the client of the impact of the change.
«¬¿(#îï的/0,$ò±!"t@ABCe。ƒ„…项是项目XY*2˜é的'
A)#$进度 -"。
$)%减项目-.M减少 -"。
) P>±IÊEÙÚ~(UVÄW®见。
*) `诉«¬$个/0的vw。
42.A project manager learns that correcti+e action #as implemented " a team memer , ut notdocumented.hat should the project manager do C%G&'
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 11/42
A) @eport the +iolation to the functional manager .
$) larif" the reasoning ehind the team memers action.
) Add the implemented correcti+e action to the historical record.
*) Eind out #ho caused the prolem.
项目XYÕ)项目cd»«的©ˆÊE‰bO'(。项目XY¡2˜éwx'A) [`$个&反&'êµ÷XY。
$)'(cd成e>$个ÊE)õ的/y。
)*±»«的©ˆÊEt+,'(e。
*) ª(-引Õ的$个s题。
44.Bou are assigned as the project manager in the middle of the project.&he project is #ithin
the aselines, ut the custoiner is not happ" #ith the performance of the project.hat is the
EI@S& thing "ou should do'
A) *iscuss it #ith the project team. $) @ecalculate aselines.
) @enegotiate the contract. *) 3eet #ith the customer .
ãOiÎt某个ÉÊt5T的项目e。项目Á‚ú_,ö是«¬#项目的绩效。ã
¡2˜éwx'
A) ™cd成e67M-。 $)19Åxú_。
)19谈判‚£。 *) š见«¬。
45 . &he pre+ious proiect manager for "our project managed it #ithout much project
organi<ation . &here is a lac, of management control and no clearl" defined project
deli+erales.hich of the follo#ing #ould e the $%S& choice for getting "our project etter
organi<ed'
A) Adopt a life c"cle approach to the project. $) *e+elop lessons learned for each
phase. ) *e+elop specific #or, plans for each #or, pac,age . *) *e+elop a description of the
product ol the projectH
ã项目的Ú±项目XYP‰bFH项目组织的&'ƒqY项目。B.qYË制,‰bgÌ
×Ø的项目成À。ƒ„…项是ùã项目t0+组织的*/ÑÒ'
A) ]项目ÑÒ‚’的项目`aT。 $) ]每个EF_=X9:;。
) ]每个QRS_=f×的QRÅÆ。 *) ]项目îï编写¸¹。
4 . ompan" procedures reuire the creation of a lessons learned document . hich of the
follo#ing is the $%S& use of lessons learned'
A) fiistorical records for future projects.
$) Planning record for the current project.
) Informing the team aout #hat the project manager has done.
*) Informing the team aout the project management plan.
²³£½7W‘X9:;X0。ƒ„…项*+·¸¹^X9:;的Rú'
A) R]+,'(ú¨DM的项目。
$) R])P项目的ÂÆ'(。
) ê成e¿1信°fg项目XYéwx^。
*) ê成e¿1信°fg项目qYÅÆ。
4=.&he project manager has just recei+ed a change from the customer that does not affect the
projeet schedule and is eas" to complete.hat should the project manager do EI@S&' A) 3a,e the change happen as soon as posstie.
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 12/42
$) ontact the projeet sponsor for permissionH
) !o to the change control oard.
*) %+aluate the other components of the1triple constraint2.
项目XY刚ÏtMÀ«¬的/0,$òšvw项目进度Î34‹N成。项目XY2˜
¡éwx' A)尽56/0Õ`。 $)7项目Õ起VŽ8ö。
)‘/0Ë制âeš。 *) ÿ估²³´µ¶/的tuy>。
48 .A project manager recentl" re#arded an indi+idual #ith a promotion that carried #ith it a
+er" small salar" increase ut sustantiall" more responsiilit" .&he project manager appears
to e appealing to the emplo"ees need.
A) monetar" $) ph"siological ) csteem *) self actuali<ation
一个项目XY*“”Î9:^一个;e,<bœKŠ的QU±¡,但是=i·>?^
0H°±。项目XYçe‘@A足;e的 67。
A)üB $)`Y )C1 *)ÀD»)
49 All of the follo#ing are parts of direct and manage project execution except .
A) identif"ing changes $) using a #or, rea,do#n structure
) implementing correcti+e actions *) setting up a project control s"stem
ƒ„abô是指àèqY项目Éʼ½的一li,W^ 。
A) ýþ/0 $) ùú $S ) »«©ˆª« *) <Ï项目Ë制–
50.&he project charter for a project #as appro+ed for planning and "ou ha+e just een assigned
as project manager . @eali<ing that project planning is an ongoing effort throughout the
project,#hich processes are "ou 3;S& li,el" to comine'
A) reate $S and acti+it" definition.
$) Acti+it" duration estimating and schedule de+elopment. ) ?uman resource planning and cost estimating.
*) ost estimating and cost udgeting.
项目z½ŒXO×_,ã刚OiÎ]项目XY。认ýt项目ÂÆ67EF项目的†‡GJ,
…ë¼½ã*ö÷‚Î'
A) ‘ $S ™DE×Ø。 $) DE+K估x™编制进度Ñ。
) VJUŠÂÆ™成本估x。 *) 成本估x™成本¥x。
51.Bou are ta,ing o+er a project and determine the follo#ing vActi+it" $ has an earl" finish
(%E) of da" 2 ,a late finish (>E) of da" ,and an earl" start (%S) of da" - .Actl+it+ > is
eing done " a hard O toOget resource .&he cost performance index (PI) is 1.1 and the
schedule performance index (SPI) is 0.8.$ased on this information,#hat #ould "ou e more
concerned aout'
A) E10at. $) @esources. ) ost. *) Schedule.
ãP°某个项目,çtÞƒ信°vDE $ *早;¶HT是› 2I,*J;¶HT是›
I,*早lmHT是› -I。DE >,œKptUŠ。成本绩效指数 PI 是 1.1,进度绩效
指数 SPI 是 0.8。ú¨e¹信°,ã67#…랟0H@ä'
A) KK。 $) UŠ。 ) 成本。 *) 进度。
5-.If PI is 1.02 and A is 7000,ho# much is %'
A) =7000. $) 7180. ) =7-00. *) -00.
ÞÀ PIÛ1.02,AÛ000,% 是H少' A) =000。 $) 180。 ) =-00。 *) -00。
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 13/42
52.hat does cost performance index (PI) less than 1.0 indicate'
A) ost o+errun of the estimates. $) ost according to the estimatesH
) ost underrun of the estimates. *) %arl" progress.
成本绩效指数 (PI)Š¨ 1 ®LQwx'
A) 成本超Ý。 $) 成本Á‚估x。 ) 成本Mµ。 *) P进度早T。54.hich of the follo#ing is not an example of constraints that can limit flexiilit" in the human
resource planning process'
A) ;rgani<ational structure. $) ollecti+e argaining agreements.
) %conomic conditions. *) Acti+it" resource reuirements.
ƒ„…项是vwVJUŠÂƼ½N)的制µy>的OP'
A)组织;Z。 $) IUQž谈判Ø议。 ) XmR"。 *) DEUŠ6W。
55.hich of the follo#ing estalishes ualit" metrics'
A) ualit" assuranceSualit" control. $) ualit" planning.
) ualit" aseline. *) ualit" chec,list.
ƒ„…项úM‘í¡指¤'
A) ¡Ä证™¡Ë制。 $) ¡ÂÆ。 ) ¡ú_。 *) ¡©ªS。
5.h" is it important to ha+e a project charter'
A) It is the collection of all susidiar" project documents.
$) &he project charter is the necessar" asis for all #or, pac,ages to e performed.
) It formall" authori<es the proiect.
*) It trac,s the progress of the project.
]wx项目z½o17'
A) y]cA^项目ab的T=XY。 $) 项目z½是ab7ÉÊ的QRS?7的úU。
) y]¾ˆ•€^项目。 *) y]¾VW项目的进度。5= . hich of the follo#ing are the most commonl" used performance measures of e+aluating
#hether or not #or, is eing accomplished as planned at an" gi+en point of time'
A) PSA. $) A,%+JP+. ) SS. *) SPI,%SA.
ƒ„…项KúM衡¡项目的QR是÷Pf×KLgX/ÅÆN成'
A) P ™ A。 $) A,% ™ P。 ) ™ S。 *) SPI,% ™ A。
58.If SÛO800,PÛ=7000,ho# much is %'
A) 87000. $) 7-00. ) 97000 *) 7000。
ÞÀ SÛO800,PÛ=000,% 是H少'
A) 8000。 $) -00。 ) 9000。 *) 000。
59.As per P3$;K ,+arious executing processes fall into spedfic ,no#ledge areas.*e+elop
project teamis a part of #hich of the follo#ing ,no#ledge areas'
A) Project management integration. $) Project procurement management.
) Project human resource management. *) Project communications management.
YÝ P3$;K ,£的Éʼ½Z¨£的ËýÌÍ。cd‘<Z¨…个ËýÌÍ'
A) 项目ÉšqY。 $) 项目>?qY。 ) 项目VJUŠqY。 *) 项目¤JqY。
0.hat does estimate at complete mean'
A) %ach anticipated cost for project. $) %stimated a+erage cost at project completion.
) Anticipated total cost at project completion . *) Anticipated expenses at project
completion. NQ估x®LQ'
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 14/42
A) 项目的每个¥T成本。 $) 项目NQK估x的[\成本。
) 项目NQK的¥T:成本。 *) 项目NQK的¥TlÝ。
1.hich of the follo#ing indicates the acceptale range of +ariation of a process as represented
on the control chart'
A) 3ean. $) Specification limit. ) @ule of se+en. *) :pper and lo#er controllimits.
ƒ„…项指(^PË制ó5¼½/¡的öÏÐ-.'
A)[\Ü。 $) ÂÂ制。 )]gÂá。 *) Ë制e‚™ƒ‚。
- . hich of the follo#ing is the most common non eha+ioral reason for projects eing
completed ehind schedule and going o+er udget'
A) Selecting a #rong person as the project manager . $) Selecting a #rong person as the
sponsor .
) Accepting a high ris, project. *) Inadeuatel" defined reuirements.
ƒ„…项是*K见的àÂ项目进度^õ、成本超Ý的œÊ]/y'
A)ÑÒ^0误的Vr项目XY。 $)ÑÒ^0误的VrÕ起V。
) ÏÐ^$ûü的项目。 *) ’r的6W×Ø。
2.Bou are in the close project process.Bou are engaged in the acti+it" to settle and close some
contract agreements estalished for the project.hich of the follo#ing acti+ities are "ou into'
A) Administrati+e closure. $) ontract closure. ) Project executing. *) Planning.
ãPcd项目¼½。ãP进ÊëDEMN成项目5的一ë‚£Ø议。ƒ„…个DE是ãˆP
进Ê的'
A) qYcd。 $) ‚£cd。 ) 项目ÉÊ。 *) ÂÆ。
4.In an oject diagram,the name of an oject is .
A) in old $) in italics ) underlined *) none of these P#_ó5,#_的`a 。
A) úbšÑÓ $) úcšaÑÓ ) úƒdeÑÓ *) ìeô#
5.As per P3$;K ,all are parts of the executing process group except .
