ITB Reference: ITB/RERL/REES:KTP 2012/002
SN Particulars Specifications Unit QtyRate in Figure,
Rs.
Am
I
1.1
Turbine:Cross Flow with 16 kW
shaft power with baseframe (12
kW electrical output)
The turbine runner should be of mild steel, rated to continuously deliver
adequate shaft output at 504 rpm at the operating condition of site: 139 l/s
design flow and 15.13 m net head to generate 12 kW from generator. The
casing should be of 10 mm thick MS. The set should be complete with any
inlet adapter pipe (to connect the main valve placed just ahead of the
turbine),butterfly valve, base frame, foundation bolts and accessories, all
complete.
Set 1 -
1.2
Power Transmission System:
(Pully on turbine, pully ongenerator and habasit flat Belts )
Drive System with necessary pulleys and Flat habasit belt , bearings and
other necessary components required to change the necessary speed/orientation of the drive with safety guard etc.
Set 1 -
Penstock Pipes:
Mild steel penstock pipes
Mild steel penstock pipes 280 mm ID and 3 mm wall thickness, with the
provision of flanged joints and with necessary accessories such as 'C'
clamps, 'O' ring rubber gaskets, anchor, tarpaulin sheets, nuts and bolts all
complete. The pipes should be pressure tested in the workshop to withstand
the total head (including surge head).
m 43
BendsThe bends should meets the quality of penstock pipe and should resist the
pressurenos 2 -
1.4
GI vent pipeMild Steel Bell Mouth with GI vent pipe 11/2'' ID, 1.35 m in length, with
necessary accessories for fixing, all completeSet 1 -
1.5
u ce a e or n a e
Gravel Trap )
Mild Steel Gate of 1.2 m height & 0.5m X 0.5 m opening with necessary
accessories for fixing, all completeSet 2 -
1.6
-
A. Steel coarse trash-rackA. Coarse trash-rack made of steel 0.6 m x 0.65 m having 40 x 40 x 5 mm
angle iron and 30 x 5 mm flat iron strips @ 60 mm c/c all completeSet 1 -
B. Steel fine trash-rackB. Fine trash-rack made of steel 0.85 m x 1.5 m having 40 x 40 x 5 mm
angle iron and 30 x 5 mm flat iron strips @ 15 mm c/c all completeSet 1 -
1.7 Expansion joints: (Sliding type)
, ,
min of 30 mm length for expansion / contraction, with all necessary
Set 2 -
1.8 Pressure Gauge Standard pressure gauge, fixing with all necessary accessories Set 1 -
Sub Total (I)
RURAL ENHANCED ENERGY SERVICES: KABELI TRANSMISS
1.3
ALTERNATIVE ENERGY PROMOTION CENTER
Bill of Quantities and Specifications
RENEWABLE ENERGY FOR RURAL LIVLIHOOD PROG
Subject: Site Verification, Electro Mechanical Equipment Supply, Delivery, Installation, Testing & Commissioning of Nibu Khola IX
Mechanical Equipments
140355064.xls.ms_office
-
7/28/2019 2) BOQ - Nibu Khola IX MHS (12 kW) Nawmidanda VDC Panchthar_20120928040957
2/3
II
2.1
Synchronous generator: 25 kVA,
brushless , rated to continuously
deliver 12 kW
Synchronous generator 25 kVA, brushless, rated to continuously deliver 12
kW, 230/400 volts, 50 hertz, 1500 rpm, 3 phase 4 wire electrical outputs at
the generator terminal at 0.8 load power-factor at the operating condition of
site. The generator should be self excited and self regulated type with AB
series. The insulation class will be F with environmental protection IP23.The set should be complete with base frames, foundation bolts, couplings
and accessories all complete
Set 1 -
2.2
Three phase electronic load
controller (ELC) with energy
meter
Three phase electronic load controller (ELC), thyrister type, 12 kW in
vermin proof metal cubicle with resistive ballast loads 15 kW (water
heaters) to continuously regulate and dump the load at the given site
condition, all complete
Set 1 -
2.3 Ballast Tank with Heater 15 kWBallast heater of 15 Kw with water tank to continuously regulate and dump
the load at the given site condition, all completeSet 1
2.4
on ro , ns rumen a on,
protection systems:
As a minimum, the
instrumentation should be for
generated voltage/ frequency,
load current, and ballast voltage,
kW and kWh.
