51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

42
2012 9 PMP 认证模拟考试一试卷 200 1 A manufa ctu ring pto ject has a sch edule perfo rma nce inde x (SPI) of 0.89 and a cos t  performance index (PI) of 0.91 !enerall"#hat is the $%S& explanation for #h" this occurred'  A) &he scope #as changed $) A supplier #ent out of usiness and a ne# one needed to e fo und ) Additional euipment needed to e purchased *) A critical path acti +it" too, longer and neede d more laor hours t o complete 某个制造项目的进度绩效指数 (SPI) 0.89;成本绩效指数 (PI) 0.91!"#$ %&'()*+,'  A) -./0 $) 123456789的。  ) :;<=67>? *) @ABCDEFG670HIEJKLMN成。 - *uring the completion of #or, pac,ages the sponsor as,s the project manager to report on ho# the project is goingIn order to prepare the reportthe project manager as,s all the team memers #hat percent complete their #or, is &here is one team memer #ho has een hard to manage from the eginning In response to eing as,ed #hat percent complete he is the team memer as,s Percent complete of #hat'/$eing tired of such comments the project manager reports to the team memers oss that the team memer is not cooperating hich of the follo#ing is li,el" to e the real prolem'  A) & he proje ct mana ger did not get u"Oin from the manager for the resources on the project  $) &he pr oject manager di d not create an a deuate re#ar d s"stem for team me mers to impro+e their cooperation ) &he project manage r should ha+e ha d a meeting # ith the team memers oss the first time the team memer caused troule*) &he project manager does not ha+e #or, pac,agesPNQRSTL(UV7W项目XYZ[项目进\]^_=[`项目XY7W abcdefgQRN成的hijbcdeklmnopqYrstuQ RNhijKufvwxNhij'/y]z{$|#}项目XY~cde•€[`f$个成e‚Rƒ„…0†‡ˆs' A) 项目XY‰bkUŠqY‹Œ‡ˆ]项目Ž$) 项目XY‰b‘‚’“”M—cdeR) 项目XY2˜™cde•€lšPcde›œžŸK*) 项目XY‰bQRS

Transcript of 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

Page 1: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 1/42

2012年 9 月 PMP认证模拟考试一试卷 200

1 . A manufacturing ptoject has a schedule performance index (SPI) of 0.89 and a cost

 performance index (PI) of 0.91 .!enerall",#hat is the $%S& explanation for #h" this

occurred'

  A) &he scope #as changed.

  $) A supplier #ent out of usiness and a ne# one needed to e found.

  ) Additional euipment needed to e purchased.

  *) A critical path acti+it" too, longer and needed more laor hours to complete.

  某个制造项目的进度绩效指数 (SPI) 是 0.89;成本绩效指数 (PI) 是 0.91。一!",#$

%&'()的*+的,是'

  A) -./0。

  $) 12345,6789的。

  ) :;的<=67>?。

  *) @ABC的DEFG,670HIEJKLMN成。

-.

*uring the completion of #or, pac,ages,

the sponsor as,s the project manager to report onho# the project is going.In order to prepare the report,the project manager as,s all the team

memers #hat percent complete their #or, is.&here is one team memer #ho has een hard

to manage from the eginning.In response to eing as,ed #hat percent complete he is ,the

team memer as,s,Percent complete of #hat'/$eing tired of such comments ,the project

manager reports to the team memers oss that the team memer is not cooperating .hich

of the follo#ing is li,el" to e the real prolem'

  A) &he project manager did not get u"Oin from the manager for the resources on the project.

  $) &he project manager did not create an adeuate re#ard s"stem for team memers to impro+e

their cooperation.

  ) &he project manager should ha+e had a meeting #ith the team memers oss the first time

the team memer caused troule.

*) &he project manager does not ha+e #or, pac,ages.

PN成QRSTL,(UV7W项目XYZ[项目进\。]^_=[`,项目XY7W

ab的cd成efgQRN成的hij。b个cd成eklmnopqY,rstuQ

RN成hijK,ufvwx是N成hij'/y]z{$|#},项目XY~cd成

e的•€[`f$个成e‚R。ƒ„…个0†‡ˆ的s题'

A) 项目XY‰bkUŠqY‹Œ‡ˆ]项目ŽUŠ。

$) 项目XY‰b‘‚’的“”–M—进cd成e的‚R。

) 项目XY2˜™cd成e的•€l个š,Pcd成e›一œžŸK。

*) 项目XY‰bQRS。

Page 2: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 2/42

2.hich is not a goal in oth project management and ualit" management'

  A) Pre+ention o+er inspection.  $) ustomer satisfaction.

  ) 3anagement responsiilit".  *) &riple constraint.

  ƒ„…个是项目qY™¡qY的¢£目¤'

  A) ¥¦§¨©ª。  $) «¬®。  ) qY¯°±。  *) ²³´µ¶。4.hich of the follo#ing $%S& descries the +erif" scope process'

  A) It pro+ides assurances that the deli+erale meets the specifications,is an input to the project

management plan.and is an output of perform ualit" control.

  $) It ensures that the deli+erale is completed on time and gets customer acceptance,and sho#s

that the deli+erale meets specifications.

  ) It ensures customer acceptance , sho#s that the deli+erale meets specifications , and

 pro+ides a chance for differences of opinion to come to light.

  *) It is an output of perform ualit" control,occurs efore define scope,and ensures customer 

acceptance.

  ƒ„…项*+·¸¹^º»-.¼½'

  A) ¾¿1成ÀÁ‚ÂÃ的Ä证,是项目qYÅÆ的ÇÈ,是ÉÊ¡Ë制的Ç(。

  $) ¾ÌÄ成ÀÍKN成Ît«¬ÏÐ,Ñg成ÀÁ‚ÂÃ7W。

  ) ¾ÌÄ«¬ÏÐ,ÒÓ成ÀÁ‚ÂÃ7W,¿1ÔšÍKÕ)ÖP的s题。

  *) ¾是ÉÊ¡Ë制的Ç(,P×Ø-.ÙÚ(),ÌÄ«¬ÏÐ。

5 . A project has the follo#ing earned +alue data assessed v A Û  6470007000 ; Û   6 O

5007000;SPIÛl.1-;$AÛ 697507000.hat is the earned +alue of the project'

  A) 6270007000.  $) 6275007000.) 6474807000.  *) 657507000.

项目»)Ü数ÝÞƒvAÛ470007000 ßà;ÛO5007000 ßà;SPIÛ1.1-;$AÛ

97507000 ßà。á %Û  。A) 270007000 ßà  $) 275007000 ßà  ) 474807000 ßà  *) 57507000 ßà

.At the eginning of project execution,"ou notice different opinions et#een team memers

relating to project #or, and deli+erales and to the le+el of o+erall complexit" .hat should

"ou do right no#'

  A) !i+e "our team memers some time to de+elop a common understanding of the project scope

and product scope.:pcoming interface prolems ma" e resol+ed later .

  $) :se the ris, management processes to identif" and assess ris,s caused " misunderstandings

and de+elop a plan #ith measures in order to respond to them.

) ;rgani<e meetings to identif" and resol+e mlsunderstandings et#een team memers in

order to earl" a+oid interface prolems,disintegration and costl" re#or, .

  *) :se inter+ie#s in pri+ate #ith each indi+idual team memer to inform them of "our 

expectations and "our reuirements in an atmosphere of confidence.

  P项目ÉÊâT,ãä®t项目cd成e#项目QR™成À的åæ½度b£的çè。ã

)P2˜éwx'

  A) êcd成eëKL,ì‘í#项目-.™îï-.的¢£Yð,ñò()的Ïós题

ôõö÷šðø。

  $) ùúûüqY¼½Mýþ™ÿ估由¨误ð引Õ的ûü,编写个ÅÆM衡¡Î回2¾们。

  )组织š议Mýþ、ðøcd成eÙL的误ð,ì便尽早避免Ïós题,减少返Q成本。

  *)私ƒš见每个cd成e,P互相信±的氛.ƒ`诉u们ã的T望™ã的7W。= . $eing the project manager in a soft#are project #hich is currentl" initiated , "ou #ant to

Page 3: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 3/42

assess high le+el ris,s.hat should "ou do'

  A) *e+elop a preliminar" scope statement and document initiall" identified ris,s in this

document.

  $) Identif" and anal"<e ris, e+ents using ualitati+e and uantitati+e techniues.

  ) *e+elop contingenc" plans and fallac, plans in case the original plan pro+es #rong.*) *iscuss the ris,s documented in "our ris, register #ith the project ,e" sta,eholders.

ã是个项目XY,刚刚E一个!"项目,ã#ÿ估*$¯œ的ûü,ã2˜éwx'

A)编写â%-.fg&,'(ƒM*âýþ的ûü。

$) ùú×)™×¡*+ýþ™i,ûü-"。

)编写2.ÅÆ™õ=ÅÆì¦/M的ÅÆ()0误。

*) ™项目172V#ãûü3'45的ûü进Ê67。

8.hat is not a reason for companies to organi<e lessons learned'

  A) >essons learned dataases are an essential element of the organi<ational process assets.

  $) >essons learned should focus on identif"ing those accountale for errors and failures.

  ) >essons learned sessions should ring aout recommendations to impro+e future performance

on projects.

  *) Phase end lessons learned sessions pro+ide a good team uilding exercise for project staff 

memers.

  ƒ„…一项是85组织X9:;的/y'

  A) X9:;数Ý<是组织¼½Uî的=7à>。

  $) X9:;?@A5¨ýþ0误™BC的°±。

  ) X9:;š议2˜¿(‘议ì¿$项目DM的绩效。

  *)EFX9:;š]项目成e¿1^o+的cd‘<GH。

9.?o# should change management e planned for'  A) hanges are generall" not predictale,therefore planning for change management cannot e

sensile.

  $) Planning for change management should e done #hile the +arious change control processes

are eing applied.

  ) hange management can e planned in a set of management plans or a specific change

management plan.

  *) hanges are a sign of ad planning . ;ne should a+oid changes during a project thus

eliminating the need to manage them.

  /0qY˜ÞIÅÆ'

  A) /0JK是ö¥L的,yMÂÆ/0qYgN。

  $) rb£的/0Ë制¼½O2úK,?@7ÂÆ/0qY。

  ) /0qYöìPQ一„qYÅÆ!ÂÆ,RöìST进ÊÂÆ。

  *) /0是ÂÆR+的信U,2˜P项目ÉÊ5避免/0,RnVW^qY¾们的6

7。

10.hich of the follo#ing documents is not used as input for product acceptance'

  A) &he project scope statement,it descries the acceptance criteria.

  $) &he project scope management plan,it descries the acceptance process.

  ) &he #or, rea,do#n structure ($S) ,it descries the deli+erales for acceptance.

  *) &he @AI matrix,it descries accountallities in case of product rejection.  ƒ„…个XY是îïÏÐ的ÇÈ'

Page 4: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 4/42

Page 5: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 5/42

A) 2º»×Ø的ab¼½组的¼½ŒN成,M;¶项目EF

$) 2Ì×项目的îïO®·N成

) 项目qYÅÆO项目(UVV

*) 9的/0ŽWOE

1 . Bou ha+e recentl" appointed a project manager to handle a critical prolect in "our organi<ation .Bou #ant to pro+ide the project manager #ith authorit" to appl" organi<ational

resources to project acti+ities.hich document should "ou use'

  A) @esouree authori<ation document.  $) or, rea,do#n structure.

  ) project charter .  *) Project scope statement.

ã*指×^某个项目XY°ã组织的@A项目,ã#ê项目XY‚‘2ú组织U

Št项目DEe。ã2˜ùú…个XY'

A) UŠ€XY。  $) QRið;Z。  ) 项目z½。  *) 项目-.fg&。

1=.Bou are the project manager of a ne# project ,#hich #ill construct a ridge on the @i+er 

 Cile in %g"pt.$efore initiating the project,"ou should .

A) create a scope management plan to document ho# the project scope #ill e

defined,+erified and controlled

  $) de+elop a project management plan

  ) determine specific acti+ities that need to e performed to produce the +arious project

deli+erales

  *) facilitate the formal authori<ation to start a ne# project

  ã是9项目的项目XY,P’Í“”e‘<O–—˜。P项目EÙÚ,ã2  ̃DD 。

  A) ‘-.qYÅÆM'(项目的-.ÞIO×Ø、º»™Ë制

  $) lÕ项目qYÅÆ

  ) Ì×™š的DEúMÉÊî`£的项目成À  *)›Eˆ•€,E9项目

18 . As a project manager , project plan de+elopment is an important element of managing

 projects. hich phase of the project management >ife c"cle does project plan de+elopment

 elong to'

  A) Initiation process.   $) Planning process.   ) %xecution process.   *) ontrolling

 process.

  R]项目XY,项目ÅÆlÕ是qY项目œK17的à>,ƒ„…个项目qY`aTEF

S项目ÅÆ编制'

  A)E¼½组。  $) ÂƼ½组。  ) Éʼ½组。  *) Ë制¼½组。

19.A customer informed "ou that it is preferale to change a certain aspect of the project .hat

should "ou do first'

  A) &al, #ith team memers to understand implications of the change.

  $) ommunicate the change to the management to get their inputs.

  ) ;pen up a change control.

  *) *o si<ing for the change and communicate to the customer .

  «¬`诉ã*+/0项目某个žŸ。ã¡2˜éwx'

  A) ™cd成e¢£Yð$个/0的vw。

$) n$个/0™qY¯¤Jtu们的ÇÈ。

) lm/0Ë制。*) i,/0¥Š,™«¬进Ê¢£。

Page 6: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 6/42

-0 . In "our project , "ou #ant to monitor and control project processes associated #ith

initiating, planning,executing and closing.&his #ill help "ou ta,e correcti+e or pre+enti+e

action to control project performance.In this context,#hat should "ou do first'

  A) @e+ie# all project forecasts.

  $) *etail all the acti+ities of project team memers in+ol+ed in executing administrati+e closurefor the project.

  ) @e+ie# the project management plan and #or, performance information for "our project.

  *) 3anage project ris,s.

  Pã的项目5,ã#„Ë项目E、ÂÆ、ÉÊ、cd¦¼½,$ò§¨ã>©ˆª«¬

¥¦ª«MË制项目绩效。P$%&'ƒ,ã¡2˜éwx'

  A)回ab项目¥L。

  $) PÉÊqYcdK®¯ab项目cd的DE。

  )回项目qYÅÆ™项目的QR绩效信°。

  *) qY项目ûü。

-1 . Bou recentl" joined as the project manager of A$ ompan" . &he outgoing project

manager mentioned that of late , she had een facing se+eral issues #ith ne# change

reuests.&he customers #ere located in the same office and the" interacted directl" #ith the

 project team and,at times,informall" as,ed for some changes in the projects product.If the

changes #ere small,the project team memers usuall" agreed to do the changes .&he project

manager found it difficult to prioriti<e acti+ities and ensure that tas,s are done as per 

schedule.  &he project had 50 team memers and there #as some discontent amongst them

aout the #or, the" #ere supposed to do.hat should e "our first priorit" in this project'

  A) reate a detailed project scope statement.