A) acuire project team $) de+elop project team ) information distriution *) identif"
sta,eholder
YÝ P3$;K ,ƒ„¼½ô是Éʼ½组的li,W^ 。
A)组‘项目cd $) ‘<cd )信°Õ¶ *) ýþ项目2V
.&he close project process is a part of #hich of the follo#ing project management ,no#ledge
areas'
A) project scope management. $) project integration management.
) project time management. *) project communication management.
项目cd¼½是ƒ„…个项目qYËýÌÍ的li'
A) 项目-.qY。 $) 项目ÉšqY。 ) 项目KLqY。 *) 项目¤JqY。
=.hile e+aluating the !antt chart,the project manager determines that the project is ehind
schedule.hat should she do'
A) ;tain appro+al from the customer to slip the project $) @eport findings to
management.
) %+aluate the alternati+es #ith the team. *) %+aluate the alternati+es #ith the
customer . rÿ估ffóK,项目XYÕ)项目^õ¨进度,她2˜éwx'
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 15/42
A) Ž«¬的×_‘±g项目。 $) ~qY¯[`Õ)。
) ™cd成eÿ估öÑžÆ。 *) ™«¬ÿ估öÑžÆ。
8.hich of the follo#ing is not used in the ualit" control process'
A) !antt charts. $) ontrol charts. ) Pareto charts. *) Statistical sampling.
ƒ„…项Oú¨¡Ë制¼½' A)ffó。 $) Ë制ó。 )hijó。 *) –Åk¹。
9.hich of the follo#ing $%S& descries a project management plan'
A) A print ;ut from project management soft#are.
$) A ar chart.
) @is, management,staffing, process impro+ement and other management plans.
*) &he project scope.
ƒ„…项*+·¸¹^项目qYÅÆ'
A) 项目qY!"的lmÇ(。 $)nßó。
) ûüqY、µe、¼½—进™tuqYÅÆ。 *) 项目-.fg&。
=0.Bou are a ne# project manager #ho has ne+er managed a project efore .Bou ha+e een
as,ed to plan a ne# project.It #ould e $%S& in this situation to rel" on during planning in
order to impro+e "our chance of success.
A) "our intuition and training $) sta,eholder anal"sis
) historical information *) configuration management
ã是个9的项目XY,ÚkDqY¼项目。ãO7WÂÆ9的项目。P$%&'ƒ,ã*
+op M¿$ã成Ú的rq。
A) ã的¼r™st $)2Vi, )+,信° *)ÎÏqY
=1.A particular sta,eholder has a reputation for ma,ing man" changes on projects .hat is the
$%S& approach a project manager can ta,e at the eginning of the project to manage thissituation'
A) Sa+no/to the sta,eholder a fe# times to dissuade him from sumitting more changes.
$) !et the sta,eholder in+ol+ed in the project as earl" as possile.
) &al, &o the sta,eholders oss to find #a"s to direct the sta,eholders acti+ities to another
project.
*) As, that the sta,eholder not e included in the sta,eholder listing.
某个项目2VKKP项目e¿(/0。ƒ„…项是项目XYöìP项目lmK>ú的q
YM&´的*+žè'
A) ~$个2Vf,uvu¿(0H/0。
$)尽早6项目2Vçèt项目5。
) 82V•€¢£,8(žè62V‘tu项目。
*)ŽWò2Vk2V(S5wW。
=-.@euirements documentation is an input to .
A) scope control and scope +erification
$) direct and manage project execution and integrated change control
) de+elop project management plan and de+elop project charter
*) de+elop project management plan and schedule de+elopment
6WX"是 的ÇÈ。
A) -.Ë制™º»-. $) 指àèqY项目Éʙɚ/0Ë制 ) 制x项目qYÅÆ™制R项目z½ *) 制x项目qYÅÆ™编制项目进度Ñ
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 16/42
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 17/42
in'
A) Planning. $) %xecuting. ) 3onitoring and controlling. *) losing.
项目XY7Ì认项目的îïŒXYÝ项目qYÅÆON成。项目XYP…个项目qY¼½
5'
A) ÂÆ。 $) ÉÊ。 )„Ë。 *)cd。80 .A project manager does not ha+e much time to spend planning efore the mandator" start
date arri+es.?e therefore #ants to mo+e through planning as effecti+el" as possile .hich
of the follo#ing #ould "ou recommend'
A) 3a,e sure "ou ha+e a completed preminar" project scope statement and then start the
$S.
$) reate an acti+it" list efore creating a net#or, diagram.
) *ocument all the ,no#n ris,s efore "ou document the highOle+el assumptions.
*) Einali<e the ualit" management plan efore "ou determine ualit" metrics.
项目XYPÛ制lmHTtMÙÚ‰bFHKLöìú¨ÂÆ,uä望尽ö÷ùÂƼ½
/b效q。ãò›ƒ„…项'
A) ÌÄãN成â%-.fg&Îlm‘ $S。
$) P‘ñòóÙÚ‘DE„Ñ。
) Pã'(ƒ$¯œ的‚<ÙÚ'(ƒabŒË的ûü。
*) PãÌס指¤ÙÚÌ×项目¡qYÅÆ。
81 . &he $S and $S dictionar" are completed . &he project team has egun #or,ing on
identif"ing ris,s.&he sponsor contacts the project manager , reuesting that the responsiilit"
assignment matrix e issued.&he project has a udget of :.S.
610 , 000 and is ta,ing place in three countries using 14 human resources &here is little ris,
expected for the project and the project manager has managed man" projects similar to thisone.hat is the next thing to do'
A) :nderstand the experience of the sponsor o* similar projects.
$) reate an acti+it" list.
) 3a,e sure the project scope is defined.
*) omplete ris, managenlent and issue the responsiilit" assignment matrix
项目的 $S ™ $SaƒŒXN成。项目cdlmýþ项目ûü。项目(UV7项目X
Y,7WÕ¶µ°iÎ[\。$个项目¥x 100 000 ßà,P²个„ÈQR,ùú 14 个V
JUŠ。项目XYqY¼一ë|…的项目,M项目ûü½Š。σM2˜éwx'
A) Yð(UVP|…项目e的X9。 $) ‘DE„Ñ。
) Ì认项目-.O×Ø。 *) N成ûüqY,Õ¶µ°iÎ[\。
8- . &he high O le+el project schedule constraints ha+e just een determined . hat project
management process group are "ou in'
A) Initiating. $) Planning. ) %xecuting. *) 3onitoring and controlling.
r7的项目进度µ¶刚刚OÌ×。ã)PP…个项目qY¼½组'
A)E。 $) ÂÆ。 ) ÉÊ。 *)„Ë。
82.&he project sponsor has just pro+ided the project charter .hat is the C%G& thing to do'
A) $egin to complete #or, pac,ages. $) omplete scope +erification.
) Start integrated change control. *) Start to create managernent *lans.
项目(UV刚刚¿1项目z½,σM67éwx' A) lmN成QRS。 $) N成º»-.。 ) lmÉš/0Ë制。 *) lm‘qYÅ
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 18/42
Æ。
84.hich of the follo#ing is C;& an input to the initiating process group'
A) ompan" processes. $) &he compan" culture ) ?istorical $Ss. *) Project
scope statement.
ƒ„…项是E¼½组的ÇÈ'A)²³¼½。 $)²³Xh。 )+,$S。 *) 项目-.fg&。
85.&he person #ho should e in control of the project during project management planning is
the .
A) project manager $) team memer ) functional manager *) sponsor
P项目qYÂÆK?@iÎt†MË制项目的是 。
A) 项目XY $) cd成e )µ÷XY *) (UV
8.A detailed project schedule can e created onl" after creating the .
A) project udget $) #or, rea,do#n structure ) project management plan *)
detailed ris, assessment
®¯的项目进度<bP‘ Ùõ‡öìO‘。
A) 项目¥x $) QRið;Z ) 项目qYÅÆ *)®¯的ûüÿ估
8= . &he project team has just completed the initial project schedule and udget . &he C%G&
thing to do is .
A) egin ris, identification $) egin iterations
) determine communications reuirements *) create a ar (!antt) chart
项目cd刚刚N成*â的项目进度™¥x,ƒ一%67
A) lmûüýþ $) lm1å ) ÌפJ6W *) ‘nß (ff)ó
88.&he project charter is created in #hich project management process group'
A) %xecuting. $) Planning. ) losing. *) Initiating 项目z½是P…个项目qY¼½组‘的'
A) ÉÊ。 $) ÂÆ。 )cd。 *)E。
89 . Cear the end of "our last project , additional reuirements #ere demanded " a group of
sta,eholders #hen the" learned the" #ould e affected " "our projeet . &his ecame a
prolem ecause "ou had not included the time or cost in the project management plan for these
reuirements . hat is the $%S& thing "ou can do to pre+ent such a prolem on future
projects'
A) @e+ie# the $S dictionar" more thoroughl",loo,ing for incomplete descriptions.
$) @e+le# the project charter more thoroughl",examining the usiness case
) *o a more thorough jo of contract planning.
*) Pa" more attention to sta,eholder management.
ã°的项目5;¶^,一ë项目2VÕ),$个项目ò#u们造成一ëvw,]M
u们¿(^一ë:;的6W。$n()^s题,y]ãP项目qYÅÆ5ÎD]$ë:;
的6W考~成本¬进度žŸ的ÂÆ。]避免|…s题PDM的项目5þœ(),ã*2˜
éwx'
A) 0±ˆ‰Š¯·ÿÖ$Saƒ,ìª8tŒëNÉ的¸¹。
$) 0±ˆ‰Š¯·ÿÖ项目z½,쩪()5~‹Œ的·ž。
) 0±ˆ‰Š¯·é+‚£ÂÆQR。
*)ƒ0H的JŽP项目2VqYe。90.&he soft#are de+elopment project is not going #ell .&here are o+er 20 sta,eholders,and
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 19/42
no one can agree on the project ojecti+es .;ne sta,eholder elie+es the project can achie+e a
20 percent impro+ement #hile another elie+es a 50 percent impro+ement is possile . &he
project manager thin,s a 10 percent impro+ement is more realistic .hat is the $%S& course
of action'
A) 3o+e for#ard #ith the project and loo, for more information later to settle the issue. $) A+erage the numers and use that as an ojecti+e.
) Perform a feasiilit" anal"sis.
*) As, the sponsor to ma,e the final decision.
某个!"lÕ项目进\Î+。̃ 项目b 20 H个项目2V,¥È#项目目¤‰b成
一Â的çè。一个项目2V认]项目öìt 20L的—进效À,!;一个认]t
50L是ö÷的。项目XY‘认] 10L的—进效À相#Mf0±)»。Ÿ#$%&',*2
˜>的ÊE是'
A)’‡“Ú›进$个项目,”õþcA0H的信°ìðø$个s题。
$)x($ë数a的[\Ü,ÎìM]一个目¤。
) 进ÊöÊ)i,。
*)6项目(UVé*õ的ø×。
91 . hen chec,ing the calendar of a team memer to schedule a meeting , "ou see she has
scheduled a meeting #ith a ,e" sta,eholder that "ou #ere not informed of . &he $%S&
approach #ould e to .
