Transcript of 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant...
![Page 1: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/1.jpg)
1
Welcome to the International Right of Way
Association’s
Course 303Managing the
Consultant Process
303-PT – Revision 3 – 01.30.08.USA
![Page 2: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/2.jpg)
2
Course Purpose
Government’s role is changing from…
staff to consultant
“doer” to manager
staff assignments to consultant contracting
…eventually, there will be a rebalancing.
![Page 3: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/3.jpg)
3
Introductions
Who we are…
What we do…
Where we do it…
How long we’ve been doing it…
Our goals for the course...
![Page 4: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/4.jpg)
4
Objectives (1) At the conclusion of the course,
you will be able to...
• Understand better the contracting process
• Avoid common mistakes and misunderstandings in proposal development
• Evaluate proposal submissions
![Page 5: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/5.jpg)
5
Objectives (2) At the conclusion of the course,
you will be able to...
• Monitor consultant work effort
• Understand better the issues and concernsof both agencies and consultants
• Engage in best practices
![Page 6: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/6.jpg)
6
Housekeeping
![Page 7: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/7.jpg)
7
Schedule (1)
8:00 - 9:00 Introductions, Etc.
9:00 - 12:00 Why and When to Use a Consultant
1:00 - 3:00 Proposal Elements
3:00 - 4:15 Consultant Proposal Evaluation
(start)
4:15 - 4:30 Recap Day One
![Page 8: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/8.jpg)
8
Schedule (2)
8:00 - 8:15 Recap Day One/Introduce Day Two
8:15 - 9:15 Consultant Proposal Evaluation (conclude)
9:15 - 10:30 Contract Execution Process
10:45 - 12:00 Consultant Monitoring (start)
1:00 - 2:00 Consultant Monitoring (conclude)
2:15 - 2:45 Invoicing and Auditing Issues
2:45 - 3:45 Process Evaluation
3:45 - 4:45 Post-Test
4:45 - 5:00 Summary and Review
![Page 9: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/9.jpg)
9
Fact or Fiction?(1)
Agency:“A consultant should only be used as a last resort.”
Consultant:“The agency only contracts out the impossible projects.”
![Page 10: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/10.jpg)
10
When to Use Consultants
• Project demands
• Staffing issues
• Political/other issues
![Page 11: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/11.jpg)
11
Wrong Reasons to Use Consultants
• Impossible timing
• No schedule
• No defined scope of work
![Page 12: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/12.jpg)
12
Agency Considerations
Will a consultant result in the best use of the agency’s staff?
Will a consultant result in the best use of the agency’s financial resources?
Does the agency have oversight capabilities?
Will a consultant affect the agency staff?
![Page 13: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/13.jpg)
13
Why Consultants arein Business
• Make money
• Offer a service and meet a need
• Provide staff flexibility
• Provide general and specialized expertise
![Page 14: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/14.jpg)
14
Contracting Methods
• Sole Source
• Special/Specific Task
• Turnkey
![Page 15: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/15.jpg)
15
Solicitation Methods
• LOI/SOI
• RFQ/SOQ
• RFP
![Page 16: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/16.jpg)
16
Developing a ProspectiveProposers’ List
• Scope of solicitation
• Solicitation methods• Established list
• Pre-qualified list
• Publication and Advertisement
![Page 17: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/17.jpg)
17
Fact or Fiction?(2)
Agency:“The scope of work can always bechanged if we overlook something.”
Consultant:“The scope of work is the most important part of the contract process.”
![Page 18: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/18.jpg)
18
Proposal Elements (1)
• Project description
• Scope of work
• Agency responsibilities
• Contractor responsibilities
• Project schedule
• Specific agency contracting requirements
![Page 19: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/19.jpg)
19
Proposal Elements (2)
• Subcontractor identificationand requirements
• Insurance
• Cost and pricing methods
• Interviews
• Evaluation criteria
• Pre-proposal meetings
![Page 20: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/20.jpg)
20
Proposal Elements (3)
• Timing issues for proposal issuance
• Proprietary information
• Appeals and protests
• Sampler contractes and forms
• Other elements
![Page 21: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/21.jpg)
21
Fact or Fiction?(3)
Agency:“The consultant will always use personnel in their proposal that look good – but they never show up on the project.”