  $) Align the project ojecti+es #ith the organi<ational goals.  ) %nsure proper project scope control.

  *) all a meeting of all the project sta,eholders to determine and resol+e an" outstanding

issues.

  ã*±Èt A$²³é项目XY。ñò´µ的项目XY¿t,*Õ¶^·个9的/0

ŽW。«¬¸¨£¹的º²»,öì¼Ï™项目cd进Ê¢互,bKšœˆ•·¿(îï

的9/0。ÞÀ/0j½Š,项目cd成eJK£®$ë/0。项目XYÕ)$¹opÌ

×DE的¾¡¿,ÌÄ每个进度Ñ的±~ON成。$个项目b 50 个cd成e,bë#À

Á的QR。ã¡2˜éwx'

  A) ‘®¯的项目-.fg&。

  $) ù项目目¤™组织目¤一Â。

  ) ÌÄ‚’的项目-.Ë制。

  *)Ãlab2Vš议MÌ×™ðø*gÒ的s题。

--.In a recent jo inter+ie# ,"ou #ere as,ed to define the most important characteristic of a

 project manager .hich of the follo#ing #ill e "our est ans#er'

  A) Suject matter expert.  $) Integrator .  ) reati+e person.  *) @is, minimi<er .

  *Ÿ试QR,ãO7W×Ø项目XY*17的fÄ,ƒ„…个是ã*+的ÅÆ'

  A) Ê5ÇÈ。  $)É‚‹。  ) 造‹。  *) ûüÊ估‹。

-2.hich of the follo#ing is not a project management ,no#ledge area'

  A) Project integration management.  $) Project procurement management.  ) Project configuration management.  *) Project communications management.

Page 7: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 7/42

  ƒ„…项是项目qYËýÌÍ'

  A) 项目ÉšqY。  $) 项目>?qY。  ) 项目ÎÏqY。  *) 项目¤JqY。

-4.hen deciding #hich project to select.  .

  A) select the project #ith higher life c"cle cost $) select the project #ith lo#er life c"cle cost

  ) select the project #ith higher sun, cost *) select the project #ith lo#er sun, cost  røÐÑÒ项目K,  。

  A)ÑÒ$`aT成本的项目  $)ÑÒÊ`aT成本的项目

  )ÑÒ™b$Ó‰成本的项目  *)ÑÒ™bÊÓ‰成本的项目

-5.hile doing ualit" inspection,fe# defects #ere identified in the product.After rectif"ing

the defects,the repaired items #ere reinspected and accepted .Suseuentl",a notification

#as issued,#hich can also e referred to as .

  A) +alidated defect repair $) product acceptance ) ualit" audit *) appro+ed change

reuest

  rR¡©ªK,îï的少数BCOýþ。PÔå$ëBCõ,Ôå项O19©ª™ÏÐ。

Põ,一个JËOÕ¶,$个JËOÕ]  。

  A)BCÔåÌ认  $) îïÏР ) ¡ÖÅ  *)×_的/0ŽW

-   . Project integration management includes the proeesses and acti+ities needed to

identif" , define , comine , unif" and coordinate the +arious processes and project

management acti+ities.Eor successful project integration management, "ou should definitel"

ha+e (select the est option) .

  A) a strong matrix organi<ational structure in "our compan"

  $) a good communication management *lan

  ) good project selection techniues

  *) positi+e sta,eholders #ho support the project项目ÉšqYS一ë¼½™DE,úMýþ、×Ø、É‚、ØÙ£¼½™项目qYDE。

]^成Ú·N成项目ÉšqY,ã2˜™=  (ÑÒ*+的Ñ项) 。

  A)Û[\组织;Z  $)Ü+的¤JqYÅÆ  )Ü+的项目ÑÒ*+  *) ˆŸÝ†项

目的2V

-= . Bou ha+e een gi+en a high priorit" tas, that needs to e completed #ithin a short time

frame.Since "ou ,no# #hat has to e done."ou assign tas,s to the different team memers

and tell them #hen and ho# the tas,s should e done . &he management st"le that "ou are

follo#ing is .

  A) directing $) laisse< faire ) delegating *) tas,Foriented

  ã刚Ž$¾¡¿的±~,67PoÞ的KLbN成。y]ãËßwx67ON成,ãi

α~ê£的cd成e,`诉u们wxK_、ÞIN成±~。$%qYûÃ是  的。

  A) 指àá  $)À由•  )âãá  *)Ÿ~±~

-8.As a project manager ,"ou ad+ocate acti+e participation of "our teaill memers O  this is

 ecause "ou elie+e in .

  A) theor" B (3c!regor model) $) theor" G (3c!regor model)

) 3aslo#s hierarch" of needs *) referent po#er 

R]项目XY,ãä望ã的cd成eåæçè,$是y]ã相信 

A) B Y7 (éêÃë模á) $) G Y7 (éêÃë模á) )ìí6Wf  *)

ç考J-9.ost *erformance measurement is $%S& done through #hich of the follo#ing'

Page 8: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 8/42

  A) As,ing for a percent complete from each team memer and reporting that in the monthl"

 progress report.

  $) alculating earned +alue and using the indexes and other calculations to report past

 performance and forecast future performance.

  ) :sing the 5050 rule and ma,ing sure the life c"cle cost is less than the project cost.  *) Eocusing on the amount expended last month and #hat #ill e expended the follo#ing

month.

  成本绩效衡¡*+J¼ƒ„…项M»)'

  A) s每个成e进度N成的hijÎP月度[`5[`。

  $) Åx%,ùú指数™tuÅx;ÀM[`项目¼‘的绩效™#DM绩效的¥L。

  ) ùú 5050 Âá,ÌÄ`aT成本少¨项目成本。

  *)A5Pe个月的ïð™ƒ个月òïðH少e。

20   . &he $S   , estimates for each #or, pac,age   , and the net#or, diagram are

completed.hich of the follo#ing #ould e the C%G& thing for the project manager to do'

  A) Seuence the acti+ities.

  $) erif" that the" ha+e the correct scope.

  ) reate a preliminar" schedule and get the teams appro+al.

  *) omplete ris, management.

  $S每个QRS的估x™ñòóôŒXN成。σM项目XY2˜éwx'

  A) DEõö。  $) ©ª-.是÷ˆÌ。

  ) ‘â%的进度ÑÎŽcd成e认ö。  *) N成ûüqY。

21 . A project management plan should e realistic in order to e used to manage the

 project.hich of the follo#ing is the $%S& method to achie+e a realistic project management

 plan'A) Sponsor creates the project management plan ased on input from the projcot manager .

  $) Eunctional manager creates the project management plan ased on input from the project

manager .

  ) Project manager creates the project management plan ased on input from senior 

management.

  *) Project manager creates the project management plan ased on input from the team.

  项目qYÅÆ?@Á‚»øk!MqY项目。ƒ„…项是*+的žèMŽù»öÊ的项

目qYÅÆ'

  A) (UVú¨项目XY的ÇÈ‘项目qYÅÆ。

  $)µ÷XYú¨项目XY的ÇÈ‘项目qYÅÆ。

  ) 项目XYú¨UûqY¯的ÇÈ‘项目qYÅÆ。

  *) 项目XYú¨cd的ÇÈ‘项目qYÅÆ。

2-.*uring project execution,the customer authori<es and funds a scope change #hich

  reuires a major change in the schedule.&he aseline schedule .

  A) no# ecomes the ne# schedule , including the changes , and the original aseline is

disregarded

  $) is still the original aseline ut annotated to refleet that a change has ta,en place

  ) is amended to reflect the scope change, ut the original aseline is still maintained for postO

 project re+ie#  *) is meaningless since e+er" schedule update changes the aseline

Page 9: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 9/42

  P项目Éʼ½5,ú¬€/0-.ÎÙÉ^Uü,由MýM^项目进度的¥的/0。

á项目进度ú_  ,

  A) /]9的进度Ñ,S^/0,/进度ú_þ’ú

  $)ÿ然是/进度ú_,但7ê(ä,ì反映ŒXÕ`的/0

  ) 67ÙÉì反映-./0,但/进度ú_ÿ2维护ì=项目õÖª  *) ‰b±I®Ø,y]每一œ进度的09ôš—/进度ú_

22.All technical #or, is completed on the project.hich of the follo#ing remains to e done'

  A) erif" scope.   $) @is, response plan.   ) Staffing management plan.   *) >essons

learned

项目ab*+QRôN成^,σMéwx'

A) º»-.。  $) ÂÆûü2#。  )µeqYÅÆ。  *) X9:;

24 . 3ajor difficulties arise #hen multiple projects need to e managed in the functional

organi<ational structure ecause of .

  A) the le+el of authorit" of the project manager 

  $) conflicts o+er the relati+e priorities of different projects in competition for limited resources

  ) project team memers #ho are focused on their functional specialt" rather than on the project

  *) the need for the project manager to >lSe interpersonal s,ills to resol+e conflicts informall"

  rH个项目67Pµ÷á组织;Z5进ÊqY的K_,š()o¥的困p,y] DD 。

  A) 项目XY的‚b‚

  $) £的项目P竞争b‚的UŠ¼½5šÕ`冲突

  ) 项目Š组成e0@äµ÷l门的本µQR!是è项目b@的QR

  *) 67项目XYˆú个V¢ø÷Jœˆ•·ðø冲突

25.hich of the follo#ing is included in a project charter'

  A) Identification of ris,s.  $) or, pac,age estimates.  ) *etailed fesource estimates.  *) &he usiness need for the project.

  ƒ„…项S含P项目z½b'

  A) ýþ的ûü。  $) QRS估x。  )®¯的U料估x。  *) 项目356W。

2.Bou ha+e een #or,ing on a +er" large soft#are de+elopment project that has made use of 

o+er -20 people.Einall",all the scope of #or, is completed,it #ould e $%S& to .

  A) thro# a part" for the team memers $) ma,e sure the project is integrated #ith other 

 projects

  ) egin to focus on "our other projects *) anal"<e project S:%SS or failure

  ãçè^一个œK¥á的!"lÕ项目,˜项目涉Í超¼ -20 V。*õ,QR-.5的a

bQRôN成^,$K*+2  ̃ 。

  A) ]项目组成el个ã#  $) Ì认Oƒ$个项目是£tu项目A成P一起的

) lm@äã的tu项目  *) i,项目的成Úè失败

2=.&he project is not completed until .

  A) the project scope is completed.administrati+e closure is completed and pa"ment is recei+ed

  $) formal acceptance is recei+ed。and an" other reuirenlents for project closure as stated in the

contract are met

  ) the customer is satisfied and final pa"ment is recei+ed

  *) lessons learned are completed

  项目还‰bN成,¼t  。  A) 项目-.N成,qYcdRN成,Ý付的ðúŒct

Page 10: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 10/42

  $)ŒOˆ•ÏÐ,‚£5tu项目cd的6WôŒXO足

  ) «¬®,*终的ðúŒXct

  *) X9:;ON成

28.A1l of the follo#ing #ould occur during the closure of the project %G%P& .

  A) creating lessons learned $) formal acceptance  ) reducing resource spending *) performing enefit cost anal"sis

  ƒ„ô是项目cdKÕ`的,W^  。

  A) ‘X9:;  $) ˆ•ÏР )减少UŠùú  *) ÉÊc益成本i,

29.An output of close project is the creation of .

  A) project archi+es $) a prolect charter ) a project management plan *) a ris, anal"sis

 plan

 cd项目的Ç(Ù一是  。

  A) 项目YÆ  $) 项目z½  ) 项目qYÅÆ  *) ûüi,ÅÆ

40 .A project manager has just een assigned to a ne# project and has een gi+en the project

charter .&he EI@S& thing the project manager must do is .

  A) create a project scope statement

  $) confirm that all the sta,eholders ha+e had input into the scope

) anal"<e project ris, 

*) egin #or, on a project management plan

项目XY刚刚OiÎt9项目Ît^项目z½,σM项目XY¡2˜  。

A) ‘项目-.fg&  $) Ì认ab2V¿1ÇÈt-.

) i,项目ûü  *) lm编制项目qYÅÆ

41.A project manager is managing a fixed price (EP) contract.She thin,s that a large customerF

reuested change might impact the schedule of the project.hat should she do EI@S&'  A) 3eet #ith the sta,eholders.

  $) 3eet #ith the team.

  ) @enegotiate the remainder of the contract.

  *) Eollo# the change control s"stem.

  项目XYPqY一个固×价£,她认]«¬o¥的/0ŽWòvwt项目进度。她

¡2˜éwx'

  A) š见2V。  $) š见cd成e。 ) n09的‚£19谈判。  *)遵循/0Ë制–。

4-.&he client demands changes to the product specification that #ill add onl" t#o #ee,s to the

critical path.hich of the follo#ing is the est thing for the project manager to do'

  A) ompress the schedule to reco+er the t#o #ee,s.

  $) ut scope to reco+er the t#o #ee,s.

  ) 0nsuIt #ith the sponsor efore ta,ing an" action.

  *) Ad+ise the client of the impact of the change.

  «¬¿(#îï的/0,$ò±!"t@ABCe。ƒ„…项是项目XY*2˜é的'

  A)#$进度 -"。

  $)%减项目-.M减少 -"。

  ) P>±IÊEÙÚ~(UVÄW®见。

  *) `诉«¬$个/0的vw。

42.A project manager learns that correcti+e action #as implemented " a team memer , ut notdocumented.hat should the project manager do C%G&'

Page 11: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 11/42

  A) @eport the +iolation to the functional manager .

$) larif" the reasoning ehind the team memers action.

) Add the implemented correcti+e action to the historical record.

*) Eind out #ho caused the prolem.

项目XYÕ)项目cd»«的©ˆÊE‰bO'(。项目XY¡2˜éwx'A) [`$个&反&'êµ÷XY。

$)'(cd成e>$个ÊE)õ的/y。

)*±»«的©ˆÊEt+,'(e。

*) ª(-引Õ的$个s题。

44.Bou are assigned as the project manager in the middle of the project.&he project is #ithin

the aselines, ut the custoiner is not happ" #ith the performance of the project.hat is the

EI@S& thing "ou should do'

A) *iscuss it #ith the project team.  $) @ecalculate aselines.

) @enegotiate the contract.  *) 3eet #ith the customer .