A) a+oid mentioning it to the team memer ut continue to #atch her acti+ities
$) notif" "our oss aout the prolem
) address the concern #ith the team memers oss
*) address the concern #ith the team memer
ãˆlxõ一个š议,r©ª一个cd成e的H+K,ãÕ)她ŒXè一个@A项目2V¥x^一个š议,!ã#$一gÎË&。ã*2˜é的-&是 。
A)避免P$†成eŸÚ¿Í$"-,但是’‡„Ë她的DE
$)ƒ$个s题`诉êã的•€
)è$†成e的•€#}
*)è$†成e#}
9-.Bou are in the middle of a ne# product de+elopment for "our pulicl" traded compan" #hen
"ou disco+er that the pre+ious project manager made a :.S. 6270007000 pa"ment that #as not
appro+ed in accordance #ith "our compan" policies .>uc,il",the project cost performanee
index (PI) is 1.-.hat should "ou do'
A) ontact "our manager .
$) Put the pa"ment in an escro# account.
) $ur" the cost in the largest cost center a+ailale.
*) Ignore the pa"ment.
ãˆP]ãaP的²¢–‹²³5的9îïlÕ项目!—˜,$K,ãÕ)ìÚ的项目X
YÝ付^Oj$ 2 000 000 ßà的ðú,!$™ðúΉb遵循ã²³的šÐ。›ˆ的
是,项目的成本绩效指数 (PI) 是 1.-。MKã2˜œxé'
A)7òã的XY。
$) ò$™Ý(¨›²žÄqž¬5。
) ò$™Ý(Ÿtöú的*¥成本5¡。*)¢£$™Ý(。
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 20/42
92.%+en though "ou are a project manager in a pharmaceutical compan","ou ha+e #or,ed as a
scientist in the industr" for se+eral "ears .Bour suordinates loo, up to "ou for guidance and
ad+ice.&he po#er that "ou ha+e o+er "our suordinates is .
A) referent $) expert ) legitimate *) re#ard
ã)P是某个制¤²³的项目XY,MÚãŒXR]¥¦ÈPMÊ5QRH年。ã的ƒZC§ãÎŽã的‘议™指à。ãa¨b的J是 J。
A)ç考 $)ÇÈ ) ‚è *) “”
94 . &he follo#ing information is a+ailale aout a particular tas, in "our project plan veari"
start (%S) ,-5 da"s;late start (>S) ,20 da"s;earl" finish (%E) ,50 da"s;late finish (>E)
,55 da"s.$ased on this information,"ou can deduce that .
A) the project float is 5 da"s $) the project ma" get dela"ed
) the tas, is not on the critical path *) the tas, ls on the critical *ath
@¨ã项目ÅÆ5的某个DEbÞƒ信°v*早lm (%S) -5I;*Jlm (>S) 20I;
*早;¶ (%E) 50I;*J;¶ (>E) 55I。ú¨$ë信°,ãöìi,( .
A) 项目的KK是 5I $) 项目ö÷O©误
) $个±~P@ABCe *) $个±~P@ABCe
95.*uring acti+it" seuencing,"ou identif" and document interacti+it" dependencies.All the
tollo#ing are outputs from acti+it" seuencing process %G%P& .
A) project schedule net#or, diagrams $) acti+it" attriute updates ) reuested changes
*) milestone list
PDEõöTL,ãýþÎ'(DE的op@。ƒ„ª项ô是DEõö¼½的Ç(,W
^ 。
A) 项目进度ñòó $) DEZ)09 )ŽW的/0 *) ½«„Ñ
9.Bou are managing tooling for an aircraft part.Bour team memers tell "ou that the" found afe# defecti+e parts.hen "ou as,ed them the reasons for the defect ,the" mentioned that it
could ecause of se+eral reasons including the material used , the measurement
s"stem,inaccurate tolerances in the machine or other factors.&o help them to illustrate etter
ho# +arious factors might ha+e contriuted to the defect,"ou #ill .
A) use a control chart $) create a flo#ehart
) dra# a fishhone diagram *) dra# a Pareto chart
ãPqY¬®的±Q。ã的cd成e`诉ãu们Õ)少8BC。rã¯su们BC的/
yK,u们¿Íö÷boH/y,Sùú的°料、衡¡–、Ô®0误的4K¬tuy
>。]^§¨u们0+·fg…ë/yö÷引ÕBC,ã2˜ 。
A) ùúË制ó $) ‘£½ó )±制²³ó *)±制hijó
9=.Bou are managing a project in a foreign countr".#here "ou reali<e that "ou #ill ha+e to pa"
a fee to some go+ernment agencies to get "our #or, done.Bou should .
A) pa" the fee to the go+ernment agencies
$) refuse to Pa+ the fee ecause the" are ries and hence unethical
) instead of pa"ing the fee , "ou pro+ide small gifts to go+ernment officials to get their
support
*) ma,e a case for #h" fees should e paid to go+ernment agencies , and present it to "our
management
ãP;„qY某个项目,PŒã认ýtã67Ý付ðúêš´ÔZk!lmã的QR。ã2˜ 。
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 21/42
A)Ý付ðúêš´ÔZ
$)]^Ý付ðú,y]$是ʵ,是߶的
) Ý付ðú,·¸žÆ是¿1빺ꚴ»eìŽu们݆
*)写(M]wx7Ý付êš´ÔZðú,~ã的qY¯Z[
98 . Bou are the project manager responsile for de+eloping a soft#are application ased oncustomer reuirements. As the customer reuirements ,eep changing freuentl" ,#hat tool
can "ou use to conduct integrated change control of "our project'
A) Project selection methods. $) Additional planning.
) orrecti+e action. *) Project management information s"stem.
ã是项目XY,°ú¨«¬6WlÕ2ú!"。考~t«¬的6W¼½/0,ãò]ã
的项目PÉš/0Ë制5ùúwxQ™'
A) 项目ÑÒžè。 $) :;的ÂÆ。 )©ˆª«。 *) 项目qY信°–。
99.ost of ualit" is the total cost of all efforts to achie+e productser+ice ualit",and ineludes
all #or, to ensure conformance to reuirements . All of the follo#ing are costs that are
incurred %G%P& .
A) ost of poor ualit" $) opportunit" cost ) external failure ost *) appraisal ost
¡成本是ab»)îï}~¡aïð的成本,SabÌÄè6W一Â的QR。ƒ„
ô是¡成本,W^ 。
A)Ê¡成本 $) Ôš成本 ) ;l失败成本 *) ©ª成本
100.In "onr project,"ou use thede+elop project teamprocess to impro+e the competencies
and interaction of team memers to enhance project performance . &he outputs from this
process are .
A) project staff assignments $) team performance assessment
) staffing management plan *) project staff assigtmaents , staffing management plan,team performance assessment
Pã的项目5,ãùúcd‘</¼½M—进cd成e的÷J™互Eì¿$项目绩效。$
个¼½的Ç(是
A) 项目µeiÎ $) cd绩效衡¡
)µeqYÅÆ *) 项目µeiÎ,µeqYÅÆ,cd绩效衡¡
101.&he method of constructing a project schedule net#or, diagram that represents
acti+ities and connects then to sho# the all dependencies is ,no#n as .
A) precedence diagramming method $) acti+it" list
) arro# diagramming method *) schedule net#or, templates
÷¾\ÓabDE的op@。
A) P*3 (Úàó) $) DE„Ñ ) A*3 (¿eó) *) 进度ñò模€
10-.hich of the follo#ing acti+ities is not concerned #ith de+eloping the project charter'
A) Project justification. $) ollecting output of the planning processes.
) urrent understanding of the customers need. *) *ocumenting the usiness needs.
ƒ„…项DE™制×项目z½À@'
A) 项目7证。 $)cAÂƼ½组的Ç(。 ) Yð«¬的6W。 *)'(356W。
102.hich of the follo#ing is not a tool of the acti+it" definition process'
A) @olling #a+e planning. $) ontrol account. ) *ecomposition. *) &emplates.
ƒ„…项是DE×ؼ½5的Q™' A)ÁE•ÂÆ。 $) Ë制ž¬。 ) ið。 *) 模€。
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 22/42
104 . hat is the process for aggregating the estimated costs of indi+idual acti+ities or #or,
pac,ages to estalish a cost aseline ,no#n as'
A) ost assessment . $) *etermine udget . ) Plan contracting . *) ost
estimating.
ƒ„…个¼½ZA每个DE™QRS的估x成本M‘í成本ú_'A) 成本估Å。 $) 制×¥x。 ) ÂÆ‚£。 *) 成本估x。
105.;ut of the follo#ing definitions of a project sta,eholder ,#hich one do "ou thin, is most
appropriate'
A) An enterprise #hose emplo"ees are directl" in+ol+ed in doing the project #or, .
$) An entit+ #hose interest ma" e affected as a result of the project execution.
) An entit+ that performs acti+ities to accomplish ojecti+es.
*) ;ne #ho is responsile for managing the project.
ƒ„…个@¨项目2V的×Øã认]*Âr'
A) 某个85,teQ¼Ïçè项目的QR。 $) 某个个V¬组织,tÃ益šÐt项
目ÉÊ的vw。
) 某个个V¬组织,ÉÊN成项目a67的DE。 *)°qY项目的个V。
10.In #hich of the follo#ing organi<ational structures,do project managers ha+e high or total
authorit"'
A) Eunetional organi<ation. $) $alanced matrix organi<ation.
) 3atrix organi<ation. *) Projecti<ed organi<ation.
ƒ„…个组织;Z5,项目XYb*$的J'
A)µ÷á。 $)[衡[\。 )[\组织。 *) 项目á组织。
10=.hich of the follo#ing is not a toolStechniue of the de+elop project charter process'
A) %arned +alue method. $) Project selection methods. ) Project management information s"stem. *) Project management methodolog".
ƒ„…项是制×项目z½¼½的Q™™*+'
A) »)Üžè。 $) 项目ÑÒžè。 ) 项目qY信°–。 *) 项目qYžè7。
108.In #hich phase of the project life c"cle,are cost and staffing le+els high'
A) Intermediate stage. $) Einal stage. ) Pre intermediate stage. *) Initial stage.
P…个项目`aT的EF,成本™UŠÄÈ*$'
A)5LEF。 $) *终EF。 )5LÅÚEF。 *)EEF。
109.ho is responsile for completing the lessons learned documentation'
A) Project team. $) Sponsor . ) Project architect. *) Project manager .
-°N成X9:;XY'
A) 项目cd。 $) Õ起V。 ) 项目<ÅÆ。 *) 项目XY。
110.&o manage a project including .
A) identit" the reuest and ma,e sure the clarit" and achie+ale aim
$) alance the reuest of ualit",scope,time and fee
) ma,e the technolog" regulation explaination, plan and means e fit for different reuests and
expectation of all ,inds of sta,eholders
*) all of ao+e
qY一个项目S 。
A) ýþ7W™Ì×(Ç!È÷¾»)的目¤$)[衡¡、-.、KL™ðúžŸ的7W
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 23/42
) ù*+Â×fg&、ÅÆ™žè’‚¨ab2V的£6WèT望
*) ìeÉlÑ项
111.%xecuting processes are concerned #ith .