Control, instrumentation, protection and switchgear of main switch 40 A, 3
phase in a free standing steel cubicle for manual start, adequate monitoring
and protection of generator with necessary incoming / outgoing terminations
for inter-phasing to other components, all complete.
Set 1 -
2.5Control and power cable inside
powerhouse:
16 mm2
4 core cupper armored cable, for interconnecting generator, control
panel, ELC, ballast, sensors etc, all completem 15 -
2.6 Power cable :25 mm
24 core aluminum armored cable for control panel feeder terminals
(main switch) to the first pole, all completem 20 -
2.7
Materials for power house
wiring including necessary
lighting and power fixtures
Power house wiring with 5 light points and 2 power points, all complete. 4'*
40 watt tube lights - 2 nos, 75 watt bulbs with holders-3 nos, and single
phase power socket- 2 nos with necessary number of switches and wires.
L.S. 1 -
2.8 Energy meter As Per AEPC's CC unit Specification No. 1
Sub- Total (II)
III
Conductors: ACSR conductors
ACSR conductors, suspended overhead, with minimum of 4.5 ground
clearance, having clearance of 300 mm between them. These should have
approved current rating by NS.
a. Squirrel Resistance:>1.374 ohms/ km m 17780 -
b. Weasel Resistance:>0.9116 ohms/km m 1060 -
c. Rabbit Resistance:>0.5449 ohms/ km m 4600 -
d. Dog m 4290
3.2 Service wire (4 mm2) Concentric cable m 3510 -
Medium size Nos 114 -
Small size Nos 473
Large size Nos 155
3.4 Stay sets Should include guy wire, turn buckle, rod, insulators and plates, all complete Sets 68 -
3.5
Lightning arrestors:
0.5 kV with necessary stand and
accessories, all complete
Lightning arrestors to be provided at every 500 m for current carrying
conductors. All joints along the earth path should be able to carry a lightning
strike of 20 kA.
Set 43 -
3.6 Earthing arrangements:8 SWG copper earth wire, 600 x 600 x 3 mm copper plate as earth electrode
with necessary coke, lime, salt, nut, bolts, washer etc. all complete.Sets 18 -
Sub Total (III)
3.1
3.3
Insulators (shackle) with 'D'
Irons with necessary nuts, bolts,
etc. all complete
Transmission / Distribution Systems
Electrical Equipment
140355064.xls.ms_office
-
7/28/2019 2) BOQ - Nibu Khola IX MHS (12 kW) Nawmidanda VDC Panchthar_20120928040957
3/3
IV
Spare Parts : For turbine, generator, control panel and load controlling set
etc. as deemed necessary. 10 % of bolts, one set gaskets and seals, HRC
Fuse, Panel meter, one set of bearings of turbine and generators thyristers,
Insulators, grease 1 kg
L.S. 1 -
Tools : Complete electromechanical tools set with tool box, which includes
tester, digital clamp meter, hammer, slide wrench, grease gun, screw driver
sets, flat and round file, hacksaw frame & 5 blades, chisel, wire steeper.
HRC fuse 3 sets, 3 thyristers as spare, wire puller 2 ton, 2 safety belts, 2
safety helmets, alluminium ladder folding type (20 ft. long & 3.5 mm thick
plate ISO standard).
L.S. 1 -
Sub Total (IV)
V
a. Site Verification L.S. -
b.Civil Works Supervision L.S.
c. Mechanical Equipment Installations L.S. -
d. Electrical Equipment Installation L.S. -
e. Erection / Fixation of Transmission / Distribution Lines L.S. f. Testing & Commissioning L.S. -
Sub Total (V)
Cost Summary
I. Mechanical Equipments -
II. Electrical Equipments -
III. Transmission and Distribution -
IV. Spare parts and tools -
-
-
-
V. Installation & Testing and others -
-
Net total Rupees in word:
Note:
4. Photo copy of Pre- qualification certificate by AEPC should be submitted.
Official Seal
4.1
Miscellaneous
3. Form should be submitted with authorized person's signature and official seal in each page.
Grand Total Rs.
Spare Parts and Tools:
Site verification, civil works
supervision, Installation,
erection, testing &
commissioning including
maintenance for one year, all
complete
5.1
Site verification, civil works supervision, installation, erection, testing & commissioning including
5. Pre- qualification validity renewal certificate by AEPC should be submitted.
Sub-Total (A)
VAT (13%)
Total (Sub-Total + VAT)