ãOiÎt某个ÉÊt5T的项目e。项目Á‚ú_,ö是«¬#项目的绩效。ã

¡2˜éwx'

A) ™cd成e67M-。  $)19Åxú_。

)19谈判‚£。  *) š见«¬。

45   . &he pre+ious proiect manager for "our project managed it #ithout much project

organi<ation . &here is a lac, of management control and no clearl" defined project

deli+erales.hich of the follo#ing #ould e the $%S& choice for getting "our project etter 

organi<ed'

  A) Adopt a life c"cle approach to the project.   $) *e+elop lessons learned for each

 phase.  ) *e+elop specific #or, plans for each #or, pac,age .   *) *e+elop a description of the

 product ol the projectH

  ã项目的Ú±项目XYP‰bFH项目组织的&'ƒqY项目。B.qYË制,‰bgÌ

×Ø的项目成À。ƒ„…项是ùã项目t0+组织的*/ÑÒ'

  A) ]项目ÑÒ‚’的项目`aT。  $) ]每个EF_=X9:;。

  ) ]每个QRS_=f×的QRÅÆ。  *) ]项目îï编写¸¹。

4 . ompan" procedures reuire the creation of a lessons learned document . hich of the

follo#ing is the $%S& use of lessons learned'

  A) fiistorical records for future projects.

  $) Planning record for the current project.

  ) Informing the team aout #hat the project manager has done.

  *) Informing the team aout the project management plan.

 ²³£½7W‘X9:;X0。ƒ„…项*+·¸¹^X9:;的Rú'

  A) R]+,'(ú¨DM的项目。

  $) R])P项目的ÂÆ'(。

  ) ê成e¿1信°fg项目XYéwx^。

  *) ê成e¿1信°fg项目qYÅÆ。

4=.&he project manager has just recei+ed a change from the customer that does not affect the

 projeet schedule and is eas" to complete.hat should the project manager do EI@S&'  A) 3a,e the change happen as soon as posstie.

Page 12: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 12/42

  $) ontact the projeet sponsor for permissionH

  ) !o to the change control oard.

  *) %+aluate the other components of the1triple constraint2.

  项目XY刚ÏtMÀ«¬的/0,$òšvw项目进度Î34‹N成。项目XY2˜

¡éwx'  A)尽56/0Õ`。  $)7项目Õ起VŽ8ö。

  )‘/0Ë制âeš。  *) ÿ估²³´µ¶/的tuy>。

48 .A project manager recentl" re#arded an indi+idual #ith a promotion that carried #ith it a

+er" small salar" increase ut sustantiall" more responsiilit" .&he project manager appears

to e appealing to the emplo"ees need.

  A) monetar" $) ph"siological ) csteem *) self actuali<ation

  一个项目XY*“”Î9:^一个;e,<bœKŠ的QU±¡,但是=i·>?^

0H°±。项目XYçe‘@A足;e的  67。

  A)üB  $)`Y  )C1  *)ÀD»)

49 All of the follo#ing are parts of direct and manage project execution except .

A) identif"ing changes $) using a #or, rea,do#n structure

  ) implementing correcti+e actions *) setting up a project control s"stem

  ƒ„abô是指àèqY项目Éʼ½的一li,W^  。

A) ýþ/0  $) ùú $S ) »«©ˆª«  *) <Ï项目Ë制–

50.&he project charter for a project #as appro+ed for planning and "ou ha+e just een assigned

as project manager . @eali<ing that project planning is an ongoing effort throughout the

 project,#hich processes are "ou 3;S& li,el" to comine'

  A) reate $S and acti+it" definition.

  $) Acti+it" duration estimating and schedule de+elopment.  ) ?uman resource planning and cost estimating.

  *) ost estimating and cost udgeting.

  项目z½ŒXO×_,ã刚OiÎ]项目XY。认ýt项目ÂÆ67EF项目的†‡GJ,

…ë¼½ã*ö÷‚Î'

  A) ‘ $S ™DE×Ø。  $) DE+K估x™编制进度Ñ。

  ) VJUŠÂÆ™成本估x。  *) 成本估x™成本¥x。

51.Bou are ta,ing o+er a project and determine the follo#ing vActi+it" $ has an earl" finish

(%E) of da" 2 ,a late finish (>E) of da" ,and an earl" start (%S) of da" - .Actl+it+ > is

 eing done " a hard O toOget resource .&he cost performance index (PI) is 1.1 and the

schedule performance index (SPI) is 0.8.$ased on this information,#hat #ould "ou e more

concerned aout'

  A) E10at.  $) @esources.  ) ost.  *) Schedule.

  ãP°某个项目,çtÞƒ信°vDE $ *早;¶HT是› 2I,*J;¶HT是›

I,*早lmHT是› -I。DE >,œKptUŠ。成本绩效指数 PI 是 1.1,进度绩效

指数 SPI 是 0.8。ú¨e¹信°,ã67#…랟0H@ä'

  A) KK。  $) UŠ。  ) 成本。  *) 进度。

5-.If PI is 1.02 and A is 7000,ho# much is %'

  A) =7000.  $) 7180.  ) =7-00.  *) -00.

  ÞÀ PIÛ1.02,AÛ000,% 是H少'  A) =000。  $) 180。  ) =-00。  *) -00。

Page 13: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 13/42

52.hat does cost performance index (PI) less than 1.0 indicate'

  A) ost o+errun of the estimates.  $) ost according to the estimatesH

  ) ost underrun of the estimates.  *) %arl" progress.

  成本绩效指数 (PI)Š¨ 1 ®LQwx'

A) 成本超Ý。  $) 成本Á‚估x。  ) 成本Mµ。  *) P进度早T。54.hich of the follo#ing is not an example of constraints that can limit flexiilit" in the human

resource planning process'

  A) ;rgani<ational structure.  $) ollecti+e argaining agreements.

  ) %conomic conditions.  *) Acti+it" resource reuirements.

  ƒ„…项是vwVJUŠÂƼ½N)的制µy>的OP'

  A)组织;Z。  $) IUQž谈判Ø议。  ) XmR"。  *) DEUŠ6W。

55.hich of the follo#ing estalishes ualit" metrics'

  A) ualit" assuranceSualit" control.  $) ualit" planning.

  ) ualit" aseline.  *) ualit" chec,list.

  ƒ„…项úM‘í¡指¤'

  A) ¡Ä证™¡Ë制。  $) ¡ÂÆ。  ) ¡ú_。  *) ¡©ªS。

5.h" is it important to ha+e a project charter'

  A) It is the collection of all susidiar" project documents.

  $) &he project charter is the necessar" asis for all #or, pac,ages to e performed.

  ) It formall" authori<es the proiect.

  *) It trac,s the progress of the project.

  ]wx项目z½o17'

  A) y]cA^项目ab的T=XY。  $) 项目z½是ab7ÉÊ的QRS?7的úU。

  ) y]¾ˆ•€^项目。  *) y]¾VW项目的进度。5= . hich of the follo#ing are the most commonl" used performance measures of e+aluating

#hether or not #or, is eing accomplished as planned at an" gi+en point of time'

  A) PSA.  $) A,%+JP+.  ) SS.  *) SPI,%SA.

  ƒ„…项KúM衡¡项目的QR是÷Pf×KLgX/ÅÆN成'

  A) P ™ A。  $) A,% ™ P。  ) ™ S。  *) SPI,% ™ A。

58.If SÛO800,PÛ=7000,ho# much is %'

  A) 87000.  $) 7-00.  ) 97000 *) 7000。

  ÞÀ SÛO800,PÛ=000,% 是H少'

  A) 8000。  $) -00。  ) 9000。  *) 000。

59.As per P3$;K ,+arious executing processes fall into spedfic ,no#ledge areas.*e+elop

 project teamis a part of #hich of the follo#ing ,no#ledge areas'

  A) Project management integration.  $) Project procurement management.

  ) Project human resource management.  *) Project communications management.

 YÝ P3$;K ,£的Éʼ½Z¨£的ËýÌÍ。cd‘<Z¨…个ËýÌÍ'

  A) 项目ÉšqY。  $) 项目>?qY。  ) 项目VJUŠqY。  *) 项目¤JqY。

0.hat does estimate at complete mean'

  A) %ach anticipated cost for project.  $) %stimated a+erage cost at project completion.

  ) Anticipated total cost at project completion .   *) Anticipated expenses at project

completion.  NQ估x®LQ'

Page 14: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 14/42

  A) 项目的每个¥T成本。  $) 项目NQK估x的[\成本。

  ) 项目NQK的¥T:成本。  *) 项目NQK的¥TlÝ。

1.hich of the follo#ing indicates the acceptale range of +ariation of a process as represented

on the control chart'

  A) 3ean.  $) Specification limit.  ) @ule of se+en.  *) :pper and lo#er controllimits.

  ƒ„…项指(^PË制ó5¼½/¡的öÏÐ-.'

  A)[\Ü。  $) ÂÂ制。  )]gÂá。  *) Ë制e‚™ƒ‚。

- . hich of the follo#ing is the most common non eha+ioral reason for projects eing

completed ehind schedule and going o+er udget'

  A) Selecting a #rong person as the project manager .   $) Selecting a #rong person as the

sponsor .

  ) Accepting a high ris, project.  *) Inadeuatel" defined reuirements.

  ƒ„…项是*K见的àÂ项目进度^õ、成本超Ý的œÊ]/y'

  A)ÑÒ^0误的Vr项目XY。  $)ÑÒ^0误的VrÕ起V。

  ) ÏÐ^$ûü的项目。  *) ’r的6W×Ø。

2.Bou are in the close project process.Bou are engaged in the acti+it" to settle and close some

contract agreements estalished for the project.hich of the follo#ing acti+ities are "ou into'

  A) Administrati+e closure.  $) ontract closure.  ) Project executing.  *) Planning.

  ãPcd项目¼½。ãP进ÊëDEMN成项目5的一ë‚£Ø议。ƒ„…个DE是ãˆP

进Ê的'

  A) qYcd。  $) ‚£cd。  ) 项目ÉÊ。  *) ÂÆ。

4.In an oject diagram,the name of an oject is .

  A) in old $) in italics ) underlined *) none of these  P#_ó5,#_的`a  。

  A) úbšÑÓ  $) úcšaÑÓ  ) úƒdeÑÓ  *) ìeô#

5.As per P3$;K ,all are parts of the executing process group except .

  A) acuire project team $) de+elop project team ) information distriution *) identif"

sta,eholder 

 YÝ P3$;K ,ƒ„¼½ô是Éʼ½组的li,W^  。

  A)组‘项目cd  $) ‘<cd  )信°Õ¶  *) ýþ项目2V

.&he close project process is a part of #hich of the follo#ing project management ,no#ledge

areas'

  A) project scope management.  $) project integration management.

) project time management.  *) project communication management.

  项目cd¼½是ƒ„…个项目qYËýÌÍ的li'

A) 项目-.qY。  $) 项目ÉšqY。  ) 项目KLqY。  *) 项目¤JqY。

=.hile e+aluating the !antt chart,the project manager determines that the project is ehind

schedule.hat should she do'

  A) ;tain appro+al from the customer to slip the project $) @eport findings to

management.

  ) %+aluate the alternati+es #ith the team.   *) %+aluate the alternati+es #ith the

customer .  rÿ估ffóK,项目XYÕ)项目^õ¨进度,她2˜éwx'

Page 15: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 15/42

  A) Ž«¬的×_‘±g项目。  $) ~qY¯[`Õ)。

  ) ™cd成eÿ估öÑžÆ。  *) ™«¬ÿ估öÑžÆ。

8.hich of the follo#ing is not used in the ualit" control process'

  A) !antt charts.  $) ontrol charts.  ) Pareto charts.  *) Statistical sampling.

  ƒ„…项Oú¨¡Ë制¼½'  A)ffó。  $) Ë制ó。  )hijó。  *) –Åk¹。

9.hich of the follo#ing $%S& descries a project management plan'

  A) A print ;ut from project management soft#are.

  $) A ar chart.

  ) @is, management,staffing, process impro+ement and other management plans.

  *) &he project scope.

  ƒ„…项*+·¸¹^项目qYÅÆ'

  A) 项目qY!"的lmÇ(。  $)nßó。

  ) ûüqY、µe、¼½—进™tuqYÅÆ。  *) 项目-.fg&。

=0.Bou are a ne# project manager #ho has ne+er managed a project efore .Bou ha+e een

as,ed to plan a ne# project.It #ould e $%S& in this situation to rel" on during planning in

order to impro+e "our chance of success.

A) "our intuition and training $) sta,eholder anal"sis

) historical information *) configuration management

ã是个9的项目XY,ÚkDqY¼项目。ãO7WÂÆ9的项目。P$%&'ƒ,ã*

+op  M¿$ã成Ú的rq。

  A) ã的¼r™st  $)2Vi,  )+,信°  *)ÎÏqY

=1.A particular sta,eholder has a reputation for ma,ing man" changes on projects .hat is the

$%S& approach a project manager can ta,e at the eginning of the project to manage thissituation'

  A) Sa+no/to the sta,eholder a fe# times to dissuade him from sumitting more changes.

  $) !et the sta,eholder in+ol+ed in the project as earl" as possile.

  ) &al, &o the sta,eholders oss to find #a"s to direct the sta,eholders acti+ities to another 

 project.

  *) As, that the sta,eholder not e included in the sta,eholder listing.

  某个项目2VKKP项目e¿(/0。ƒ„…项是项目XYöìP项目lmK>ú的q

YM&´的*+žè'

  A) ~$个2Vf,uvu¿(0H/0。

  $)尽早6项目2Vçèt项目5。

  ) 82V•€¢£,8(žè62V‘tu项目。

  *)ŽWò2Vk2V(S5wW。

=-.@euirements documentation is an input to .

  A) scope control and scope +erification

  $) direct and manage project execution and integrated change control

  ) de+elop project management plan and de+elop project charter 

  *) de+elop project management plan and schedule de+elopment

  6WX"是  的ÇÈ。

  A) -.Ë制™º»-.  $) 指àèqY项目Éʙɚ/0Ë制  ) 制x项目qYÅÆ™制R项目z½  *) 制x项目qYÅÆ™编制项目进度Ñ

Page 16: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 16/42

Page 17: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 17/42

in'

  A) Planning.  $) %xecuting.  ) 3onitoring and controlling.  *) losing.

  项目XY7Ì认项目的îïŒXYÝ项目qYÅÆON成。项目XYP…个项目qY¼½

5'

  A) ÂÆ。  $) ÉÊ。  )„Ë。  *)cd。80 .A project manager does not ha+e much time to spend planning efore the mandator" start

date arri+es.?e therefore #ants to mo+e through planning as effecti+el" as possile .hich

of the follo#ing #ould "ou recommend'

  A) 3a,e sure "ou ha+e a completed preminar" project scope statement and then start the

$S.

  $) reate an acti+it" list efore creating a net#or, diagram.

  ) *ocument all the ,no#n ris,s efore "ou document the highOle+el assumptions.

  *) Einali<e the ualit" management plan efore "ou determine ualit" metrics.