A) recogni<ing that a project or phase should egin
$) coordinating people and other resources to carr" ;:t the plan ) de+ising and maintaining a #or,ale method to accomplish the usiness need that the project
#as underta,en to address
*) ensuring that the project ojecti+es are met " monitoring and measuring progress and
ta,ing correcti+e action #hen necessar"
Éʼ½组 。
A) Ž项目¬项目EFE的认ö
$)ØÙVJ™tuUŠN成项目ÅÆ
) <Å™维†öùú的žèMt项目*âa¥T的356W
*)J¼„€èË制¼½ÌÄ项目目¤的»),?7K>©ˆÊE
11-.Eor an acti+it",the optimistic,most li,el" and pessimistic estimates are 1- ,1 and 18
respecti+el".hich of the follo#ing statement is correct'
A) &here is 8.-Lchance that the acti+it" #ill e completed in 15 to 1= da"s.
$) &here is 95.44Lchance that the acti+it" #ill e completed in 15 to 1= da"s.
) &here is 8.-Lchance that the acti+it" #i? e completed in 14.= to 1.= da"s.
*) &here is 92.=2Lchance that the acti+it" #ill e completed in 15 to 1= da"s.
某个DE,*ÊË的估x是 1-;*ö÷估x是 1;*ÌË估x是 18。ƒ„…个fè是ˆ
Ì的'
A) b 8.-L的rq,DEòP 15Í1=IÙbN成。
$) b 95.44L的rq,DEòP 15Í1=IÙbN成。 ) b 8.-L的rq,DEòP 14.=Í1.=IÙbN成。
*) b 92.=2L的rq,DEòP 15Í1=IÙbN成。
112.alculate the standard de+iation of a tas, if ;Û4,PÛ10,3Û.
A) 1. $) 12. ) -5. *) -2.
ÞÀ*ÌË估ÅÛ10,*ÊË估ÅÛ4,*ö÷估ÅÛ,Žs¤_K是'
A) 1。 $) 12。 ) -5。 *) -2。
114.Bou are ioo,ing at the follo#ing data.Project A has a PI of 0.8 and SPI of 1.- and % of
450 . Project $ has PI of 1.- and SPI of 0.8 and % of 50 . hich of the follo#ing
statement is true'
A) Project $ is performing etter ecause it has a higher earned +alue.
$) Project A has schedule slippage and project $ is ahead of schedule.
) rashing project A is a good option.
*) rashing project $ is a good option.
ãP烄数Ý。项目 A 的 PI 是 0.8,SPI 是 1.-,% 是 450;项目 $ 的 PI 是 1.-,SPI
是 0.8,% 是 50。ƒ„…个fè是ˆÌ的'
A) 项目 $ 5绩j½+,y]¾的 % j½$。
$) 项目 A 的进度^õ,项目 $ 进度¿Ú。
)ÎQ项目 A 是0的ÑÒ。
*)ÎQ项目 $ 是0的ÑÒ。115.hich of the follo#ing is C;& a method for progress reporting for #or, pac,ages'
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 24/42
A) Percent complete. $) East trac,ing. ) -080 rule. *) 5050 rule.
ƒ„…项是QRS[`进度K>ú的žè'
A) N成hij。 $)5gV进。 ) -080 Âá。 *) 5050 Âá。
11.Bou are the project manager of a large soft#are de+elopment project .&here is a conflict
et#een t#o module leads on #here the changes ha+e to e rnade.Bou inter+ene and tell themthe importance of getting the project on time and as, them to find a solution #hich is acceptale
to oth of thern.hich conflict resolution techniue are "ou using here'
A) onfronting. $) ompromising. ) Smoothing. *) Eorcing.
ã是个¥á!"lÕ项目的项目XY。!个模Ï组GÙLPwx·žé/0e()^冲突。
ãÐÈ`诉u们XKN成项目的17),7Wu们8(Qžô÷ÏÐ的žÆ。ãP$ù
ú的是…%冲突ðøžÆ' 。
A)Ÿ#。 $)ÑØ。 )Ù™。 *)Û制。
11=.$ased on the net present +alue (CP) .#hich project "ou #ill choose'&he CP of project
Av 6-57000, project $v 657000, project v 6407000, project *v 6257000.
A) Project A. $) Project $. ) Project . *) Projdct *.
ú¨ CP (Ò)Ü) ãšÑÒ…个项目'项目 A 的 CP 是 -5000 ßà;项目 $ 的 CP 是
5000 ßà;项目 的 CP 是 40000 ßà;项目 * 的 CP 是 25000 ßà。
A) 项目 A。 $) 项目 $。 ) 项目 。 *) 项目 *。
118.#hich of the follo#ing is the $%S& tool for sho#ing the team the project schedule status
during project execution'
A) 3ilestone chart. $) !antt chart. ) or, rea,do#n structure. *) Cet#or,
diagram.
ƒ„…个是P项目ÉÊTLúM\Ó项目进度{|的*+的Q™'
A) ½«ó。 $)ffó。 ) QRið;Z。 *)ñòó。l19 . An organi<ation structure that in+ol+es +arious organi<ational t"pes at +arious le+els is
called a .
A) strong matrix $) alanced organi<ation ) composite *) alanced matrix
一%P£¯Ÿe™b£的组织|á的组织;ZOÕ] 。
A)Û[\ $)[衡组织 ) å‚á *)[衡[\
1-0.ho has the highest cost ris, in ease of a fixed price contract'
A) $u"er . $) Seller . ) Sponsor . *) &eam.
P固×价£b-bQ*$的成本ûü'
A)Óž。 $)Ôž。 ) (UV。 *) cd。
1-1.Bou are in the de+elopment phase of a soft#are project and meeting the de+elopinent team
to collect the status.Bou #ant to sho# the team memers the actual dependencies of different
tas,s.hich scheduling tool "ou #ill e using to explain them (choose the est ans#er) '
A) 3ilestone chart. $) Elo# chart. ) Cet#or, diagram. *) !antt chart.
ãP!"项目的lÕEFš见lÕcdMcA项目{|。ã#~cd成e\Ó£±~Ù
L的ÕÖ@。…个进度Q™öìúPM¼½ (ÑÒ*+的ÅÆ) '
A) ½«ó。 $)£½ó。 )ñòó。 *)ffó。
1--.hich of the follo#ing is C;& an input to monitor and control project #or,'
A) Project management plan. $) %nterprise en+ironmental factors.
) hange reuests. *) Performance reports. ƒ„…项是„Ë项目QR的ÇÈ' .
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 25/42
A) 项目qYÅÆ。 $)-5jky>。 ) /0ŽW。 ) 绩效[`。
1-2.Bou are the project manager for soft#are de+elopment project .&he feasiilit" stud" can
start an" time and ta,es 1 #ee, and reuirement gathering ta,es - #ee,s #hich can start onl"
after feasiilit" stud" . &he design and test plan de+elopment can start in parallel after the
reuirements gathering . &est plan preparation ta,es 8 #ee,s follo#ed " a re+ie# " thecustomer and the time estimated for re+ie# is 1 #ee, .After the re+ie#,&est data preparation
ta,es #ee,s.*esign ta,es #ee,s and it is follo#ed " de+elopment and unit testing .for
one module it ta,es - #ee,s and for the other module it ta,es - #ee,s . &here are no
dependencies et#een modules and the" can e de+eloped simultaneousl" . After test data
preparation and de+elopment and unit testing of oth the modules , there is - #ee,s s"stem
testing.hat is duration of the critical path'
A) 14 #ee,s. $) 15 #ee,s. ) -0 #ee,s. *) 19 #ee,s.
ã是!"lÕ项目的项目XY。öÊ)×ØöP±IKLlm,67ïð 1";6WcA
?@PöÊ)×ØN成Ùõ进Ê,67ïð -"。<Å™L试ÅÆlÕöìP6WcAõ
΄进Ê。L试ÅÆ_=67ïð 8",σM是«¬ÿ估,«¬ÿ估¥Åïð 1"。ÿ
估Ùõ,L试数Ý_=67ïð "。<Åïð ",ÏQ是lÕ™SàL试,t5一个
模Ïïð -",一个模Ïïð -"。模ÏÙL‰bop@,öì£KlÕ。L试数Ý
_=™lÕ™SàL试Ùõ,b -"的–L试。项目@ABC的+K是H少'
A) 14"。 $) 15"。 ) -0"。 *) 19"。
1-4 . Bou are #or,ing on a soft#are de+elopment project and there is 0L proailit" that
de+elopment #ill e completed " the ptanned date and =0Lproailit" that testing #ill e
completed " the planned date .hat is the proailit" that de+elopment and testing #ill e
completed as per scheduleÙ
A) 5L. $) 4-L. ) L. *) 2L. ãQRP一个!"lÕ项目e,lÕQRb 0L的rqXÅÆHTN成;L试QRb
=0L的rqXÅÆHTN成。lÕ™L试QRôXyÅÆHTN成的rq是H少'
A) 5L。 $) 4-L。 ) L。 *) 2L.
1-5.hich of the follo#ing statements is C;& true'
A) Integration in+ol+es effecti+el" integrating processes among the project.
$) Integrated change control includes re+ie#ing and appro+ing all change reuests.
) &he project preliminar" scope statement pro+ides a high le+el scope narrati+e.
*) &he project management plan is an input in de+eloping the preliminar" project scope
statement.
ƒ„…个fè是ˆÌ的'
A)Ú‚Sb效·É‚项目ab¼½。 $)Éš/0Ë制Sÿ估、Ö×ab/0
ŽW。
) 项目â%-.fg&¿1½r7的-.fg。 *) 项目qYÅÆ是制×â%-.fg
&的ÇÈ。
1-.%stimate at completion (%A) is .
A) actual ost (A) Û udgeted cost ($) $) actual cost (A) Ûestimate to complete
(%&)
) udgeted cost ($) Oactual cost (A) *) actual cost (A) O planned +alue (P)
NQ估x是 DD 。 A) »ø成本 (A)Û¥x成本 ($) $) »ø成本 (A)ÛNQÜ6估x (%&)
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 26/42
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 27/42
in a metrics organi<ation'
A) :pdate the details in #or, product information and share that #ith functional manager .
$) :pdate the details in performance measurement aseline and share that #ith functional
manager .
) ?a+e an informal discussion #ith the team memer to find out the reason.*) Eormall" communicate the slippage from the team memer to the functional manager and
reuest him to discuss #ith the emplo"ee to ensure that this #ill not happen in the future.
P项目{|še,ãÕ)b个cd成e‰bN成u2˜P本"N成的±~。ãR]Pˆ•
的组织5的项目XY2˜>wxÊE'
A) 09®¯的±~îï信°Î¢àêµ÷XY。
$) 09®¯的绩效衡¡ú_΢àêµ÷XY。
) ™Œ个cd成e进Êœˆ•的67,8(áâ的/y。
*) ˆ•™qY˜cd成e的µ÷XY¢£,Žu™u的µe谈}ìÌÄDMþÕ`$
%&'。
124.@euest seller responses and select sellers is associated #ith #hich process group'
A) Planning. $) Procurement 3anagement. ) Initiating. *) %xecuting.