Consultant:“The agency doesn’t read the proposal.”
![Page 22: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/22.jpg)
22
Day One Recap
![Page 23: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/23.jpg)
23
Recap Day OneIntroduce Day Two
![Page 24: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/24.jpg)
24
Case Study No. 2
![Page 25: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/25.jpg)
25
Fact or Fiction?(4)
Agency:“Starting a project without a signed contract is an acceptable process.”
Consultant:“There is so much ‘boilerplate’ in the contract that doesn’t apply to me.”
![Page 26: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/26.jpg)
26
Contracts
• Formal agreements
• Purchase orders
• Master contract with task orders
![Page 27: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/27.jpg)
27
Conflicts (1)
You have some concerns with the progress that a consultant is making and have discussed
it at progress status meetings.
A few days later, the consultant’s project manager calls and invites you to be his guest to
play golfat an exclusive local country clubto discuss the “progress issue.”
![Page 28: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/28.jpg)
28
Conflicts (2)
During the holiday season, a consultant sends you a basket of fruit,
candy and Napa Valley wine.
![Page 29: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/29.jpg)
29
Conflicts (3)
One of the consultants, with whom you do business, takes you and your staff to
lunch and picks up the tab.
![Page 30: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/30.jpg)
30
Conflicts (4)
You have a project that will eventually be contracted out. A consultant who is likely to submit a proposal
is in your office for a “cold call” visit. The consultant gives you several pens, a calendar
and a really nice traveling coffee mug. You accept the gifts and hand out the pens
to people in the office, you give the calendar to your
significant other and keep the coffee mug.
![Page 31: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/31.jpg)
31
Notice to ProceedYou ask one of your consultant appraisers to get a jump on an assignment. You believe and tell the appraiser that the notice to
proceed will be issued next week. Next week arrives with no authorization to proceed. You ask the consultant to continue
her work, which she does.
The following week, you receive a call from the project manager, who tells you that the project has been delayed
for a year and to stop all work. You are getting readyto telephone the appraiser.
What do you say?
The appraiser asks you how she will get paid for the work she has done on the appraisals.
What do you say?
![Page 32: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/32.jpg)
32
Fact or Fiction?(5)
Agency:
“We hired the best consultant available; why does he/she née so much oversight?”
Consultant:“ Why can’t we get answers to our questions/issues in a
timely manner?”
![Page 33: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/33.jpg)
33
Keys in Monitoring Projects
• Project staffing
• Reporting
• Schedule compliance
• Work product review
• Budget adherence
• Compliance
• Feedback
![Page 34: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/34.jpg)
34
Fact or Fiction?(6)
Agency:“The consultant is getting rich on this contract –
the claim for payment can wait a week or so.”
Consultant:“The proposal states that payment will be made in
30 days – it takes nearly 90 days to receive it.”
![Page 35: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/35.jpg)
35
Sixth Corollary
The sixth corollary to Murphy’s Law is:
The first invoice neverhas a chance.
![Page 36: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/36.jpg)
36
Fact or Fiction?(7)
Agency:“The consultant is only interested in moving
on to the next job.”
Consultant:“The agency doesn’t really want a critique
of its program.”
![Page 37: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/37.jpg)
37
Agency Complaints
• The consultant does the easy work…
• The consultant pulls the “bait and switch”...
• The consultant doesn’t follow up...
![Page 38: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/38.jpg)
38
Consultant Complaints
• The agency doesn’t provide the deliverables
• The agency doesn’t pay promptly
• The agency withholds forms and documents
![Page 39: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/39.jpg)
39
Objectives (1) Now, you are able to...
• Understand better the contracting process
• Avoid common mistakes and misunder- standings in proposal development
• Evaluate proposal submissions
![Page 40: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA.](https://reader036.fdocument.pub/reader036/viewer/2022062309/5697bfc71a28abf838ca7889/html5/thumbnails/40.jpg)
40
Objectives (2) Now, you are able to...
• Monitor consultant work effort
• Understand better the issues andconcerns of both agencies and consultants
• Engage in best practices