  项目XYPÛ制lmHTtMÙÚ‰bFHKLöìú¨ÂÆ,uä望尽ö÷ùÂƼ½

/b效q。ãò›ƒ„…项'

  A) ÌÄãN成â%-.fg&Îlm‘ $S。

  $) P‘ñòóÙÚ‘DE„Ñ。

  ) Pã'(ƒ$¯œ的‚<ÙÚ'(ƒabŒË的ûü。

  *) PãÌס指¤ÙÚÌ×项目¡qYÅÆ。

81 . &he $S and $S dictionar" are completed . &he project team has egun #or,ing on

identif"ing ris,s.&he sponsor contacts the project manager , reuesting that the responsiilit"

assignment matrix e issued.&he project has a udget of :.S.

  610 , 000 and is ta,ing place in three countries using 14 human resources &here is little ris, 

expected for the project and the project manager has managed man" projects similar to thisone.hat is the next thing to do'

A) :nderstand the experience of the sponsor o* similar projects.

$) reate an acti+it" list.

) 3a,e sure the project scope is defined.

*) omplete ris, managenlent and issue the responsiilit" assignment matrix

项目的 $S ™ $SaƒŒXN成。项目cdlmýþ项目ûü。项目(UV7项目X

Y,7WÕ¶µ°iÎ[\。$个项目¥x 100 000 ßà,P²个„ÈQR,ùú 14 个V

JUŠ。项目XYqY¼一ë|…的项目,M项目ûü½Š。σM2˜éwx'

A) Yð(UVP|…项目e的X9。  $) ‘DE„Ñ。

) Ì认项目-.O×Ø。  *) N成ûüqY,Õ¶µ°iÎ[\。

8- . &he high O le+el project schedule constraints ha+e just een determined . hat project

management process group are "ou in'

  A) Initiating.  $) Planning.  ) %xecuting.  *) 3onitoring and controlling.

 r7的项目进度µ¶刚刚OÌ×。ã)PP…个项目qY¼½组'

  A)E。  $) ÂÆ。  ) ÉÊ。  *)„Ë。

82.&he project sponsor has just pro+ided the project charter .hat is the C%G& thing to do'

  A) $egin to complete #or, pac,ages.  $) omplete scope +erification.

  ) Start integrated change control.  *) Start to create managernent *lans.

  项目(UV刚刚¿1项目z½,σM67éwx'  A) lmN成QRS。  $) N成º»-.。  ) lmÉš/0Ë制。  *) lm‘qYÅ

Page 18: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 18/42

Æ。

84.hich of the follo#ing is C;& an input to the initiating process group'

  A) ompan" processes.  $) &he compan" culture ) ?istorical $Ss.  *) Project

scope statement.

ƒ„…项是E¼½组的ÇÈ'A)²³¼½。  $)²³Xh。  )+,$S。  *) 项目-.fg&。

85.&he person #ho should e in control of the project during project management planning is

the .

A) project manager $) team memer ) functional manager *) sponsor 

P项目qYÂÆK?@iÎt†MË制项目的是  。

A) 项目XY  $) cd成e  )µ÷XY  *) (UV

8.A detailed project schedule can e created onl" after creating the .

A) project udget $) #or, rea,do#n structure ) project management plan *)

detailed ris, assessment

®¯的项目进度<bP‘  Ùõ‡öìO‘。

A) 项目¥x  $) QRið;Z  ) 项目qYÅÆ  *)®¯的ûüÿ估

8= . &he project team has just completed the initial project schedule and udget . &he C%G&

thing to do is .

  A) egin ris, identification $) egin iterations

) determine communications reuirements *) create a ar (!antt) chart

项目cd刚刚N成*â的项目进度™¥x,ƒ一%67 

A) lmûüýþ  $) lm1å  ) ÌפJ6W  *) ‘nß (ff)ó

88.&he project charter is created in #hich project management process group'

  A) %xecuting.  $) Planning.  ) losing.  *) Initiating  项目z½是P…个项目qY¼½组‘的'

  A) ÉÊ。  $) ÂÆ。  )cd。  *)E。

89 . Cear the end of "our last project , additional reuirements #ere demanded " a group of 

sta,eholders #hen the" learned the" #ould e affected " "our projeet . &his ecame a

 prolem ecause "ou had not included the time or cost in the project management plan for these

reuirements . hat is the $%S& thing "ou can do to pre+ent such a prolem on future

 projects'

  A) @e+ie# the $S dictionar" more thoroughl",loo,ing for incomplete descriptions.

  $) @e+le# the project charter more thoroughl",examining the usiness case

) *o a more thorough jo of contract planning.

*) Pa" more attention to sta,eholder management.

ã°的项目5;¶^,一ë项目2VÕ),$个项目ò#u们造成一ëvw,]M

u们¿(^一ë:;的6W。$n()^s题,y]ãP项目qYÅÆ5ÎD]$ë:;

的6W考~成本¬进度žŸ的ÂÆ。]避免|…s题PDM的项目5þœ(),ã*2˜

éwx'

A) 0±ˆ‰Š¯·ÿÖ$Saƒ,ìª8tŒëNÉ的¸¹。

$) 0±ˆ‰Š¯·ÿÖ项目z½,쩪()5~‹Œ的·ž。

) 0±ˆ‰Š¯·é+‚£ÂÆQR。

*)ƒ0H的JŽP项目2VqYe。90.&he soft#are de+elopment project is not going #ell .&here are o+er 20 sta,eholders,and

Page 19: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 19/42

no one can agree on the project ojecti+es .;ne sta,eholder elie+es the project can achie+e a

20 percent impro+ement #hile another elie+es a 50 percent impro+ement is possile . &he

 project manager thin,s a 10 percent impro+ement is more realistic .hat is the $%S& course

of action'

  A) 3o+e for#ard #ith the project and loo, for more information later to settle the issue.  $) A+erage the numers and use that as an ojecti+e.

  ) Perform a feasiilit" anal"sis.

  *) As, the sponsor to ma,e the final decision.

  某个!"lÕ项目进\Î+。̃ 项目b 20 H个项目2V,¥È#项目目¤‰b成

一Â的çè。一个项目2V认]项目öìt 20L的—进效À,!;一个认]t

50L是ö÷的。项目XY‘认] 10L的—进效À相#Mf0±)»。Ÿ#$%&',*2

˜>的ÊE是'

  A)’‡“Ú›进$个项目,”õþcA0H的信°ìðø$个s题。

  $)x($ë数a的[\Ü,ÎìM]一个目¤。

  ) 进ÊöÊ)i,。

  *)6项目(UVé*õ的ø×。

91 . hen chec,ing the calendar of a team memer to schedule a meeting , "ou see she has

scheduled a meeting #ith a ,e" sta,eholder that "ou #ere not informed of  . &he $%S&

approach #ould e to .

  A) a+oid mentioning it to the team memer ut continue to #atch her acti+ities

  $) notif" "our oss aout the prolem

) address the concern #ith the team memers oss

*) address the concern #ith the team memer 

ãˆlxõ一个š议,r©ª一个cd成e的H+K,ãÕ)她ŒXè一个@A项目2V¥x^一个š议,!ã#$一gÎË&。ã*2˜é的-&是  。

A)避免P$†成eŸÚ¿Í$"-,但是’‡„Ë她的DE

$)ƒ$个s题`诉êã的•€

)è$†成e的•€#}

*)è$†成e#}

9-.Bou are in the middle of a ne# product de+elopment for "our pulicl" traded compan" #hen

"ou disco+er that the pre+ious project manager made a :.S. 6270007000 pa"ment that #as not

appro+ed in accordance #ith "our compan" policies .>uc,il",the project cost performanee

index (PI) is 1.-.hat should "ou do'

  A) ontact "our manager .

  $) Put the pa"ment in an escro# account.

  ) $ur" the cost in the largest cost center a+ailale.

  *) Ignore the pa"ment.

  ãˆP]ãaP的²¢–‹²³5的9îïlÕ项目!—˜,$K,ãÕ)ìÚ的项目X

YÝ付^Oj$ 2 000 000 ßà的ðú,!$™ðúΉb遵循ã²³的šÐ。›ˆ的

是,项目的成本绩效指数 (PI) 是 1.-。MKã2˜œxé'

A)7òã的XY。

$) ò$™Ý(¨›²žÄqž¬5。

) ò$™Ý(Ÿtöú的*¥成本5¡。*)¢£$™Ý(。

Page 20: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 20/42

92.%+en though "ou are a project manager in a pharmaceutical compan","ou ha+e #or,ed as a

scientist in the industr" for se+eral "ears .Bour suordinates loo, up to "ou for guidance and

ad+ice.&he po#er that "ou ha+e o+er "our suordinates is .

A) referent $) expert ) legitimate *) re#ard

ã)P是某个制¤²³的项目XY,MÚãŒXR]¥¦ÈPMÊ5QRH年。ã的ƒZC§ãÎŽã的‘议™指à。ãa¨b的J是  J。

A)ç考  $)ÇÈ  ) ‚è  *) “”

94 . &he follo#ing information is a+ailale aout a particular tas, in "our project plan veari"

start (%S) ,-5 da"s;late start (>S) ,20 da"s;earl" finish (%E) ,50 da"s;late finish (>E)

,55 da"s.$ased on this information,"ou can deduce that .

A) the project float is 5 da"s $) the project ma" get dela"ed

) the tas, is not on the critical path *) the tas, ls on the critical *ath

@¨ã项目ÅÆ5的某个DEbÞƒ信°v*早lm  (%S) -5I;*Jlm (>S) 20I;

*早;¶ (%E) 50I;*J;¶ (>E) 55I。ú¨$ë信°,ãöìi,(  .

A) 项目的KK是 5I  $) 项目ö÷O©误

) $个±~P@ABCe  *) $个±~P@ABCe

95.*uring acti+it" seuencing,"ou identif" and document interacti+it" dependencies.All the

tollo#ing are outputs from acti+it" seuencing process %G%P& .

  A) project schedule net#or, diagrams $) acti+it" attriute updates ) reuested changes

*) milestone list

  PDEõöTL,ãýþÎ'(DE的op@。ƒ„ª项ô是DEõö¼½的Ç(,W

^  。

A) 项目进度ñòó  $) DEZ)09  )ŽW的/0  *) ½«„Ñ

9.Bou are managing tooling for an aircraft part.Bour team memers tell "ou that the" found afe# defecti+e parts.hen "ou as,ed them the reasons for the defect ,the" mentioned that it

could ecause of se+eral reasons including the material used   , the measurement

s"stem,inaccurate tolerances in the machine or other factors.&o help them to illustrate etter 

ho# +arious factors might ha+e contriuted to the defect,"ou #ill .

A) use a control chart $) create a flo#ehart

) dra# a fishhone diagram *) dra# a Pareto chart

ãPqY¬®的±Q。ã的cd成e`诉ãu们Õ)少8BC。rã¯su们BC的/

yK,u们¿Íö÷boH/y,Sùú的°料、衡¡–、Ô®0误的4K¬tuy

>。]^§¨u们0+·fg…ë/yö÷引ÕBC,ã2˜  。

A) ùúË制ó  $) ‘£½ó  )±制²³ó  *)±制hijó

9=.Bou are managing a project in a foreign countr".#here "ou reali<e that "ou #ill ha+e to pa"

a fee to some go+ernment agencies to get "our #or, done.Bou should .

A) pa" the fee to the go+ernment agencies

$) refuse to Pa+ the fee ecause the" are ries and hence unethical

) instead of pa"ing the fee , "ou pro+ide small gifts to go+ernment officials to get their 

support

*) ma,e a case for #h" fees should e paid to go+ernment agencies , and present it to "our 

management

ãP;„qY某个项目,PŒã认ýtã67Ý付ðúêš´ÔZk!lmã的QR。ã2˜  。

Page 21: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 21/42

A)Ý付ðúêš´ÔZ

$)]^Ý付ðú,y]$是ʵ,是߶的

) Ý付ðú,·¸žÆ是¿1빺ꚴ»eìŽu们݆

*)写(M]wx7Ý付êš´ÔZðú,~ã的qY¯Z[

98 . Bou are the project manager responsile for de+eloping a soft#are application ased oncustomer reuirements. As the customer reuirements ,eep changing freuentl" ,#hat tool

can "ou use to conduct integrated change control of "our project'

  A) Project selection methods.  $) Additional planning.

  ) orrecti+e action.  *) Project management information s"stem.

  ã是项目XY,°ú¨«¬6WlÕ2ú!"。考~t«¬的6W¼½/0,ãò]ã

的项目PÉš/0Ë制5ùúwxQ™'

  A) 项目ÑÒžè。  $) :;的ÂÆ。  )©ˆª«。  *) 项目qY信°–。

99.ost of ualit" is the total cost of all efforts to achie+e productser+ice ualit",and ineludes

all #or, to ensure conformance to reuirements . All of the follo#ing are costs that are

incurred %G%P& .

  A) ost of poor ualit" $) opportunit" cost ) external failure ost *) appraisal ost

  ¡成本是ab»)îï}~¡aïð的成本,SabÌÄè6W一Â的QR。ƒ„

ô是¡成本,W^  。

  A)Ê¡成本  $) Ôš成本  ) ;l失败成本  *) ©ª成本

100.In "onr project,"ou use thede+elop project teamprocess to impro+e the competencies

and interaction of team memers to enhance project performance . &he outputs from this

 process are .

A) project staff assignments $) team performance assessment

) staffing management plan *) project staff assigtmaents , staffing management plan,team performance assessment

Pã的项目5,ãùúcd‘</¼½M—进cd成e的÷J™互Eì¿$项目绩效。$

个¼½的Ç(是

A) 项目µeiΠ $) cd绩效衡¡

)µeqYÅÆ  *) 项目µeiÎ,µeqYÅÆ,cd绩效衡¡

101.&he method of constructing a project schedule net#or, diagram that represents

acti+ities and connects then to sho# the all dependencies is ,no#n as .

A) precedence diagramming method $) acti+it" list

) arro# diagramming method *) schedule net#or, templates

÷¾\ÓabDE的op@。

A) P*3 (Úàó) $) DE„Ñ  ) A*3 (¿eó) *) 进度ñò模€

10-.hich of the follo#ing acti+ities is not concerned #ith de+eloping the project charter'

  A) Project justification.  $) ollecting output of the planning processes.

  ) urrent understanding of the customers need.  *) *ocumenting the usiness needs.

  ƒ„…项DE™制×项目z½À@'

  A) 项目7证。  $)cAÂƼ½组的Ç(。  ) Yð«¬的6W。  *)'(356W。

102.hich of the follo#ing is not a tool of the acti+it" definition process'

  A) @olling #a+e planning.  $) ontrol account.  ) *ecomposition.  *) &emplates.

  ƒ„…项是DE×ؼ½5的Q™'  A)ÁE•ÂÆ。  $) Ë制ž¬。  ) ið。  *) 模€。

Page 22: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 22/42

104 . hat is the process for aggregating the estimated costs of indi+idual acti+ities or #or, 

 pac,ages to estalish a cost aseline ,no#n as'

A) ost assessment .   $) *etermine udget .   ) Plan contracting .   *) ost

estimating.