ŽÔžw2™ÑÒÔžZ¨…个¼½组'
A) ÂÆ。 $) >?qY。 )E。 *) ÉÊ。
125.In #hich t"pe of organi<ation is the project managers role most li,el" partOtime
A) Eunctional. $) ea, matrix. ) Strong matrix. *) A and $.
ƒ„…个组织;Z5项目XY*ö÷是ãµ的'
A)µ÷á。 $)ä[\。 )Û[\。 *) A ™ $。
l2.hich of the follo#ing is the est use of lessons learned'
A) Planning record for the current project . $) &o impress the senior management.
) Informing the team aout #hat mista,es team has made. *) ?istorieal information for
future projects.
ƒ„…项是X9:;的*+úå'
A) ])P的项目ÂÆ'(。 $) ê$¯qY‹æƒm_。
) `诉cd成eu们ç¼的0误。 *) ]DM的项目¿1+,信°
12=.Bou ha+e een assigned to manage a large enterprise resource planning (%@P) project in
"our organi<ation.Bou reali<e that detailed planning ,execution,and closing processes are
prereuisites for Success.&o support the project from initiation through closing "ou should use
.
A) a ma,eOor O u" anal"sis
$) lessons learned and other historical information from pre+ious projeets
) enefitOcost anal"sis
*) the project management information s"stem
ãOiÎMqY一个¥á的 %@P 项目。ã®ýt®¯的ÂÆ、ÉÊ、cd项目是项目成Ú
的¡øR"。]^݆项目kEtcd,ã2˜ùú 。
A) ——?Ó À制i, $) X9:;™ÙÚ项目的tu+,信°
)c益成本i, *) 项目qY信°–
128.hich of the follo#ing process is not part of project integration management' A) Integrated change control. $) Performance reporting
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 28/42
) lose project. *) *irect and manage project execution.
ƒ„…个¼½是项目ÉšqY的li'
A)Éš/0Ë制。 $) 绩效[`。 )cd项目。 *) 指àèqY项目ÉÊ。
129.A paint manufacturer authori<ing a project to estalish guidelines to handle toxic material is
an example of a project initiate ecause of . A) mar,et demand $) a customer reuest ) a leagal reuirement *) a technological
ad+ance
è料éÕ起项目M‘í#bêº的ëR指ì,$是y] !E项目的OP。
A)íî67 $) «¬67 ) èï7W *)*+—进
140.A project manager is at the project ,ic,FoffFmeeting .?e confidentl" states the +ision and
mission for the project.&his P3 is exhiiting leadership st"le.
A) hierarchical $) authoritarjan ) charismatic *) associati+e
项目XYˆP项目的Eše。uÀ信·¸¹Q项目的ðñ™ùa。$个项目XYP\Ó 。
A)¦¿ $)J )òJ *)7#
141 . Bou are the project manager of Alpha Cet#or, Inc . Bour compan" is doing net#or,
planning for a major an, .Bou are planning to digram the acti+it" dependancies using acti+it"
list.hich of the follo#ing is true'
A) P*3 is also the A;A diagramming method. $) P*3 is also the A;* digramming
method.
) P*3 is also A;C digramming method. *) P*3 is also A*3 diagramming method.
ã是 Alphañò²³的项目XY。ã们²³P]一个¥óÊôZñòÂÆ。ãÅÆùúñò
óMÑ)DE„Ñ5DE的op@。ƒ„…个fè是ˆÌ的'
A) P*3ÈOÕ] A;A±óè。 $) P*3ÈOÕ] A;*±óè。
) P*3ÈOÕ] A;C±óè。 *) P*3ÈOÕ] A*3±óè。14- . &as, A has the follo#ing details v ;ptimistic estimate Û 20 , pessimistic estimate Û
40 , most li,el+ estimate Û 25 . &as, $ has the follo#ing details v ;ptimistic estimate Û
2- , *essimistic estimate Û 2= , most li,el" estimate Û 24 . &as, has the fo1lo#ing
details v ;ptimistic estimate Û -5 , most li,el" estimate Û 25 , pessimistic estimate Û
45.hich tas, has the highest standard de+iation'
A) &as, A. $) &as, $. ) &as, . *) &as, AS&as, .
±~ A bÞƒ信°vÊË估xÛ20,ÌË估xÛ40,*ö÷估xÛ25;±~ $ bÞƒ信
°vÊË估xÛ2-,ÌË估xÛ2=,*ö÷估xÛ24;±~ bÞƒ信°vÊË估xÛ
-5,*ö÷估xÛ25,ÌË估xÛ45。…个±~b*$的¤_K'
A) ±~A。 $) ±~$。 ) ±~。 *) ±~A ™±~。
142.In case of conflicts of interest among sta,eholders,#hom should the project manager gi+e
priorit" to'
A) Project team. $) Project manager ta,es his o#n decision.
) Senior management. *) ustomer .
r项目2VÙLÕ`Ã益冲突K,项目XY2˜ƒ-的¾¡¿Žt*$'
A) 项目cd。 $) 项目XYÀÁø×。 )$¿qY¯。 *) «¬。
144.hich process group focuses on completing the reuirements of the projectÙ
A) Initiating. $) Planning. ) %xecuting. *) losing.
ƒ„…个¼½组@ä¨N成项目的6W' A)E。 $) ÂÆ。 ) ÉÊ。 *)cd。
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 29/42
145.ho is responsihle for ualit" management in the project'
A) Project leader . $) ualit" control department ) Project manager . *) &eam
memer .
-#项目的¡qY°'
A) 项目Ìà。 $) ¡Ë制l门。 ) 项目XY。 *) cd成e。14 . In "our soft#are de+elopment project "ou ha+e to #ait for 5 da"s after ordering a ne#
soft#are and then onl" "ou can start integration testing .&he 5 da"s in this case is an example of
.
A) lead $) lag ) dela" *) f1oat
Pã的!"lÕ项目5,ã67PÙÉ9!"Ùõ¦õ 5I‡÷lmÉšL试。$ 5I是
的OP。
A) ¿Ú $)öõ )©误 *) KK
14= . Bou are #or,ing on internal projects for a ig corporation . Bou are in to reuirement
definition for ne# claim s"stem that #ill enale emplo+ees claim their hours #or,ed on the
projects using their moile phones also.*ue to udget cuts it #as decided to cancel the project
and deplo" the people to commercial projects.hich of the follo#ing is true'
A) &he project ended due to integration ecause the resources #here distriuted to commercial
projects.
$) &he project ended due to star+ation ecause the funding #as cut.
) &he project ended due extinction ecause of the udget cut.
*) &he project ended due to integration ecause of udget cut.
ãQRP某个¥áic的bl项目e。ãO7W×Ø9的Z[–,$òù;eJ¼ùú
÷Eø}Z[u们P项目e的QRŠK数。由¨¥x#$,M项目OV,项目成eO
õt3~项目e。ƒ„…项是ˆÌ的' A) 项目的;¶ù¨É‚,y]UŠOõt35项目e。
$) 项目的;¶ù¨ú.,y]UüO$减。
) 项目的;¶ù¨ûv,y]¥xO$减。
*) 项目的;¶ù¨É‚,y]¥xO$减。
148.hich of the follo#ing statements is C;& true regarding arro# digramming method'
A) Schedu, acti+ities are represented " arro#s.
$) &he length of the arro# represents the expected duration of the acti+it"H
) &he tail of the arro# represents the start ot the acti+it"H
*) &he head of the arro# represents the finish of the acti+it".
ƒ„@¨ A*3 的fè…个是ˆÌ的'
A) 进度DEJ¼¿eÑ)。 $)¿e的G度š)DE的¥T+K。
)¿e的dü¸ÑDE的lm。 *)¿e的ýl¸ÑDE的;¶。
149.hich of the follo#ing statement is #rong'
A) >eading,communicating, Cegotiating, prolem sol+ing and the ailit" to influence the
organi<ation are considered ,e" s,ill for project managers to possessH
$) Project managers should ta,e into consideration and plan accordingl" for influences.
) Project management s,ills ha+e no relation to general management s,ills.
*) ;rgani<arions are increasingl" accountale for impacts resulting from project.
ƒ„…个fè是0误的' A)Ìà、¤J、谈判、s题ðø™vw组织的÷J是项目qY‹?=的@A*÷。
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 30/42
$) 项目XY?@考~ÅÆö÷ýM的vw。
) 项目qY‹的*÷™KÂqY*÷‰@。
*)组织#项目的vw°。
150 . &he follo#ing are the internal rate of return (I@@) for different projects . Project A v
5L, project $v-5L, project v20L, project *v9L.hich is the est project' A) Project A. $) Project $. ) Project . *) Project *.
£项目的blc益q (I@@) Þƒv项目 A ] 5L;项目 $ ] -5L;项目 ] 20L;项目
* ] 9L。*+的项目是…个'
A) 项目 A。 $) 项目 $。 ) 项目 。 *) 项目 *。
151.hich of the follo#ing is true regarding estimation'
A) P%@& is superior to P3.
$) P%@& estimates are etter than 3onte arlo simulation.
) P3 uses 2 estimates on a tas, (pessimistic,optimistic and most li,elB)
*) 3onte arlo simulation uses P%@& formula.
ƒ„…个@¨估x的fè是ˆÌ的'
A) P%@& j P3 0+。
$) P%@&估xjþfÿî模拟7+。
) P3 #一个±~ùú²个估x (*ÌË、*ÊË™*ö÷) 。
*)þfÿî模拟ùú P%@&²•。
15-.Bou ha+e to finish a project #ith in - #ee,s and "our lead de+eloper had to ta,e 1 #ee,
lea+e due to personal emergenc",Another project manager has agreed to loan the ser+ice of
his lead de+eloper for l #ee, .Bou are ta,ing his help and completing the project .&his case is
an example of (hoose the est ans#er) .
A) fast trac,ing $) crashing ) ris, management *) resource le+eling ãP!"bn7;¶项目,ã的席lÕ‹y]个V-~´l一"。一个项目XY£®
6u的席lÕ‹¼M§¨,ãÏÐ^$个§¨N成^项目。$是 的OP (ÑÒ*/
ÅÆ) 。
A)5gV进 $)ÎQ ) ûüqY *) UŠ[衡
152.A complex project #ill fit est in #hat t"pe of organi<ation'
A) Eunctional. $) rossFfunctional. ) 3atrix. *) $aIanced.
åæ的项目*+ùúƒ„…%组织;Z'
A)µ÷á。 $)跨l门。 )[\á。 *)[衡á。
154.hen the project cost is 6-7000 and the profit is 6500,#hat is the $@ for the project'
A) -7500. $) -5L. ) 4. *) not enough information to calculate
$@ .
项目成本是 -000 ßà,Ã润是 500 ßà,项目的 $@ 是H少'
A) -500。 $) -5L。 ) 4。 *) ‰b足¾的信°MÅx$@ 。
155.hich of the follo#ing is C;& an input to perform integrated change control'
A) Proiect management plan. $) @euested changes.