ƒ„…个¼½ZA每个DE™QRS的估x成本M‘í成本ú_'A) 成本估Å。  $) 制×¥x。  ) ÂÆ‚£。  *) 成本估x。

105.;ut of the follo#ing definitions of a project sta,eholder ,#hich one do "ou thin, is most

appropriate'

  A) An enterprise #hose emplo"ees are directl" in+ol+ed in doing the project #or, .

  $) An entit+ #hose interest ma" e affected as a result of the project execution.

  ) An entit+ that performs acti+ities to accomplish ojecti+es.

  *) ;ne #ho is responsile for managing the project.

  ƒ„…个@¨项目2V的×Øã认]*Âr'

  A) 某个85,teQ¼Ïçè项目的QR。  $) 某个个V¬组织,tÃ益šÐt项

目ÉÊ的vw。

  ) 某个个V¬组织,ÉÊN成项目a67的DE。  *)°qY项目的个V。

10.In #hich of the follo#ing organi<ational structures,do project managers ha+e high or total

authorit"'

  A) Eunetional organi<ation.  $) $alanced matrix organi<ation.

  ) 3atrix organi<ation.  *) Projecti<ed organi<ation.

  ƒ„…个组织;Z5,项目XYb*$的J'

  A)µ÷á。  $)[衡[\。  )[\组织。  *) 项目á组织。

10=.hich of the follo#ing is not a toolStechniue of the de+elop project charter process'

  A) %arned +alue method.  $) Project selection methods.  ) Project management information s"stem.  *) Project management methodolog".

  ƒ„…项是制×项目z½¼½的Q™™*+'

  A) »)Üžè。  $) 项目ÑÒžè。  ) 项目qY信°–。  *) 项目qYžè7。

108.In #hich phase of the project life c"cle,are cost and staffing le+els high'

A) Intermediate stage.  $) Einal stage.  ) Pre intermediate stage.  *) Initial stage.

P…个项目`aT的EF,成本™UŠÄÈ*$'

A)5LEF。  $) *终EF。  )5LÅÚEF。  *)EEF。

109.ho is responsile for completing the lessons learned documentation'

  A) Project team.  $) Sponsor .  ) Project architect.  *) Project manager .

 -°N成X9:;XY'

  A) 项目cd。  $) Õ起V。  ) 项目<ÅÆ。  *) 项目XY。

110.&o manage a project including .

  A) identit" the reuest and ma,e sure the clarit" and achie+ale aim

  $) alance the reuest of ualit",scope,time and fee

  ) ma,e the technolog" regulation explaination, plan and means e fit for different reuests and

expectation of all ,inds of sta,eholders

  *) all of ao+e

qY一个项目S  。

A) ýþ7W™Ì×(Ç!È÷¾»)的目¤$)[衡¡、-.、KL™ðúžŸ的7W

Page 23: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 23/42

) ù*+Â×fg&、ÅÆ™žè’‚¨ab2V的£6WèT望

*) ìeÉlÑ项

111.%xecuting processes are concerned #ith .

  A) recogni<ing that a project or phase should egin

  $) coordinating people and other resources to carr" ;:t the plan  ) de+ising and maintaining a #or,ale method to accomplish the usiness need that the project

#as underta,en to address

*) ensuring that the project ojecti+es are met " monitoring and measuring progress and

ta,ing correcti+e action #hen necessar"

Éʼ½组  。

A) Ž项目¬项目EFE的认ö

$)ØÙVJ™tuUŠN成项目ÅÆ

) <Å™维†öùú的žèMt项目*âa¥T的356W

*)J¼„€èË制¼½ÌÄ项目目¤的»),?7K>©ˆÊE

11-.Eor an acti+it",the optimistic,most li,el" and pessimistic estimates are 1- ,1 and 18

respecti+el".hich of the follo#ing statement is correct'

  A) &here is 8.-Lchance that the acti+it" #ill e completed in 15 to 1= da"s.

  $) &here is 95.44Lchance that the acti+it" #ill e completed in 15 to 1= da"s.

  ) &here is 8.-Lchance that the acti+it" #i? e completed in 14.= to 1.= da"s.

  *) &here is 92.=2Lchance that the acti+it" #ill e completed in 15 to 1= da"s.

  某个DE,*ÊË的估x是 1-;*ö÷估x是 1;*ÌË估x是 18。ƒ„…个fè是ˆ

Ì的'

  A) b 8.-L的rq,DEòP 15Í1=IÙbN成。

  $) b 95.44L的rq,DEòP 15Í1=IÙbN成。  ) b 8.-L的rq,DEòP 14.=Í1.=IÙbN成。

  *) b 92.=2L的rq,DEòP 15Í1=IÙbN成。

112.alculate the standard de+iation of a tas, if ;Û4,PÛ10,3Û.

  A) 1.  $) 12.  ) -5.  *) -2.

  ÞÀ*ÌË估ÅÛ10,*ÊË估ÅÛ4,*ö÷估ÅÛ,Žs¤_K是'

  A) 1。  $) 12。  ) -5。  *) -2。

114.Bou are ioo,ing at the follo#ing data.Project A has a PI of 0.8 and SPI of 1.- and % of 

450 . Project $ has PI of 1.- and SPI of 0.8 and % of 50 . hich of the follo#ing

statement is true'

  A) Project $ is performing etter ecause it has a higher earned +alue.

  $) Project A has schedule slippage and project $ is ahead of schedule.

  ) rashing project A is a good option.

  *) rashing project $ is a good option. 

ãP烄数Ý。项目 A 的 PI 是 0.8,SPI 是 1.-,% 是 450;项目 $ 的 PI 是 1.-,SPI

是 0.8,% 是 50。ƒ„…个fè是ˆÌ的'

  A) 项目 $ 5绩j½+,y]¾的 % j½$。

  $) 项目 A 的进度^õ,项目 $ 进度¿Ú。

  )ÎQ项目 A 是0的ÑÒ。

  *)ÎQ项目 $ 是0的ÑÒ。115.hich of the follo#ing is C;& a method for progress reporting for #or, pac,ages'

Page 24: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 24/42

  A) Percent complete.  $) East trac,ing.  ) -080 rule.  *) 5050 rule.

ƒ„…项是QRS[`进度K>ú的žè'

A) N成hij。  $)5gV进。  ) -080 Âá。  *) 5050 Âá。

11.Bou are the project manager of a large soft#are de+elopment project .&here is a conflict

 et#een t#o module leads on #here the changes ha+e to e rnade.Bou inter+ene and tell themthe importance of getting the project on time and as, them to find a solution #hich is acceptale

to oth of thern.hich conflict resolution techniue are "ou using here'

  A) onfronting.  $) ompromising.  ) Smoothing.  *) Eorcing.

  ã是个¥á!"lÕ项目的项目XY。!个模Ï组GÙLPwx·žé/0e()^冲突。

ãÐÈ`诉u们XKN成项目的17),7Wu们8(Qžô÷ÏÐ的žÆ。ãP$ù

ú的是…%冲突ðøžÆ' 。

  A)Ÿ#。  $)ÑØ。  )Ù™。  *)Û制。

11=.$ased on the net present +alue (CP) .#hich project "ou #ill choose'&he CP of project

Av 6-57000, project $v 657000, project v 6407000, project *v 6257000.

  A) Project A.  $) Project $.  ) Project .  *) Projdct *.

  ú¨ CP (Ò)Ü) ãšÑÒ…个项目'项目 A 的 CP 是 -5000 ßà;项目 $ 的 CP 是

5000 ßà;项目 的 CP 是 40000 ßà;项目 * 的 CP 是 25000 ßà。

  A) 项目 A。  $) 项目 $。  ) 项目 。  *) 项目 *。

118.#hich of the follo#ing is the $%S& tool for sho#ing the team the project schedule status

during project execution'

  A) 3ilestone chart.   $) !antt chart.   ) or, rea,do#n structure.   *) Cet#or, 

diagram.

  ƒ„…个是P项目ÉÊTLúM\Ó项目进度{|的*+的Q™'

  A) ½«ó。  $)ffó。  ) QRið;Z。  *)ñòó。l19 . An organi<ation structure that in+ol+es +arious organi<ational t"pes at +arious le+els is

called a .

  A) strong matrix $) alanced organi<ation ) composite *) alanced matrix

  一%P£¯Ÿe™b£的组织|á的组织;ZOÕ]  。

A)Û[\  $)[衡组织  ) å‚á  *)[衡[\

1-0.ho has the highest cost ris, in ease of a fixed price contract'

  A) $u"er .  $) Seller .  ) Sponsor .  *) &eam.

  P固×价£b-bQ*$的成本ûü'

  A)Óž。  $)Ôž。  ) (UV。  *) cd。

1-1.Bou are in the de+elopment phase of a soft#are project and meeting the de+elopinent team

to collect the status.Bou #ant to sho# the team memers the actual dependencies of different

tas,s.hich scheduling tool "ou #ill e using to explain them (choose the est ans#er) '

  A) 3ilestone chart.  $) Elo# chart.  ) Cet#or, diagram.  *) !antt chart.

  ãP!"项目的lÕEFš见lÕcdMcA项目{|。ã#~cd成e\Ó£±~Ù

L的ÕÖ@。…个进度Q™öìúPM¼½ (ÑÒ*+的ÅÆ) '

  A) ½«ó。  $)£½ó。  )ñòó。  *)ffó。

1--.hich of the follo#ing is C;& an input to monitor and control project #or,'

  A) Project management plan.  $) %nterprise en+ironmental factors.

  ) hange reuests.  *) Performance reports.  ƒ„…项是„Ë项目QR的ÇÈ' .

Page 25: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 25/42

  A) 项目qYÅÆ。  $)-5jky>。  ) /0ŽW。  ) 绩效[`。

1-2.Bou are the project manager for soft#are de+elopment project .&he feasiilit" stud" can

start an" time and ta,es 1 #ee, and reuirement gathering ta,es - #ee,s #hich can start onl"

after feasiilit" stud" . &he design and test plan de+elopment can start in parallel after the

reuirements gathering . &est plan preparation ta,es 8 #ee,s follo#ed " a re+ie# " thecustomer and the time estimated for re+ie# is 1 #ee, .After the re+ie#,&est data preparation

ta,es #ee,s.*esign ta,es #ee,s and it is follo#ed " de+elopment and unit testing .for 

one module it ta,es - #ee,s and for the other module it ta,es - #ee,s . &here are no

dependencies et#een modules and the" can e de+eloped simultaneousl" . After test data

 preparation and de+elopment and unit testing of oth the modules , there is - #ee,s s"stem

testing.hat is duration of the critical path'

  A) 14 #ee,s.  $) 15 #ee,s.  ) -0 #ee,s.  *) 19 #ee,s.

  ã是!"lÕ项目的项目XY。öÊ)×ØöP±IKLlm,67ïð 1";6WcA

?@PöÊ)×ØN成Ùõ进Ê,67ïð -"。<Å™L试ÅÆlÕöìP6WcAõ

΄进Ê。L试ÅÆ_=67ïð 8",σM是«¬ÿ估,«¬ÿ估¥Åïð 1"。ÿ

估Ùõ,L试数Ý_=67ïð "。<Åïð ",ÏQ是lÕ™SàL试,t5一个

模Ïïð -",一个模Ïïð -"。模ÏÙL‰bop@,öì£KlÕ。L试数Ý

_=™lÕ™SàL试Ùõ,b -"的–L试。项目@ABC的+K是H少'

  A) 14"。  $) 15"。  ) -0"。  *) 19"。

1-4 . Bou are #or,ing on a soft#are de+elopment project and there is 0L proailit" that

de+elopment #ill e completed " the ptanned date and =0Lproailit" that testing #ill e

completed " the planned date .hat is the proailit" that de+elopment and testing #ill e

completed as per scheduleÙ

  A) 5L.  $) 4-L.  ) L.  *) 2L.  ãQRP一个!"lÕ项目e,lÕQRb 0L的rqXÅÆHTN成;L试QRb

=0L的rqXÅÆHTN成。lÕ™L试QRôXyÅÆHTN成的rq是H少'

  A) 5L。  $) 4-L。  ) L。  *) 2L.

1-5.hich of the follo#ing statements is C;& true'

A) Integration in+ol+es effecti+el" integrating processes among the project.

  $) Integrated change control includes re+ie#ing and appro+ing all change reuests.

) &he project preliminar" scope statement pro+ides a high le+el scope narrati+e.

*) &he project management plan is an input in de+eloping the preliminar" project scope

statement.

ƒ„…个fè是ˆÌ的'

A)Ú‚Sb效·É‚项目ab¼½。  $)Éš/0Ë制Sÿ估、Ö×ab/0

ŽW。

) 项目â%-.fg&¿1½r7的-.fg。  *) 项目qYÅÆ是制×â%-.fg

&的ÇÈ。

1-.%stimate at completion (%A) is .

  A) actual ost (A) Û udgeted cost ($) $) actual cost (A) Ûestimate to complete

(%&)

) udgeted cost ($) Oactual cost (A) *) actual cost (A) O planned +alue (P)

NQ估x是 DD 。  A) »ø成本 (A)Û¥x成本 ($) $) »ø成本 (A)ÛNQÜ6估x (%&)

Page 26: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 26/42

Page 27: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 27/42

in a metrics organi<ation'

  A) :pdate the details in #or, product information and share that #ith functional manager .

  $) :pdate the details in performance measurement aseline and share that #ith functional

manager .

) ?a+e an informal discussion #ith the team memer to find out the reason.*) Eormall" communicate the slippage from the team memer to the functional manager and

reuest him to discuss #ith the emplo"ee to ensure that this #ill not happen in the future.

P项目{|še,ãÕ)b个cd成e‰bN成u2˜P本"N成的±~。ãR]Pˆ•

的组织5的项目XY2˜>wxÊE'

A) 09®¯的±~îï信°Î¢àêµ÷XY。

$) 09®¯的绩效衡¡ú_΢àêµ÷XY。

) ™Œ个cd成e进Êœˆ•的67,8(áâ的/y。

*) ˆ•™qY˜cd成e的µ÷XY¢£,Žu™u的µe谈}ìÌÄDMþÕ`$

%&'。

124.@euest seller responses and select sellers is associated #ith #hich process group'

  A) Planning.  $) Procurement 3anagement.  ) Initiating.  *) %xecuting.

  ŽÔžw2™ÑÒÔžZ¨…个¼½组'

  A) ÂÆ。  $) >?qY。  )E。  *) ÉÊ。

125.In #hich t"pe of organi<ation is the project managers role most li,el" partOtime

  A) Eunctional.  $) ea, matrix.  ) Strong matrix.  *) A and $.

  ƒ„…个组织;Z5项目XY*ö÷是ãµ的'

  A)µ÷á。  $)ä[\。  )Û[\。  *) A ™ $。

l2.hich of the follo#ing is the est use of lessons learned'

  A) Planning record for the current project .   $) &o impress the senior management.

  ) Informing the team aout #hat mista,es team has made.  *) ?istorieal information for 

future projects.

  ƒ„…项是X9:;的*+úå'

  A) ])P的项目ÂÆ'(。  $) ê$¯qY‹æƒm_。

  ) `诉cd成eu们ç¼的0误。  *) ]DM的项目¿1+,信°

12=.Bou ha+e een assigned to manage a large enterprise resource planning (%@P) project in

"our organi<ation.Bou reali<e that detailed planning ,execution,and closing processes are

 prereuisites for Success.&o support the project from initiation through closing "ou should use

A) a ma,eOor O u" anal"sis

$) lessons learned and other historical information from pre+ious projeets

) enefitOcost anal"sis

*) the project management information s"stem

ãOiÎMqY一个¥á的 %@P 项目。ã®ýt®¯的ÂÆ、ÉÊ、cd项目是项目成Ú

的¡øR"。]^݆项目kEtcd,ã2˜ùú  。

A) ——?Ó   À制i,  $) X9:;™ÙÚ项目的tu+,信°

)c益成本i,  *) 项目qY信°–

128.hich of the follo#ing process is not part of project integration management'  A) Integrated change control.  $) Performance reporting

Page 28: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 28/42

  ) lose project.  *) *irect and manage project execution.

  ƒ„…个¼½是项目ÉšqY的li'

  A)Éš/0Ë制。  $) 绩效[`。  )cd项目。  *) 指àèqY项目ÉÊ。

129.A paint manufacturer authori<ing a project to estalish guidelines to handle toxic material is

an example of a project initiate ecause of .  A) mar,et demand $) a customer reuest ) a leagal reuirement *) a technological

ad+ance

è料éÕ起项目M‘í#bêº的ëR指ì,$是y]  !E项目的OP。

A)íî67  $) «¬67  ) èï7W  *)*+—进

140.A project manager is at the project ,ic,FoffFmeeting .?e confidentl" states the +ision and

mission for the project.&his P3 is exhiiting leadership st"le.

  A) hierarchical $) authoritarjan ) charismatic *) associati+e

  项目XYˆP项目的Eše。uÀ信·¸¹Q项目的ðñ™ùa。$个项目XYP\Ó  。

  A)¦¿  $)J  )òJ  *)7#

141 . Bou are the project manager of Alpha Cet#or, Inc . Bour compan" is doing net#or, 

 planning for a major an, .Bou are planning to digram the acti+it" dependancies using acti+it"

list.hich of the follo#ing is true'

  A) P*3 is also the A;A diagramming method.   $) P*3 is also the A;* digramming

method.

  ) P*3 is also A;C digramming method.  *) P*3 is also A*3 diagramming method.

  ã是 Alphañò²³的项目XY。ã们²³P]一个¥óÊôZñòÂÆ。ãÅÆùúñò

óMÑ)DE„Ñ5DE的op@。ƒ„…个fè是ˆÌ的'

  A) P*3ÈOÕ] A;A±óè。  $) P*3ÈOÕ] A;*±óè。

  ) P*3ÈOÕ] A;C±óè。  *) P*3ÈOÕ] A*3±óè。14- . &as, A has the follo#ing details v ;ptimistic estimate Û 20 , pessimistic estimate Û

40 , most li,el+ estimate Û 25 . &as, $ has the follo#ing details v ;ptimistic estimate Û

2- , *essimistic estimate Û 2= , most li,el" estimate Û 24 . &as, has the fo1lo#ing

details v ;ptimistic estimate Û -5 , most li,el" estimate Û 25 , pessimistic estimate Û

45.hich tas, has the highest standard de+iation'

  A) &as, A.  $) &as, $.  ) &as, .  *) &as, AS&as, .

  ±~ A bÞƒ信°vÊË估xÛ20,ÌË估xÛ40,*ö÷估xÛ25;±~ $ bÞƒ信

°vÊË估xÛ2-,ÌË估xÛ2=,*ö÷估xÛ24;±~ bÞƒ信°vÊË估xÛ

-5,*ö÷估xÛ25,ÌË估xÛ45。…个±~b*$的¤_K'

  A) ±~A。  $) ±~$。  ) ±~。  *) ±~A ™±~。

142.In case of conflicts of interest among sta,eholders,#hom should the project manager gi+e

 priorit" to'

  A) Project team.  $) Project manager ta,es his o#n decision.

  ) Senior management.  *) ustomer .

  r项目2VÙLÕ`Ã益冲突K,项目XY2˜ƒ-的¾¡¿Žt*$'

  A) 项目cd。  $) 项目XYÀÁø×。  )$¿qY¯。  *) «¬。

144.hich process group focuses on completing the reuirements of the projectÙ

  A) Initiating.  $) Planning.  ) %xecuting.  *) losing.

  ƒ„…个¼½组@ä¨N成项目的6W'  A)E。  $) ÂÆ。  ) ÉÊ。  *)cd。

Page 29: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 29/42

145.ho is responsihle for ualit" management in the project'

A) Project leader .   $) ualit" control department ) Project manager .   *) &eam

memer .

-#项目的¡qY°'

A) 项目Ìà。  $) ¡Ë制l门。  ) 项目XY。  *) cd成e。14 . In "our soft#are de+elopment project "ou ha+e to #ait for 5 da"s after ordering a ne#

soft#are and then onl" "ou can start integration testing .&he 5 da"s in this case is an example of 

  A) lead $) lag ) dela" *) f1oat

  Pã的!"lÕ项目5,ã67PÙÉ9!"Ùõ¦õ 5I‡÷lmÉšL试。$ 5I是

的OP。

  A) ¿Ú  $)öõ  )©误  *) KK

14= . Bou are #or,ing on internal projects for a ig corporation . Bou are in to reuirement

definition for ne# claim s"stem that #ill enale emplo+ees claim their hours #or,ed on the

 projects using their moile phones also.*ue to udget cuts it #as decided to cancel the project

and deplo" the people to commercial projects.hich of the follo#ing is true'

  A) &he project ended due to integration ecause the resources #here distriuted to commercial

 projects.

  $) &he project ended due to star+ation ecause the funding #as cut.

  ) &he project ended due extinction ecause of the udget cut.

  *) &he project ended due to integration ecause of udget cut.

  ãQRP某个¥áic的bl项目e。ãO7W×Ø9的Z[–,$òù;eJ¼ùú

÷Eø}Z[u们P项目e的QRŠK数。由¨¥x#$,M项目OV,项目成eO

õt3~项目e。ƒ„…项是ˆÌ的'  A) 项目的;¶ù¨É‚,y]UŠOõt35项目e。

  $) 项目的;¶ù¨ú.,y]UüO$减。

  ) 项目的;¶ù¨ûv,y]¥xO$减。

  *) 项目的;¶ù¨É‚,y]¥xO$减。

148.hich of the follo#ing statements is C;& true regarding arro# digramming method'

  A) Schedu, acti+ities are represented " arro#s.

  $) &he length of the arro# represents the expected duration of the acti+it"H

  ) &he tail of the arro# represents the start ot the acti+it"H

  *) &he head of the arro# represents the finish of the acti+it".

  ƒ„@¨ A*3 的fè…个是ˆÌ的'

  A) 进度DEJ¼¿eÑ)。  $)¿e的G度š)DE的¥T+K。

  )¿e的dü¸ÑDE的lm。  *)¿e的ýl¸ÑDE的;¶。

149.hich of the follo#ing statement is #rong'

  A) >eading,communicating, Cegotiating, prolem sol+ing and the ailit" to influence the

organi<ation are considered ,e" s,ill for project managers to possessH

  $) Project managers should ta,e into consideration and plan accordingl" for influences.

  ) Project management s,ills ha+e no relation to general management s,ills.

  *) ;rgani<arions are increasingl" accountale for impacts resulting from project.

  ƒ„…个fè是0误的'  A)Ìà、¤J、谈判、s题ðø™vw组织的÷J是项目qY‹?=的@A*÷。

Page 30: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 30/42

  $) 项目XY?@考~ÅÆö÷ýM的vw。

  ) 项目qY‹的*÷™KÂqY*÷‰@。

  *)组织#项目的vw°。

150 . &he follo#ing are the internal rate of return (I@@) for different projects . Project A v

5L, project $v-5L, project v20L, project *v9L.hich is the est project'  A) Project A.  $) Project $.  ) Project .  *) Project *.

  £项目的blc益q (I@@) Þƒv项目 A ] 5L;项目 $ ] -5L;项目 ] 20L;项目

* ] 9L。*+的项目是…个'

  A) 项目 A。  $) 项目 $。  ) 项目 。  *) 项目 *。

151.hich of the follo#ing is true regarding estimation'

  A) P%@& is superior to P3.

  $) P%@& estimates are etter than 3onte arlo simulation.

  ) P3 uses 2 estimates on a tas, (pessimistic,optimistic and most li,elB)

*) 3onte arlo simulation uses P%@& formula.

  ƒ„…个@¨估x的fè是ˆÌ的'

  A) P%@& j P3 0+。

  $) P%@&估xjþfÿî模拟7+。

  ) P3 #一个±~ùú²个估x (*ÌË、*ÊË™*ö÷) 。

  *)þfÿî模拟ùú P%@&²•。

15-.Bou ha+e to finish a project #ith in - #ee,s and "our lead de+eloper had to ta,e 1 #ee, 

lea+e due to personal emergenc",Another project manager has agreed to loan the ser+ice of 

his lead de+eloper for l #ee, .Bou are ta,ing his help and completing the project .&his case is

an example of (hoose the est ans#er) .

  A) fast trac,ing $) crashing ) ris, management *) resource le+eling  ãP!"bn7;¶项目,ã的席lÕ‹y]个V-~´l一"。一个项目XY£®

6u的席lÕ‹¼M§¨,ãÏÐ^$个§¨N成^项目。$是   的OP (ÑÒ*/

ÅÆ) 。

  A)5gV进  $)ÎQ  ) ûüqY  *) UŠ[衡

152.A complex project #ill fit est in #hat t"pe of organi<ation'

  A) Eunctional.  $) rossFfunctional.  ) 3atrix.  *) $aIanced.

  åæ的项目*+ùúƒ„…%组织;Z'

  A)µ÷á。  $)跨l门。  )[\á。  *)[衡á。

154.hen the project cost is 6-7000 and the profit is 6500,#hat is the $@ for the project'

  A) -7500.  $) -5L.  ) 4.  *) not enough information to calculate

$@ .

项目成本是 -000 ßà,Ã润是 500 ßà,项目的 $@ 是H少'

  A) -500。  $) -5L。  ) 4。  *) ‰b足¾的信°MÅx$@ 。

155.hich of the follo#ing is C;& an input to perform integrated change control'

  A) Proiect management plan.  $) @euested changes.

  ) Project scope statement.  *) or, performance information.

  ƒ„…项是Éš/0Ë制的ÇÈ'

  A) 项目qYÅÆ。  $)ŽW的/0。  ) 项目-.fg&。  *) QR绩效信°。

15.hich ,no#ledge area does the de+elop project charter elong to'  A) Initiating.  $) Project scope management.

Page 31: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 31/42

  ) Project integration management.  *) Project communication management.

  制×项目z½Z¨…个ËýÌÍ'

A)E。  $) 项目-.qY。  ) 项目ÉšqY。  *) 项目¤JqY。

15=.&he t"pe of contract #here the u"er incurs opportunit" cost ut little or no additional cost

ris, is called .  A) fixedFprice #ith incenti+e $) firmFfixedFprice

  ) fixed price #ith economic price adjustment *) fixedFprice #ith right of rene#al

  šàÂÓž的Ôš成本±!<boŠ的¬‰b:;的ûü成本的‚£Õ]  ‚£。

  A)固×价ñ“”  $)固×价à )固×价ñXm价ÃÙÉ  *)固×价ñ’

r09

158.hich t"pe of #arrant" is enacted if a ser+ice or product does not meet the le+el of ualit"

specified in the contract'

  A) Implied #arrant" of merchantailit".  $) Implied #arrant" of specified ualit".

  ) %xpress #arrant".  *、 Cone of the ao+e.

ƒ„…%担Ä是针#}~¬îïÁ‚‚£5Â×的¡¯œ的'

A) 35bPÄ证。  $)fסbPÄ证。  )货ï¡Ä证。  *) ìeô是。

159.In "our soft#are de+elopment project "ou ha+e planned for s"stem testing from 3arch 1st

and the duration is 10 da"s.&#o da"s efore the completion of the s"stem test,"ou can start

the user acceptance test.&he - da"s in this case is an example of .

A) lead $) lag ) dela" *) float

Pã的!"lÕ项目5,ãÅÆ–L试QRk 2 月 1Hlm,+K 10I。PN成–

L试Ú -I,ãöìlmú¬ÏcL试。P$%&´ƒ,$ -I是  的OP。

A) ¿Ú  $)öõ  )©误  *) KK

10.Bou are #or,ing on a project for $right Idea Inc.and #or,ing on a project for a large retail an, . Bou ha+e alread" prepared the $S and got it signed off . $ecause of some ne#

go+ernment regulations,"ou need to add some more acti+ities to the $S .Bou ha+e got the

change reuests appro+ed through the $ . &he $S changes in turn reuire #hich of the

follo#ing'.

  A) ost changes.   $) Scope changes.   ) Schedule re+isions.   *) @is, response

change.

  ãP $right Idea²³é一个¥á零售仓<的项目。ãŒX_=^ $S ÎŽ^签a。y]

9的š´èÂ,ã67±0HDEt $S。ãŒX拿tJ¼ $×_的/0ŽW。$S

/0oœñò引Õƒ„…个/0'

  A) 成本/0。  $) -./0。  ) 进度Ôx。  *) ûü2#/0。

11 . ompan" A$ adopt "earFsummar" for decritiation of asset . &he" spent 61=7000

 purchased one computer .It is eatimated that the computer can e sold #ith 6-7000 three "ears

later .&us,ho# much #ill e the asset decritiation of this computer in "ear three'

  A) 657000.  $) 647500.  ) 6=7500.  *) 6-7500.

  A$²³JKú年™èMÅxUî的折旧。u们ï 1= 000 ßàÓ^一台ÅxÔ,估Ų年

õ÷Ô -000 ßà。Œx›²年的折旧是H少ßà'

  A) 5000。  $) 4500。  ) =500。  *) -500。

1- . Bou do not expect the t"pes of +ariances that ha+e occurred on the project to date to

continue . If $A Û 200 , %& Û -=5 , P Û 200 , A Û -00 , % Û -50 and PI Û1.-5,#hat is the %A'

Page 32: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 32/42

A) -40.  $) -50.  ) 4=5.  *) 150.

ã认]t目Ú]v项目5()的偏KDMšþ()。ÞÀ $AÛ200,%&Û-=5,P

Û200,AÛ-00,%Û-50,PIÛ1.-5,á %A 是H少'

A) -40。  $) -50。  ) 4=5。  *) 150。

12 . Bou a"e a project manager to upgrade the computer safet" of "our organi<ation . Bour Project team is made up of four contractors and t#o full time emplo"ees .&his is the first time

the" ha+e all #or,ed together .Bou ,no# that the team #ill go through the stages of team

de+elopment in the follo#ing order v

  A) Eorming   , storming   , norming   , and performing   .   $)

Storming,norming,forming,and performing.