) Project scope statement. *) or, performance information.
ƒ„…项是Éš/0Ë制的ÇÈ'
A) 项目qYÅÆ。 $)ŽW的/0。 ) 项目-.fg&。 *) QR绩效信°。
15.hich ,no#ledge area does the de+elop project charter elong to' A) Initiating. $) Project scope management.
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 31/42
) Project integration management. *) Project communication management.
制×项目z½Z¨…个ËýÌÍ'
A)E。 $) 项目-.qY。 ) 项目ÉšqY。 *) 项目¤JqY。
15=.&he t"pe of contract #here the u"er incurs opportunit" cost ut little or no additional cost
ris, is called . A) fixedFprice #ith incenti+e $) firmFfixedFprice
) fixed price #ith economic price adjustment *) fixedFprice #ith right of rene#al
šàÂÓž的Ôš成本±!<boŠ的¬‰b:;的ûü成本的‚£Õ] ‚£。
A)固×价ñ“” $)固×价à )固×价ñXm价ÃÙÉ *)固×价ñ’
r09
158.hich t"pe of #arrant" is enacted if a ser+ice or product does not meet the le+el of ualit"
specified in the contract'
A) Implied #arrant" of merchantailit". $) Implied #arrant" of specified ualit".
) %xpress #arrant". *、 Cone of the ao+e.
ƒ„…%担Ä是针#}~¬îïÁ‚‚£5Â×的¡¯œ的'
A) 35bPÄ证。 $)fסbPÄ证。 )货ï¡Ä证。 *) ìeô是。
159.In "our soft#are de+elopment project "ou ha+e planned for s"stem testing from 3arch 1st
and the duration is 10 da"s.&#o da"s efore the completion of the s"stem test,"ou can start
the user acceptance test.&he - da"s in this case is an example of .
A) lead $) lag ) dela" *) float
Pã的!"lÕ项目5,ãÅÆ–L试QRk 2 月 1Hlm,+K 10I。PN成–
L试Ú -I,ãöìlmú¬ÏcL试。P$%&´ƒ,$ -I是 的OP。
A) ¿Ú $)öõ )©误 *) KK
10.Bou are #or,ing on a project for $right Idea Inc.and #or,ing on a project for a large retail an, . Bou ha+e alread" prepared the $S and got it signed off . $ecause of some ne#
go+ernment regulations,"ou need to add some more acti+ities to the $S .Bou ha+e got the
change reuests appro+ed through the $ . &he $S changes in turn reuire #hich of the
follo#ing'.
A) ost changes. $) Scope changes. ) Schedule re+isions. *) @is, response
change.
ãP $right Idea²³é一个¥á零售仓<的项目。ãŒX_=^ $S ÎŽ^签a。y]
9的š´èÂ,ã67±0HDEt $S。ãŒX拿tJ¼ $×_的/0ŽW。$S
/0oœñò引Õƒ„…个/0'
A) 成本/0。 $) -./0。 ) 进度Ôx。 *) ûü2#/0。
11 . ompan" A$ adopt "earFsummar" for decritiation of asset . &he" spent 61=7000
purchased one computer .It is eatimated that the computer can e sold #ith 6-7000 three "ears
later .&us,ho# much #ill e the asset decritiation of this computer in "ear three'
A) 657000. $) 647500. ) 6=7500. *) 6-7500.
A$²³JKú年™èMÅxUî的折旧。u们ï 1= 000 ßàÓ^一台ÅxÔ,估Ų年
õ÷Ô -000 ßà。Œx›²年的折旧是H少ßà'
A) 5000。 $) 4500。 ) =500。 *) -500。
1- . Bou do not expect the t"pes of +ariances that ha+e occurred on the project to date to
continue . If $A Û 200 , %& Û -=5 , P Û 200 , A Û -00 , % Û -50 and PI Û1.-5,#hat is the %A'
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 32/42
A) -40. $) -50. ) 4=5. *) 150.
ã认]t目Ú]v项目5()的偏KDMšþ()。ÞÀ $AÛ200,%&Û-=5,P
Û200,AÛ-00,%Û-50,PIÛ1.-5,á %A 是H少'
A) -40。 $) -50。 ) 4=5。 *) 150。
12 . Bou a"e a project manager to upgrade the computer safet" of "our organi<ation . Bour Project team is made up of four contractors and t#o full time emplo"ees .&his is the first time
the" ha+e all #or,ed together .Bou ,no# that the team #ill go through the stages of team
de+elopment in the follo#ing order v
A) Eorming , storming , norming , and performing . $)
Storming,norming,forming,and performing.
) Corming , storming , forming , and performing . *)
Eorming,norming,storming,and performing.
ã是个项目XY,ˆP09ã们组织的ÅxÔÉ–。ã的项目cdS 4 个承S3™
- 个ɵ;e。$是u们›一œ一起QR,ãËß$个cdòXyƒ„…个zöMÕ\v
A) ´成、震荡、Â-、成熟。 $)震荡、Â-、´成、成熟。
) Â-、震荡、´成、成熟。 *) ´成、Â-、震荡、成熟。
14.*uring the execution phase of project,"ou reali<e that one of the product functionalities
has een omitted in the projeet plan ,#hich #ill not e+entuall" satisf" the reuirement ,"ou
should .
A) update the project schedule and udget
$) sumit a change reuest to change control oard and re aseline
) negotiate #ith the client for a ne# deli+er" date ased on the re+ised schedule
*) informing management and ta,e necessar" measures for changes in udget and schedule
P项目»«EF,ã®ýtP项目ÅÆ5‹Œ^一项îïÚ÷,$ò*终àÂÀè足7W,$Kã2˜ 。
A) 09项目进度ÅÆ™¥x
$) ~/0Ë制âeš¿¢/0申Ž,Î19制x项目ú_ÅÆ
)oÝÔ—的进度ÅÆ諬Ø3一个9的¢付HT
*)JË$¿qY¯,Î]/0¥x™进度ÅÆ>?7的%骤
15.A re+ie# of management processes and the associated documentation is commonl" called
.
A) audit $) inspection ) testing and measuring *) screening
#qY¼½™相@XY进Ê的ÿÖJKÕ] 。
A)ÖÅ $) ©ª )L试™L¡ *)Ž映
1.ompanies and institutions most commonl" hire project management leaders #ith .
A) a strict standing in negotiating.
$) experience in tric,ing usiness partners.
) integrit" and expertise.
*) a strong lin, to local traditions.
²³™ÔZ;ú的项目qY‹JK™= 。
A)谈判5严Ã的íî $)欺骗35伙伴的X9 ) ˆ¼的ïÙÇ5*+ *) ™本·
传–的密ù7
1=.hat is true #hen a change control s"stems pro+ision for changes #ithout formal re+ie# incase of emergenc" is eing utili<ed'
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 33/42
A) hanges can e simpl" applied #ithout further managerial acti+ities if the" help sol+ing the
prolem.
$) hanges must still e documented and captured so that the" do not cause prolems later in the
project.
) A ne# change control oard ($) should e estalished. *) &he project aseline must e changed as #ell.
rÕ`紧./0K/0–Â×öìJ¼ˆ•ÿÖnÉÊ,@¨$%&'ƒ„…个fè
是ˆÌ的'
A) ÞÀ/0ö짨ðøs题,ŒxöìPX¼0HqYDE的&'ƒO简S·ÉÊ。
$) /0?@OXY'(™VW,避免PDM引Õ项目s题。
) 67‘í9的/0Ë制âeš。
*) 项目ú_?@£K/0。
18.$eing assigned as the project manager to a project "ou perform earned +alue Anal"sis and
find the follo#ing results v % Û -507000 ; P Û -007000 ; A Û -=57000 ; $A Û
5007000.hat is right'
A) %AÛ4007000. $) %AÛ5507000. ) $&Û4007000. *) %&Û=57000.
P项 目eãé^»)Üi,,Õ)ƒ„;Àv %Û-50 000;PÛ-00 000;AÛ-=5
000;$AÛ500 000。ƒ„…项是ˆÌ的'
A) %AÛ400 000。 $) %AÛ550 000。 ) $&Û400 000。 *) %&Û=5 000。
19 . A is a preFcontract agreement that formall" estalishes the intent of one part" to u"
products or ser+ices from another part" and estalishes some preliminar" consideration in order
to reser+e resources for the anticipated contract.
A) seller initial response $) memorandum of understanding ) letter of intent *) letter
contract 一个‚£ÙÚ成的Ø议úMˆ•‘í一个®~v一žk一ž?Óîï¬}~Îâ%考
~]‚£ÄæUŠ,$个XYOÕ] DD 。
A)Ôžâmw2 $)谅ð=( ) ®~& *) ‚£&
1=0.hat does the acron"m @AI commonl" stand for in project management'
A) @esponsile,accountale,to e communicated,&o e informed.
$) @emote,attached,connected,integrated.
) @is, anal"sis and caution initiati+e.
*) @andoml" accessile cash flo# information.
P项目qY5@AI¸Ñwx'
A) b°,°,¤J,Z[。 $)!ð的,"±的,…Ï的,É‚的。
) ûüi,™#$=E。 *)PÔÏ)ü£信°。
1=1.A change reuest in a project has een rejected some #ee,s ago .Besterda",the project
manager found out that it ne+ertheless has een implemented " the team memers,#ho ,ne#
of the change reuest, ut not of the rejection .In order to a+oid such a situation ,reMected
change reuests are input to #hich process'
A) Schedule de+elopment. $) Scope +erification.
) 3onitor and control projeet #or, . *) Information distriution.
一个/0ŽWP·"ÚO]^。%I,项目XYÕ)$个/0还是Ocd成e»«^,y
]u们Ëß$个/0ŽW但ËßO]^^。]避免$%)_,]^的/0òÇÈt…个¼½'
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 34/42
A) 制×进度Ñ。 $) º»-.。 )„€èË制项目QR。 *)信°Õ¶。
1=-.All the follo#ing statements are true exceptv
A) It is axiomatic of the ualit" management discipline that the enefits out#eigh the costs.
$) ualit" should mainl" e achie+ed " testing and inspections of #or, results on a regular
ase. ) &he primar" cost of meeting ualit" reuirements is the expense associated #ith project
ualit" management acti+ities.
*) &he primar" enefit of meeting ualit" reuirements is less re#or, , #hich means higher
producti+it",lo#er costs,and increased sta,eholder satisfaction.
ƒ„ab¸¹ô是ˆÌ的,W^v
A) Ò!‹见,¡qY的ú本/á是c益?@超¼成本。
$) ¡=72˜J¼×T©ª™L试项目成ÀM»)。
) 足¡6W的=7成本ïðP项目¡qYDEe。
*) Á‚¡6W=7的+¸是减少返Q,$®LQ$`î效q、Ê成本™±的2V
®度。
1=2.hich of the follo#ing statements is not true'
A) Attriute sampling is the process of assessing #hether results conform to specifications or
not.
$) Pre+ention means ,eeping errors out of the process " appl"ing actions efore the process
starts changing its input.
) ariales sampling means that the result is classified into one of the 2
categoriesvacceptale/Facceptale after re#or,/F relected/.