  ) Corming   , storming   , forming   , and performing   .   *)

Eorming,norming,storming,and performing.

  ã是个项目XY,ˆP09ã们组织的ÅxÔÉ–。ã的项目cdS 4 个承S3™

- 个ɵ;e。$是u们›一œ一起QR,ãËß$个cdòXyƒ„…个zöMÕ\v

  A) ´成、震荡、Â-、成熟。  $)震荡、Â-、´成、成熟。

  ) Â-、震荡、´成、成熟。  *) ´成、Â-、震荡、成熟。

14.*uring the execution phase of project,"ou reali<e that one of the product functionalities

has een omitted in the projeet plan ,#hich #ill not e+entuall" satisf" the reuirement ,"ou

should .

  A) update the project schedule and udget

  $) sumit a change reuest to change control oard and re aseline

  ) negotiate #ith the client for a ne# deli+er" date ased on the re+ised schedule

  *) informing management and ta,e necessar" measures for changes in udget and schedule

  P项目»«EF,ã®ýtP项目ÅÆ5‹Œ^一项îïÚ÷,$ò*终àÂÀè足7W,$Kã2˜  。

  A) 09项目进度ÅÆ™¥x

  $) ~/0Ë制âeš¿¢/0申Ž,Î19制x项目ú_ÅÆ

  )oÝÔ—的进度ÅÆ諬Ø3一个9的¢付HT

  *)JË$¿qY¯,Î]/0¥x™进度ÅÆ>?7的%骤

15.A re+ie# of management processes and the associated documentation is commonl" called

  A) audit $) inspection ) testing and measuring *) screening

  #qY¼½™相@XY进Ê的ÿÖJKÕ]  。

  A)ÖÅ  $) ©ª  )L试™L¡  *)Ž映

1.ompanies and institutions most commonl" hire project management leaders #ith .

  A) a strict standing in negotiating.

  $) experience in tric,ing usiness partners.

  ) integrit" and expertise.

  *) a strong lin, to local traditions.

 ²³™ÔZ;ú的项目qY‹JK™=  。

  A)谈判5严Ã的íî  $)欺骗35伙伴的X9  ) ˆ¼的ïÙÇ5*+  *) ™本·

传–的密ù7

1=.hat is true #hen a change control s"stems pro+ision for changes #ithout formal re+ie# incase of emergenc" is eing utili<ed'

Page 33: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 33/42

  A) hanges can e simpl" applied #ithout further managerial acti+ities if the" help sol+ing the

 prolem.

  $) hanges must still e documented and captured so that the" do not cause prolems later in the

 project.

  ) A ne# change control oard ($) should e estalished.  *) &he project aseline must e changed as #ell.

  rÕ`紧./0K/0–Â×öìJ¼ˆ•ÿÖnÉÊ,@¨$%&'ƒ„…个fè

是ˆÌ的'

  A) ÞÀ/0ö짨ðøs题,ŒxöìPX¼0HqYDE的&'ƒO简S·ÉÊ。

  $) /0?@OXY'(™VW,避免PDM引Õ项目s题。

  ) 67‘í9的/0Ë制âeš。

  *) 项目ú_?@£K/0。

18.$eing assigned as the project manager to a project "ou perform earned +alue Anal"sis and

find the follo#ing results v % Û -507000 ; P Û -007000 ; A Û -=57000 ; $A Û

5007000.hat is right'

  A) %AÛ4007000.  $) %AÛ5507000.  ) $&Û4007000.  *) %&Û=57000.

  P项 目eãé^»)Üi,,Õ)ƒ„;Àv %Û-50 000;PÛ-00 000;AÛ-=5

000;$AÛ500 000。ƒ„…项是ˆÌ的'

  A) %AÛ400 000。  $) %AÛ550 000。  ) $&Û400 000。  *) %&Û=5 000。

19 . A is a preFcontract agreement that formall" estalishes the intent of one part" to u"

 products or ser+ices from another part" and estalishes some preliminar" consideration in order 

to reser+e resources for the anticipated contract.

  A) seller initial response $) memorandum of understanding ) letter of intent *) letter 

contract  一个‚£ÙÚ成的Ø议úMˆ•‘í一个®~v一žk一ž?Óîï¬}~Îâ%考

~]‚£ÄæUŠ,$个XYOÕ] DD 。

A)Ôžâmw2  $)谅ð=(  ) ®~&  *) ‚£&

1=0.hat does the acron"m @AI commonl" stand for in project management'

  A) @esponsile,accountale,to e communicated,&o e informed.

  $) @emote,attached,connected,integrated.

  ) @is, anal"sis and caution initiati+e.

  *) @andoml" accessile cash flo# information.

  P项目qY5@AI¸Ñwx'

  A) b°,°,¤J,Z[。  $)!ð的,"±的,…Ï的,É‚的。

  ) ûüi,™#$=E。  *)PÔÏ)ü£信°。

1=1.A change reuest in a project has een rejected some #ee,s ago .Besterda",the project

manager found out that it ne+ertheless has een implemented " the team memers,#ho ,ne#

of the change reuest, ut not of the rejection .In order to a+oid such a situation ,reMected

change reuests are input to #hich process'

  A) Schedule de+elopment.  $) Scope +erification.

  ) 3onitor and control projeet #or, .  *) Information distriution.

  一个/0ŽWP·"ÚO]^。%I,项目XYÕ)$个/0还是Ocd成e»«^,y

]u们Ëß$个/0ŽW但ËßO]^^。]避免$%)_,]^的/0òÇÈt…个¼½'

Page 34: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 34/42

  A) 制×进度Ñ。  $) º»-.。  )„€èË制项目QR。  *)信°Õ¶。

1=-.All the follo#ing statements are true exceptv

  A) It is axiomatic of the ualit" management discipline that the enefits out#eigh the costs.

  $) ualit" should mainl" e achie+ed " testing and inspections of #or, results on a regular 

 ase.  ) &he primar" cost of meeting ualit" reuirements is the expense associated #ith project

ualit" management acti+ities.

  *) &he primar" enefit of meeting ualit" reuirements is less re#or, , #hich means higher 

 producti+it",lo#er costs,and increased sta,eholder satisfaction.

  ƒ„ab¸¹ô是ˆÌ的,W^v

  A) Ò!‹见,¡qY的ú本/á是c益?@超¼成本。

  $) ¡=72˜J¼×T©ª™L试项目成ÀM»)。

  ) 足¡6W的=7成本ïðP项目¡qYDEe。

  *) Á‚¡6W=7的+¸是减少返Q,$®LQ$`î效q、Ê成本™±的2V

®度。

1=2.hich of the follo#ing statements is not true'

  A) Attriute sampling is the process of assessing #hether results conform to specifications or 

not.

  $) Pre+ention means ,eeping errors out of the process " appl"ing actions efore the process

starts changing its input.

  ) ariales sampling means that the result is classified into one of the 2

categoriesvacceptale/Facceptale after re#or,/F relected/.

  *) Inspection is often mainl" done to ,eep errors out of the hands of the customer instead of as a

means of process control.  ƒ„…个fè是ˆÌ的'

  A)Z)k¹是ÿ估;À是÷Á‚ÂÃ的¼½。

  $) ¥¦是指J¼P¼½lmÙÚ>ÊEÌÄ0误šþ)P¼½b。

  ) /¡k¹®LQ;ÀJKi]²个|þvÏÐ,返QõÏÐ,]^。

  *) ©ªJK=7úMÌÄ0误št«¬&5。

1=4.hich of the follo#ing statements regarding #histle lo#ing are not true'

  A) It is a term used to define an emplo"ees decision to disclose information on

unethical,immoral or illegal actions at #or, to an authorit" figure.

  $) An emPlo+ee should al#a"s discuss the matter #ith people external to the compan" efore

follo#ing thechain of command/and discuss it #ith the immediate superior .

  ) &he conseouences of #histle lo#ing are often extreme and include possile eing randed as

ha+ing ad Mudgment,firing,ci+il action and imprisonmentH

  *) arefull+ considered #histle lo#ing can lead to the end of unethical usiness practices.

  ƒ„…项@¨'Õ (À[È() /的fè是ˆÌ的'

  A) $个)×Ø^;eøב'*aP²³的߶的、+,的¬&è的QR。

  $) “ ”P遵循  a-.   ™¼Ïe¿67ÙÚ,eQ2˜:是™;lV67²³的s题。

  )1 ”'Õ 的õÀJK是æ/的,Sö÷Ole0误判0的1m,ð;ìÍ2-诉3™

„4。

  *) “ ”Š¯考~  'Õ öìù߶的35»56%V失。1=5. Bou are assigned as the project manager in a project #ith an aggressi+e schedule,*uring a

Page 35: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 35/42

recent meering "our team complained aout the high pressure applied and the man" hours of 

o+er#or, time.hat should "ou do first'

  A) &r" to otain additional udget and time.

  $) Impm+e team communication and a+ailailit" of high ualit" data on ris,s . :se ttlis

information to enale "ou to ma,e #ellFfounded decisions earlier .  ) &he prolem might e the customer disturing project rh"thm.Keep him on distance from

the team.

  *) Appl" fast trac,ing to shorten project duration #ithout additional #or, .

  ãOiÎt一个进度#Jo¥的项目e担±项目XY。P*的š议e,ã的cd成e~

ã78¼$的#J™¥¡的±9。ã¡2˜éwx'

  A):试Ž:;的¥x™KL。

  $) —进cd的¤J™$¡ûü数Ý的öŽ)。ùú$ë信°§¨ã½早的R(boÝ

的øÐ。

  ) $ës题ö÷MÀ«¬2;项目M<,Ć«¬ècd的=´。

  *) P±:;QR的Ú¿ƒ,ùú5gV进M$Þ项目+K。

1= . A Project team is suffering from misunderstandings et#een team memers #ho ha+e

different cultural ac,grounds   . &he project manager is e+aluating ho# to impro+e

communication and collaoration.hich of the follo#ing statements is not true'

A) ;nl" those #ho reali<e that cultural differences are a resource to e full" utili<ed #ill

sur+i+e in international project usiness.

$) &here is a common ground for people from different cuItures on #hich the" can interact

#ithout unsol+ale conflicts.

) ultural differences #ill al#a"s remain an ostacle to e o+ercome for crossFcultural

 projects.*) rossFcultural competence is a critical le+er for competiti+e ad+antage in international

 project usiness.

™b£Xh)ñ的cdCÈ相互误ð的>?5。项目XYPÿ估ÞI—进¤J™‚R。

ƒ„…个fè是ˆÌ的'

A)<bŒë认ýtXh£是个UŠ、öì=iÃú的V‡÷¾P„ø项目5›Ö。

$) MÀ£Xh的V们™b¢£的)ñ,u们öìP‰b÷ðø的冲突的&'ƒ相互

vw。

)XhK@:是ÖP的ÎAB跨Xh的项目。

*) P„ø项目355竞争5,跨Xh÷J是个@A的CD。

1==.A project management team is e+aluating the causes that might contriute to unsatisfactor"

 perforrhance and ualit".hich of the follo#ing statcments is not true'

  A) Cormal process +ariation is attriutale to random causes and sometimes also called#hite

noise/.

  $) Special callses are easier to predict and handle than random causes (also called common

causes) .

  ) Special causes are unusual e+ents #hich are difficuIt &o foresee and mostl" produce

outliers.

  *) A process can e optimi<ed to limit the and#idth of +ariations due to random causes.

  项目qYcdˆPÿ估ö÷àÂÁ‚7W的绩效™¡的/y。ƒ„…个fèˆÌ'  A) ˆK¼½的PÔ偏KöZ¨PÔ/y,bK_OÕ]EFG/。

Page 36: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 36/42

  $)fH/yjPÔ/y (IJ/y)4‹O¥Ë™Ë制。

  )fH/y是œKÂ-",op¥见,XKàÂs题。

  *) ¼½的PÔ/y的偏KöìO‚制¨ÏÐ{|Ùb。

1=8 . *uring a project the scope of a product purchased on a cost reimursale contract has

increased.In the contract the fee to co+er the contractors indirect costs and allo# a profit iscalculated as -0Lof the direct costs.hat is most li,el" to e true'

  A) &he contractors indirect costs #ill increase and the customers pa"ment for them #ill

increase,too.

  $) &he contractors indirect costs #ill increase ut the customers pa"ment for them #ill not

increase.

  ) Ceither the contractors indirect costs nor the customers pa"ment for them #ill increase.

  *) &he contractors indirect costs #ili not increase ut the customers pa"ment for them #ill

increase.

  一个ùú成本TJ‚£的îï>?‚£-.±^,P‚£ŸÓžÝ付的ðúS承S

3的LÏ成本™¼Ï成本的 -0L。ƒ„…个fè*ö÷是ˆÌ的'

  A)承S3的LÏ成本š±,]M«¬的ðúRš±。

  $)承S3的LÏ成本š±,但«¬的ðúš±。

  )承S3的LÏ成本š±,«¬的ðúRš±。

  *)承S3的LÏ成本š±,!«¬的ðúš±。

1=9.Bou are assigned as the project manager to a project #hich is executed for a customer under 

EP contract   . Bour customer informed "ou this morning that the" insist on

certain1refinements2of the project scope.Bou agree that the reuested actions ma,e reall"

sense to the project , ut elie+e that the" constitute a major change increasing the project

scope.hat should "ou do next'A) Accept the reuest of the customer .*iligentl" document the additional costs and #or,ing

hours spent " "ourself and the team on the implementation of the change and in+oice these

to the customer at appropriate rates.

$) Perform earned +alue anal"sis to assess the current status of the project and get all the

numers "ou need to communicate the case to the change control oard #ich then #ill ha+e

to ma,e the est decision regarding the customer reuestF

) hec, the contract,the project charter ,the scope statement and other documents related to

the project and the contract . Assess the impacts of the scope change . &hen discuss the

situation #ith the project sponsor and the change control oard.

*) &al, to the project sales department and find a joint solution #ith them ho# to est reject the

reuest considering the commercial and strategic +alue of the customer to the organi<ation

"ou are #or,ing for .

ãO指ã]某项目的项目XY,$个项目ùú的是固×:价‚£。ã的«¬”I早eJË

ãu们Kø7Ì×项目-.的¯M。㣮$个ŽW#项目是b益的,ã相信u们š¿1

一个/0ŽWM±项目-.。σMã2˜éwx'

A) ÏЫ¬的ŽW,认‡'(ãÀÁ™cdÉÊ$个/0aïð的:;的成本™QRK

L,Î~«¬c‚’的ðú。

$) ÉÊ»)Üi,ÿ估项目rÚ{|,ƒab数Ý¿1ê/0Ë制âešì便u们#«

¬的ŽWR(*+的øÐ。) ©ª‚£、项目z½、-.fg&ìÍtuè项目™台£相@的XY,ÿ估-./0的

Page 37: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 37/42

vw,è/0Ë制âeš™Õ起V67。

*)è项目L售l门进Ê¢£,J¼考~ã²³™«¬的35™M£价Ü,8t*+的]

^ŽW的žÆ。

180.hat is sometimes referred to as gloal illiteracies'

  A) &he ailit" to read reports #ritten in man" different languages.  $) &he ailit" to succeed in a cross cultural en+tronment.