*) Inspection is often mainl" done to ,eep errors out of the hands of the customer instead of as a
means of process control. ƒ„…个fè是ˆÌ的'
A)Z)k¹是ÿ估;À是÷Á‚ÂÃ的¼½。
$) ¥¦是指J¼P¼½lmÙÚ>ÊEÌÄ0误šþ)P¼½b。
) /¡k¹®LQ;ÀJKi]²个|þvÏÐ,返QõÏÐ,]^。
*) ©ªJK=7úMÌÄ0误št«¬&5。
1=4.hich of the follo#ing statements regarding #histle lo#ing are not true'
A) It is a term used to define an emplo"ees decision to disclose information on
unethical,immoral or illegal actions at #or, to an authorit" figure.
$) An emPlo+ee should al#a"s discuss the matter #ith people external to the compan" efore
follo#ing thechain of command/and discuss it #ith the immediate superior .
) &he conseouences of #histle lo#ing are often extreme and include possile eing randed as
ha+ing ad Mudgment,firing,ci+il action and imprisonmentH
*) arefull+ considered #histle lo#ing can lead to the end of unethical usiness practices.
ƒ„…项@¨'Õ (À[È() /的fè是ˆÌ的'
A) $个)×Ø^;eøב'*aP²³的߶的、+,的¬&è的QR。
$) “ ”P遵循 a-. ™¼Ïe¿67ÙÚ,eQ2˜:是™;lV67²³的s题。
)1 ”'Õ 的õÀJK是æ/的,Sö÷Ole0误判0的1m,ð;ìÍ2-诉3™
„4。
*) “ ”Š¯考~ 'Õ öìù߶的35»56%V失。1=5. Bou are assigned as the project manager in a project #ith an aggressi+e schedule,*uring a
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 35/42
recent meering "our team complained aout the high pressure applied and the man" hours of
o+er#or, time.hat should "ou do first'
A) &r" to otain additional udget and time.
$) Impm+e team communication and a+ailailit" of high ualit" data on ris,s . :se ttlis
information to enale "ou to ma,e #ellFfounded decisions earlier . ) &he prolem might e the customer disturing project rh"thm.Keep him on distance from
the team.
*) Appl" fast trac,ing to shorten project duration #ithout additional #or, .
ãOiÎt一个进度#Jo¥的项目e担±项目XY。P*的š议e,ã的cd成e~
ã78¼$的#J™¥¡的±9。ã¡2˜éwx'
A):试Ž:;的¥x™KL。
$) —进cd的¤J™$¡ûü数Ý的öŽ)。ùú$ë信°§¨ã½早的R(boÝ
的øÐ。
) $ës题ö÷MÀ«¬2;项目M<,Ć«¬ècd的=´。
*) P±:;QR的Ú¿ƒ,ùú5gV进M$Þ项目+K。
1= . A Project team is suffering from misunderstandings et#een team memers #ho ha+e
different cultural ac,grounds . &he project manager is e+aluating ho# to impro+e
communication and collaoration.hich of the follo#ing statements is not true'
A) ;nl" those #ho reali<e that cultural differences are a resource to e full" utili<ed #ill
sur+i+e in international project usiness.
$) &here is a common ground for people from different cuItures on #hich the" can interact
#ithout unsol+ale conflicts.
) ultural differences #ill al#a"s remain an ostacle to e o+ercome for crossFcultural
projects.*) rossFcultural competence is a critical le+er for competiti+e ad+antage in international
project usiness.
™b£Xh)ñ的cdCÈ相互误ð的>?5。项目XYPÿ估ÞI—进¤J™‚R。
ƒ„…个fè是ˆÌ的'
A)<bŒë认ýtXh£是个UŠ、öì=iÃú的V‡÷¾P„ø项目5›Ö。
$) MÀ£Xh的V们™b¢£的)ñ,u们öìP‰b÷ðø的冲突的&'ƒ相互
vw。
)XhK@:是ÖP的ÎAB跨Xh的项目。
*) P„ø项目355竞争5,跨Xh÷J是个@A的CD。
1==.A project management team is e+aluating the causes that might contriute to unsatisfactor"
perforrhance and ualit".hich of the follo#ing statcments is not true'
A) Cormal process +ariation is attriutale to random causes and sometimes also called#hite
noise/.
$) Special callses are easier to predict and handle than random causes (also called common
causes) .
) Special causes are unusual e+ents #hich are difficuIt &o foresee and mostl" produce
outliers.
*) A process can e optimi<ed to limit the and#idth of +ariations due to random causes.
项目qYcdˆPÿ估ö÷àÂÁ‚7W的绩效™¡的/y。ƒ„…个fèˆÌ' A) ˆK¼½的PÔ偏KöZ¨PÔ/y,bK_OÕ]EFG/。
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 36/42
$)fH/yjPÔ/y (IJ/y)4‹O¥Ë™Ë制。
)fH/y是œKÂ-",op¥见,XKàÂs题。
*) ¼½的PÔ/y的偏KöìO‚制¨ÏÐ{|Ùb。
1=8 . *uring a project the scope of a product purchased on a cost reimursale contract has
increased.In the contract the fee to co+er the contractors indirect costs and allo# a profit iscalculated as -0Lof the direct costs.hat is most li,el" to e true'
A) &he contractors indirect costs #ill increase and the customers pa"ment for them #ill
increase,too.
$) &he contractors indirect costs #ill increase ut the customers pa"ment for them #ill not
increase.
) Ceither the contractors indirect costs nor the customers pa"ment for them #ill increase.
*) &he contractors indirect costs #ili not increase ut the customers pa"ment for them #ill
increase.
一个ùú成本TJ‚£的îï>?‚£-.±^,P‚£ŸÓžÝ付的ðúS承S
3的LÏ成本™¼Ï成本的 -0L。ƒ„…个fè*ö÷是ˆÌ的'
A)承S3的LÏ成本š±,]M«¬的ðúRš±。
$)承S3的LÏ成本š±,但«¬的ðúš±。
)承S3的LÏ成本š±,«¬的ðúRš±。
*)承S3的LÏ成本š±,!«¬的ðúš±。
1=9.Bou are assigned as the project manager to a project #hich is executed for a customer under
EP contract . Bour customer informed "ou this morning that the" insist on
certain1refinements2of the project scope.Bou agree that the reuested actions ma,e reall"
sense to the project , ut elie+e that the" constitute a major change increasing the project
scope.hat should "ou do next'A) Accept the reuest of the customer .*iligentl" document the additional costs and #or,ing
hours spent " "ourself and the team on the implementation of the change and in+oice these
to the customer at appropriate rates.
$) Perform earned +alue anal"sis to assess the current status of the project and get all the
numers "ou need to communicate the case to the change control oard #ich then #ill ha+e
to ma,e the est decision regarding the customer reuestF
) hec, the contract,the project charter ,the scope statement and other documents related to
the project and the contract . Assess the impacts of the scope change . &hen discuss the
situation #ith the project sponsor and the change control oard.
*) &al, to the project sales department and find a joint solution #ith them ho# to est reject the
reuest considering the commercial and strategic +alue of the customer to the organi<ation
"ou are #or,ing for .
ãO指ã]某项目的项目XY,$个项目ùú的是固×:价‚£。ã的«¬”I早eJË
ãu们Kø7Ì×项目-.的¯M。㣮$个ŽW#项目是b益的,ã相信u们š¿1
一个/0ŽWM±项目-.。σMã2˜éwx'
A) ÏЫ¬的ŽW,认‡'(ãÀÁ™cdÉÊ$个/0aïð的:;的成本™QRK
L,Î~«¬c‚’的ðú。
$) ÉÊ»)Üi,ÿ估项目rÚ{|,ƒab数Ý¿1ê/0Ë制âešì便u们#«
¬的ŽWR(*+的øÐ。) ©ª‚£、项目z½、-.fg&ìÍtuè项目™台£相@的XY,ÿ估-./0的
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 37/42
vw,è/0Ë制âeš™Õ起V67。
*)è项目L售l门进Ê¢£,J¼考~ã²³™«¬的35™M£价Ü,8t*+的]
^ŽW的žÆ。
180.hat is sometimes referred to as gloal illiteracies'
A) &he ailit" to read reports #ritten in man" different languages. $) &he ailit" to succeed in a cross cultural en+tronment.
) &he ailit" to de+elop internationall" accepted contracts.
*) &he ailit" to communicate using dra#ings and pictograms #hich are understood all o+er the
#orld.
ÉNhXO/JKš涉Í…ëb4'
A)PQúH%R"写(的[`的÷J。
$)跨Xhjkƒ成Ú的÷J。
)编写„øeôÏÐ的‚£的÷J。
*) ùúÉNô÷ÏÐYð的ódž•M¤J的÷J。
181.A project management team #ants to procure some customi<ed products #hich are a+aliale
in identical grade and ualit" from man" +endors.hat should e included in the procurement
pac,age to ensure that their offers #ill e comparale'
A) A statement of #or, descriing the needs of the project in sufficient detail to enale +endors
to ma,e suitale proposals.
$) A statement of #or, specif"ing attriutes and metrics of the reuested deli+erales in detail
to allo# +endors sumission of ids.
) &he appro+ed project scope statement , the $S #hich should e ro,en do#n to #or,
pac,age le+el and the $S dictionar".
*) &he ris, management plan and the reports from those ris, management re+ie#s #hich ha+e een made so far .
项目qYcd#Žë×制h的îï,$ëîïöì由oH123¿1,Ιb£¹的
¦¿™ï。ƒ„…项?@S含P>?S5úMÌÄu们的‘议是öj½的'
A) S; P足¾的®¯½度e¸¹^项目的6WúM6Ôž¿1’r的‘议。
$) S;®¯¸¹^7W的ö¢付成À的fÄ™ç数ì便6123[价。
)×_的项目-.fg&,$S?@étQRS¯ŸÎS$Saƒ。
*) t目Ú]vé的ûüqYÅÆ™ûüqYÿ估的[`。
18-.Bour project is executed #ith a gloall" spread +irtual team.&he project progress has een
found to e too slo#.hich measure is most li,el" to immediatel" speed up the project'
A) &echnical training for all team memers.
$) *ail) phgne conferences and detailed reporting.
) A team meeting at a location con+enient to all team memers.
*) ollocation of team memers at a suitale place.
ã的项目由一个ÉNS拟cdMÉÊ。项目进\FT^。ƒ„…%žèöìíñ±g项目'
A)*+stabcd成e。
$)每IÃlø}š议£K鮯Z[。
) P¥Èô便Ã的·gÃlcdš议。
*) P’r的†ÏA5º²。
182 . *uring execution of a project #hich is performed for a customer on a &J3 (time andmaterial) contract ase ,a ne# project manager is ta,ing o+er the assignment .?e disco+ers
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 38/42
that t#o memers assigned to the project ha+e charged time #ithout performing an" #or, for
the project customer . :pon further in+estigation , he determines that this occurred ecause
there ha+e een no other project assignments open for these emplo"ees . &he customer is
una#are of these facts.hich of the follo#ing should he do'
A) &r" to find some producti+e #or, for these staff memers in the project and lea+e them on theteam.