  ) &he ailit" to de+elop internationall" accepted contracts.

  *) &he ailit" to communicate using dra#ings and pictograms #hich are understood all o+er the

#orld.

  ÉNhXO/JKš涉Í…ëb4'

  A)PQúH%R"写(的[`的÷J。

  $)跨Xhjkƒ成Ú的÷J。

  )编写„øeôÏÐ的‚£的÷J。

  *) ùúÉNô÷ÏÐYð的ódž•M¤J的÷J。

181.A project management team #ants to procure some customi<ed products #hich are a+aliale

in identical grade and ualit" from man" +endors.hat should e included in the procurement

 pac,age to ensure that their offers #ill e comparale'

A) A statement of #or, descriing the needs of the project in sufficient detail to enale +endors

to ma,e suitale proposals.

$) A statement of #or, specif"ing attriutes and metrics of the reuested deli+erales in detail

to allo# +endors sumission of ids.

  ) &he appro+ed project scope statement , the $S #hich should e ro,en do#n to #or, 

 pac,age le+el and the $S dictionar".

  *) &he ris, management plan and the reports from those ris, management re+ie#s #hich ha+e een made so far .

项目qYcd#Žë×制h的îï,$ëîïöì由oH123¿1,Ιb£¹的

¦¿™ï。ƒ„…项?@S含P>?S5úMÌÄu们的‘议是öj½的'

A) S; P足¾的®¯½度e¸¹^项目的6WúM6Ôž¿1’r的‘议。

$) S;®¯¸¹^7W的ö¢付成À的fÄ™ç数ì便6123[价。

)×_的项目-.fg&,$S?@étQRS¯ŸÎS$Saƒ。

*) t目Ú]vé的ûüqYÅÆ™ûüqYÿ估的[`。

18-.Bour project is executed #ith a gloall" spread +irtual team.&he project progress has een

found to e too slo#.hich measure is most li,el" to immediatel" speed up the project'

  A) &echnical training for all team memers.

  $) *ail) phgne conferences and detailed reporting.

  ) A team meeting at a location con+enient to all team memers.

  *) ollocation of team memers at a suitale place.

  ã的项目由一个ÉNS拟cdMÉÊ。项目进\FT^。ƒ„…%žèöìíñ±g项目'

  A)*+stabcd成e。

  $)每IÃlø}š议£K鮯Z[。

  ) P¥Èô便Ã的·gÃlcdš议。

  *) P’r的†ÏA5º²。

182 . *uring execution of a project #hich is performed for a customer on a &J3 (time andmaterial) contract ase ,a ne# project manager is ta,ing o+er the assignment .?e disco+ers

Page 38: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 38/42

that t#o memers assigned to the project ha+e charged time #ithout performing an" #or, for 

the project customer . :pon further in+estigation , he determines that this occurred ecause

there ha+e een no other project assignments open for these emplo"ees . &he customer is

una#are of these facts.hich of the follo#ing should he do'

  A) &r" to find some producti+e #or, for these staff memers in the project and lea+e them on theteam.

  $) &he est thing is to do nothing.&he customer #ill not reali<e the prolem an" a".

) &r" to find a responsile person for the o+er assignment #ho can e made accountale.

*) &a,e the t#o people off the team immediatel" and arrange for the refund of the excess

charges to the customer .

P一个ú¨KL°料‚£的项目的Éʼ½5,iÎM一个9的项目XY,uÕ)!个

项目成e‰b]«¬é±IQR。进一%的ÙªÕ),$%)_的Õ`是y]$ëµe‰

btu项目öìé。«¬Ëß$ë-»。u2˜œ¹é'

A) P项目58ë`î)的QRê$ëeQ,6u们æPcd。

$) *+是wxôé,«¬是À7ÞIRšÕ)$%&'的。

) 8(#M&'°的VMé个ð,。

*)6$!个Ví•´lcd,õU还«¬:;ïð的ðú。

184 . Bon are running a project for a customer ased on a cost reimursale contract #ith the

follo#ing terms   v &arget costs   ,   6170007000   ; fix fee   , 1007000   ;  enefitcost

sharing   , 80-0   ;  price ceiling   , 17-007000   . hich is the P&A (point of total

assumption, rea, point) of the proiect'

  A) 6172007000.  $) 6175007000.  ) 6807000.  *) 6171-57000.

  ãP]«¬é一个项目,ùú的是成本TJ‚£,数ÝÞƒv目¤成本, 1000000 ßà;

固×Vü,100000 ßà;Ã益成本i担,80-0;*$‚价,1-00000 ßà。ƒ„…个是项目的 P&A (:š‚<g,W|g) '

  A) l200000 ßà。  $) 1500000 ßà。  ) 80000 ßà。  *) 11-5000 ßà。

185 . A project management team has sucontracted #or, to a ser+ice compan" hich of the

follo#ing tools is the est choice to assure that this compan" #i e ale to meet the ualit"

reuirements of the project'

  A) ualit" audit.  $) *eli+erale inspection.  ) Eixed price contract.  *) Ser+ice le+el

agreement.

  一个项目qYcdƒQRiSê一È}~²³。샅%Q™是*+的ÑÒúMÌÄ$È

²³÷o+·足项目的¡7W'

  A) ¡ÖÅ。  $) ö¢付º©ª。  )固×:价‚£。  *)}~¦¿Ø议。

18.In a traditionall" dra#n decision tree,a circle represents .

  A) a chance to #hich no estimated monetar" +alue can e assigned so that a li,el" pa"Foff carl

not e sho#n

  $) a decision to #hich no estimated monetar" +alue can e assigned so that a li,el" pa"Foff can

not e sho#n

  ) a chance to #hich an estimated monetar" +alue ma" e assigned to calculate the most li,el"

 pa"Foff 

  *) a decision to #hich an estimated monetar" +alue ma" e assigned to calculate the most li,el"

 pa"Foff   P传–的øÐXóÆ5.一个YZ¸Ñ  。

Page 39: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 39/42

  A) 一个Ôš,‰bOiÎ%3 aì÷Åx*ö÷的回[

  $) 一个øÐ,‰bOiÎ %3 aì÷Åx*ö÷的回[

  ) 一个Ôš,OiÎ一个 %3 úMÅx*ö÷的回[

  *) 一个øÐ,OiÎ一个 %3 úMÅx*ö÷的回[

18=.Bou are #or,ing as a project manager for a major usFased pulic compan".&his morning"ou recei+ed alarming ne#s that the major strategic project "ou are responsile for #ill not e

ale to pro+ide financial enefits to the organi<ation as expected . &his dra#ac, #ill

significantl" influence future profits of the entire corporation.hat should "ou do right no#'

  A) Bou should not o+eract and chec, at least three options efore ma,ing an" decisions.

  $) Bou must immediatel" inform the corporate management to ensure real time issuers

disclosures.

  ) Bou should in+estigate detailed information on the prolem efore escalating it to corporate

nlanagement.

  *) Bou should find a uic, solution for the prolem and implement this immediatel".

  ã是一个:l<Pß„的eí²³的项目XY。”Ie[,ãct-V震\的V°,由ã

°的一个1¥M£项目òÀèk组织5Ž¥T的]šÝ†。$ò¥¥vw”õÉ个²

³的Ã润。ã)P2˜œxé'

  A) 7Õ^,PR(±Iø×ÙÚu少制x²个öÑžÆ。

  $)?@íñJ˲³qY¯,ÌÄs题ÍKO67。

  ) Ps题:¿t²³qY¯ÙÚ,Ùª˜s题的®¯信°。

  *)Þg8(ðøs题的ºè,!3ñ•_Ê。

188 . In order to speed up a project , "ou made a decision to fastFtrac, a phase currentl"

 performed #ith fi+e team memers and another one #hich #as planned to egin in four #ee,s

time #ith another fi+e team memers.hich of the follo#ing acti+ities should "ou do first'  A) 3a,e sure that all exit criteria of the consecuti+e phase ha+e een met to ensure the flo# of 

communications in a team situation #hich is more complex " a factor of -.

  $) 3a,e sure that all entr" criteria of the pre+ious phase ha+e een met " planning and

 performing a phase gate meeting to assess technical aptness.

  ) 3a,e sure that all exit criteria of the pre+ious phase ha+e een met " planning and

 performing a phase gate meeting to assess technlcal perlormance.

  *) @estructure "our team and delegate tas,s in ordcr to ensure the flo# of communications in a

team situation #hich is more complex " a factor of 4.5

  ]^±g项目,ãø×5gV进某个EF,$个EF)P由 5 个cd成eÉÊ;一个ò

P›`"lm,由tu 5 个cd成eÉÊ。ã2˜¡进ʃ„…项DE'

  A) Ì认abõ‡EF的U(¤_O足,ÌĤJza,y]$%&'ƒ¤Jjì“å

æ^ -b。

  $)J¼ÅÆ™ÉÊ一个EFš议Mÿ估*+÷J,ìÌ认abÙÚ的EF的进Ȥ_O

足。

  )J¼ÅÆ™ÉÊ一个EFš议Mÿ估*+绩效,ìÌ认abÙÚ的EFU(¤_ŒX

O足。

  *)1组ã的cdÎiα~ìÌĤJza.y]$%&'ƒ¤Jjì“åæ^ 4.5b。

189.hich of the follo#ing tools is used to create a ris, managemcnt plan'

  A) @is, planning meetings.  $) *ocumentation re+ie#s.  ) *ata precision ran,ings.  *) *iagramming techniues.

Page 40: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 40/42

Page 41: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 41/42

  $) refuse the reuest and report the customer to "our sponsor 

  ) ac,no#ledge the reuest and ad+ise the customer to sumit a formal change reuest

  *) con+ene a meeting of the project team and re#rite the scope statement

  P一个;l项目5.ã的一个«¬7WãN成一ë:;的QR.$ëQRSPˆ•‚

£5,ã2˜  。  A)Xy«¬的7Wé,ÑgÀÁ的‚Rl|,$#òM諬é`®b§¨

  $)]^«¬的7W,~ã的项目Õ起V[`$"-

  ) ÏЫ¬的7W,Α议«¬¿¢一mˆ•的/0申Ž

  *)ÃA项目cdš议,19写项目-.fg&

195.*uring half #a" to the project execution ."ou #ere assigned as a project manager .After 

careful re+ie#ing of the project,"ou found that the project might ta,e doule the time that the

 pre+ious manager estimated.?o#e+er , the upper management has een told that the project

is on schedule.&he pre+ious manager is an old friend of "ours.#hat #ill "ou do'

  A) @eport "our e+aluation to the upper management

  $) ?a+e a team meeting to find the alternati+es to meet the project schedule

  ) 3eet the pre+ious project manager and turn the project ac, .

  *) %xecute the project as planned " the pre+ious manager .

  P项目ÉÊT的5LEF,ãO±a]˜项目的XY。P#项目进Ê认‡ÿ估Ùõ,ãÕ

)项目的QT7jÚ±项目XY估x的QTG一b。ö是,$¯qY‹‘O`˘项目的

进度是PXÅÆ进Ê。Ú±项目XY是ã的一个•no,ãšœxº'

  A) ~$¯qY‹Þ»[`ã#项目的ÿ估。

  $)Ãlcdš议.×Ø(足/ÅÆ进度的tu·¸žÆ。

  ) š见Ú±项目XY,pq项目进度。

  *)XyÚ±项目XY制x的ÅÆÉÊ项目。19.hen there are conflict in the contract,  is the first one should e resol+ed.

  A) schedule planning $) deputi<e ) contract term *) criterion

  r‚£5ÖP冲突K,¡67ðø的是 DD 。

  A) 进度ÅÆ  $)¸Y  ) ‚£Rr  *) Â-

19=.In managing a project."ou notice that a deli+erale mentioned in the general conditions of 

the contraet has not "et een recei+ed .&he seller ,ho#e+er ,sa"s the special pro+isions of 

the contract +oid that dell+erale.hat should "ou do'

  A) @euire the deli+erale as in the contract.

  $) *o nothing.

  ) ontact the contract manager .

  *) Send a letter reuiring the deli+erale is met.

  P#项目进ÊqY的¼½5,ãä®t‚£一RrbÂ×的一项ö¢付成À还‰bct。

但是,Ôžfg‚£fþRrŒXV^˜ö¢付成À。ã2˜ÞIé'

  A) 7W¿1‚£Â×的ö¢付成À。  $) >±Iª«。

  )è‚£XY7。  *)签Õs",7W¿¢ö¢付成À。

198 . ontract closure procedure and administrati+e closure procedure ha+e se+eral common

characteristics,the follo#ing are their common characteristics except .

  A) exit criteria $) contract term ) srep " step *) acti+ities and responsiilities

  ‚£cd½ö™Êšcd½öboH相…Ù¸,ìƒ\是¾们的¢£fg,W  ̂DD 。  A)U(¤_  $) ‚£Rr  )6%¸Y  *) DEè°±

Page 42: 51CTO下载-2012年9月考试PMP认证模拟考试一试卷200题

8/11/2019 51CTO -2012 9 PMP 200

http://slidepdf.com/reader/full/51cto-20129pmp200 42/42

199.hich t"pe of input is the primar" cause of conttact changes'

  A) Independent estimates.  $) ;rgani<ational policies.

  ) Statement of #or, .  *) Appro+ed changes reuests

  ƒ¹…项ÇÈ是‚£/0的=7/y'

  A)Tí估x。  $)组织šÐ。  ) QRfg&。  *)×_的/0ŽW。-00.A procurement audit is a structured re+ie# of the procurement process from procurement

 planning through contract administration . hat is the primar" ojecti+e of a procurement

audit'

  A) *etermine the issues #ith "our present contract so that the contraet terms can e modified or 

impro+ed.

  $) Identif" successes and failures that #arrant transfer to other procurement irems on this project

or to other projects #ithin the performing organi<ation.

  ) &o ensure that the seller is follo#ing all the terms listed in the contract.

  *) &o ensure that the u"er is follo#ing all the terms listed in the contract.

  >?ÖÅ指#k>?ÅÆ编制t‚£qY的É个>?¼½的;Z)回。>?ÖÅ的=7

目¤是wx'

  A)L×ã目Ú的‚£s题,ì便#‚£Rr进Ê0—™Ôˆ。

  $)tþ成Ú™失败ìú¨M项目¬ÉÊ组织的tu项目的>?-项。

  ) ÌÄÔžXy‚£a„RrÉÊ。

  *) ÌÄÓžXy‚£a„RrÉÊ。