$) &he est thing is to do nothing.&he customer #ill not reali<e the prolem an" a".
) &r" to find a responsile person for the o+er assignment #ho can e made accountale.
*) &a,e the t#o people off the team immediatel" and arrange for the refund of the excess
charges to the customer .
P一个ú¨KL°料‚£的项目的Éʼ½5,iÎM一个9的项目XY,uÕ)!个
项目成e‰b]«¬é±IQR。进一%的ÙªÕ),$%)_的Õ`是y]$ëµe‰
btu项目öìé。«¬Ëß$ë-»。u2˜œ¹é'
A) P项目58ë`î)的QRê$ëeQ,6u们æPcd。
$) *+是wxôé,«¬是À7ÞIRšÕ)$%&'的。
) 8(#M&'°的VMé个ð,。
*)6$!个Ví•´lcd,õU还«¬:;ïð的ðú。
184 . Bon are running a project for a customer ased on a cost reimursale contract #ith the
follo#ing terms v &arget costs , 6170007000 ; fix fee , 1007000 ; enefitcost
sharing , 80-0 ; price ceiling , 17-007000 . hich is the P&A (point of total
assumption, rea, point) of the proiect'
A) 6172007000. $) 6175007000. ) 6807000. *) 6171-57000.
ãP]«¬é一个项目,ùú的是成本TJ‚£,数ÝÞƒv目¤成本, 1000000 ßà;
固×Vü,100000 ßà;Ã益成本i担,80-0;*$‚价,1-00000 ßà。ƒ„…个是项目的 P&A (:š‚<g,W|g) '
A) l200000 ßà。 $) 1500000 ßà。 ) 80000 ßà。 *) 11-5000 ßà。
185 . A project management team has sucontracted #or, to a ser+ice compan" hich of the
follo#ing tools is the est choice to assure that this compan" #i e ale to meet the ualit"
reuirements of the project'
A) ualit" audit. $) *eli+erale inspection. ) Eixed price contract. *) Ser+ice le+el
agreement.
一个项目qYcdƒQRiSê一È}~²³。샅%Q™是*+的ÑÒúMÌÄ$È
²³÷o+·足项目的¡7W'
A) ¡ÖÅ。 $) ö¢付º©ª。 )固×:价‚£。 *)}~¦¿Ø议。
18.In a traditionall" dra#n decision tree,a circle represents .
A) a chance to #hich no estimated monetar" +alue can e assigned so that a li,el" pa"Foff carl
not e sho#n
$) a decision to #hich no estimated monetar" +alue can e assigned so that a li,el" pa"Foff can
not e sho#n
) a chance to #hich an estimated monetar" +alue ma" e assigned to calculate the most li,el"
pa"Foff
*) a decision to #hich an estimated monetar" +alue ma" e assigned to calculate the most li,el"
pa"Foff P传–的øÐXóÆ5.一个YZ¸Ñ 。
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 39/42
A) 一个Ôš,‰bOiÎ%3 aì÷Åx*ö÷的回[
$) 一个øÐ,‰bOiÎ %3 aì÷Åx*ö÷的回[
) 一个Ôš,OiÎ一个 %3 úMÅx*ö÷的回[
*) 一个øÐ,OiÎ一个 %3 úMÅx*ö÷的回[
18=.Bou are #or,ing as a project manager for a major usFased pulic compan".&his morning"ou recei+ed alarming ne#s that the major strategic project "ou are responsile for #ill not e
ale to pro+ide financial enefits to the organi<ation as expected . &his dra#ac, #ill
significantl" influence future profits of the entire corporation.hat should "ou do right no#'
A) Bou should not o+eract and chec, at least three options efore ma,ing an" decisions.
$) Bou must immediatel" inform the corporate management to ensure real time issuers
disclosures.
) Bou should in+estigate detailed information on the prolem efore escalating it to corporate
nlanagement.
*) Bou should find a uic, solution for the prolem and implement this immediatel".
ã是一个:l<Pß„的eí²³的项目XY。”Ie[,ãct-V震\的V°,由ã
°的一个1¥M£项目òÀèk组织5Ž¥T的]šÝ†。$ò¥¥vw”õÉ个²
³的Ã润。ã)P2˜œxé'
A) 7Õ^,PR(±Iø×ÙÚu少制x²个öÑžÆ。
$)?@íñJ˲³qY¯,ÌÄs题ÍKO67。
) Ps题:¿t²³qY¯ÙÚ,Ùª˜s题的®¯信°。
*)Þg8(ðøs题的ºè,!3ñ•_Ê。
188 . In order to speed up a project , "ou made a decision to fastFtrac, a phase currentl"
performed #ith fi+e team memers and another one #hich #as planned to egin in four #ee,s
time #ith another fi+e team memers.hich of the follo#ing acti+ities should "ou do first' A) 3a,e sure that all exit criteria of the consecuti+e phase ha+e een met to ensure the flo# of
communications in a team situation #hich is more complex " a factor of -.
$) 3a,e sure that all entr" criteria of the pre+ious phase ha+e een met " planning and
performing a phase gate meeting to assess technical aptness.
) 3a,e sure that all exit criteria of the pre+ious phase ha+e een met " planning and
performing a phase gate meeting to assess technlcal perlormance.
*) @estructure "our team and delegate tas,s in ordcr to ensure the flo# of communications in a
team situation #hich is more complex " a factor of 4.5
]^±g项目,ãø×5gV进某个EF,$个EF)P由 5 个cd成eÉÊ;一个ò
P›`"lm,由tu 5 个cd成eÉÊ。ã2˜¡进ʃ„…项DE'
A) Ì认abõ‡EF的U(¤_O足,ÌĤJza,y]$%&'ƒ¤Jjì“å
æ^ -b。
$)J¼ÅÆ™ÉÊ一个EFš议Mÿ估*+÷J,ìÌ认abÙÚ的EF的进Ȥ_O
足。
)J¼ÅÆ™ÉÊ一个EFš议Mÿ估*+绩效,ìÌ认abÙÚ的EFU(¤_ŒX
O足。
*)1组ã的cdÎiα~ìÌĤJza.y]$%&'ƒ¤Jjì“åæ^ 4.5b。
189.hich of the follo#ing tools is used to create a ris, managemcnt plan'
A) @is, planning meetings. $) *ocumentation re+ie#s. ) *ata precision ran,ings. *) *iagramming techniues.
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 40/42
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 41/42
$) refuse the reuest and report the customer to "our sponsor
) ac,no#ledge the reuest and ad+ise the customer to sumit a formal change reuest
*) con+ene a meeting of the project team and re#rite the scope statement
P一个;l项目5.ã的一个«¬7WãN成一ë:;的QR.$ëQRSPˆ•‚
£5,ã2˜ 。 A)Xy«¬的7Wé,ÑgÀÁ的‚Rl|,$#òM諬é`®b§¨
$)]^«¬的7W,~ã的项目Õ起V[`$"-
) ÏЫ¬的7W,Α议«¬¿¢一mˆ•的/0申Ž
*)ÃA项目cdš议,19写项目-.fg&
195.*uring half #a" to the project execution ."ou #ere assigned as a project manager .After
careful re+ie#ing of the project,"ou found that the project might ta,e doule the time that the
pre+ious manager estimated.?o#e+er , the upper management has een told that the project
is on schedule.&he pre+ious manager is an old friend of "ours.#hat #ill "ou do'
A) @eport "our e+aluation to the upper management
$) ?a+e a team meeting to find the alternati+es to meet the project schedule
) 3eet the pre+ious project manager and turn the project ac, .
*) %xecute the project as planned " the pre+ious manager .
P项目ÉÊT的5LEF,ãO±a]˜项目的XY。P#项目进Ê认‡ÿ估Ùõ,ãÕ
)项目的QT7jÚ±项目XY估x的QTG一b。ö是,$¯qY‹‘O`˘项目的
进度是PXÅÆ进Ê。Ú±项目XY是ã的一个•no,ãšœxº'
A) ~$¯qY‹Þ»[`ã#项目的ÿ估。
$)Ãlcdš议.×Ø(足/ÅÆ进度的tu·¸žÆ。
) š见Ú±项目XY,pq项目进度。
*)XyÚ±项目XY制x的ÅÆÉÊ项目。19.hen there are conflict in the contract, is the first one should e resol+ed.
A) schedule planning $) deputi<e ) contract term *) criterion
r‚£5ÖP冲突K,¡67ðø的是 DD 。
A) 进度ÅÆ $)¸Y ) ‚£Rr *) Â-
19=.In managing a project."ou notice that a deli+erale mentioned in the general conditions of
the contraet has not "et een recei+ed .&he seller ,ho#e+er ,sa"s the special pro+isions of
the contract +oid that dell+erale.hat should "ou do'
A) @euire the deli+erale as in the contract.
$) *o nothing.
) ontact the contract manager .
*) Send a letter reuiring the deli+erale is met.
P#项目进ÊqY的¼½5,ãä®t‚£一RrbÂ×的一项ö¢付成À还‰bct。
但是,Ôžfg‚£fþRrŒXV^˜ö¢付成À。ã2˜ÞIé'
A) 7W¿1‚£Â×的ö¢付成À。 $) >±Iª«。
)è‚£XY7。 *)签Õs",7W¿¢ö¢付成À。
198 . ontract closure procedure and administrati+e closure procedure ha+e se+eral common
characteristics,the follo#ing are their common characteristics except .
A) exit criteria $) contract term ) srep " step *) acti+ities and responsiilities
‚£cd½ö™Êšcd½öboH相…Ù¸,ìƒ\是¾们的¢£fg,W ̂DD 。 A)U(¤_ $) ‚£Rr )6%¸Y *) DEè°±
8/11/2019 51CTO -2012 9 PMP 200
http://slidepdf.com/reader/full/51cto-20129pmp200 42/42
199.hich t"pe of input is the primar" cause of conttact changes'
A) Independent estimates. $) ;rgani<ational policies.
) Statement of #or, . *) Appro+ed changes reuests
ƒ¹…项ÇÈ是‚£/0的=7/y'
A)Tí估x。 $)组织šÐ。 ) QRfg&。 *)×_的/0ŽW。-00.A procurement audit is a structured re+ie# of the procurement process from procurement
planning through contract administration . hat is the primar" ojecti+e of a procurement
audit'
A) *etermine the issues #ith "our present contract so that the contraet terms can e modified or
impro+ed.
$) Identif" successes and failures that #arrant transfer to other procurement irems on this project
or to other projects #ithin the performing organi<ation.
) &o ensure that the seller is follo#ing all the terms listed in the contract.
*) &o ensure that the u"er is follo#ing all the terms listed in the contract.
>?ÖÅ指#k>?ÅÆ编制t‚£qY的É个>?¼½的;Z)回。>?ÖÅ的=7
目¤是wx'
A)L×ã目Ú的‚£s题,ì便#‚£Rr进Ê0—™Ôˆ。
$)tþ成Ú™失败ìú¨M项目¬ÉÊ组织的tu项目的>?-项。
) ÌÄÔžXy‚£a„RrÉÊ。
*) ÌÄÓžXy‚£a„RrÉÊ。