محاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEot
-
Upload
- -
Category
Engineering
-
view
960 -
download
15
Transcript of محاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEot
هشام عبد الخالق. د.أ
أستاذ هندسة و إدارة التشد
جامعة االسكندرة -كلة الهندسة
Lecture Contents
Types of Contracts.
FIDIC Claims, Dispute and Arbitration.
Types of Claims.
Claims Life Cycle.
Claim Analysis
Case Study
CONSTRUCTION CONTRACTS
Classified by Method of Evaluating Contract Cost.
(تصنف حسب تقم التكلفة)
Classified by Method of Bidding.
(تقم حسب طرقة الطرح)
Special Contracts
Contract types according to Contract Cost1. Fixed Price Contracts عقود السعر الثابت
a) Lump Sum / Stipulated Price
b) Unit Price / Bill of Quantity (BOQ)
c) Fixed Price with Escalation / Price Adjustable
Day one Dollar one Escalation (Inflation)
Significant Increase Escalation
Delay Escalation
Escalation can be measured by
Index formula
Percentage
Contract types according to Contract Cost2. Cost Reimbursement Contracts عقود التكلفة المستردة
Sometimes called Cost Plus or Prim Cost
a) Cost Plus Fee
b) Cost Plus Percentage
c) Cost Plus percentage with guaranteed maximum
d) Cost plus percentage with guaranteed. max. with bonus
e) Cost Plus target
Contract types according to Method of Bidding
Competitive Contracts
Negotiated Contracts
Combination between Comptetivness and Negotiation
Special Contracts Partnering Contracts
PPP Contracts
Package Contract
Turnkey Contract
Continuous Contract
Serial Contract
Running Contract
Service/maintenance Contract
FIDIC “ Claims, Disputes and Arbitration ”
9
Prof. Dr. Hisham Abd Elkhalek
Contracting
1987فيديك (53)وفق البند املطالبـات
10
نشـأة
المطالبـة
هـل ارسـل المقـاول اخطار الى المهندس
وما من حدوث 28بنته فى المطالبة خـالل
سـبب المطالبة
نهـاية المطالبـة
اصدار المهندس قراره
بمستحقات المقـاول بعـد االطالع على السجـالت
التفصله واخطار المقاول به
مع ارسال صـورة الى رب العـمل
ال تتجـاوز مستحـقات المقاول المبلغ
حـدده المهندس أو أى محكم الذى
هـل أرسل
وما 28المقاول خالل
اخرى او مدة
قبلها المهندس حسابا
تفصلا بالمبالغ المطلوبة
ال
ال
نعم
نعم
Contracting
1987فيديك االحمرمن الكتاب 67وفق البند حل المنازعات الناجمه فى مشروع التشييد
11
احالة الخالف الى المهندس كتابة وإرسال صورة الى الطرف االخر
مع االستمرار فى العمل1/ 67وفقا للبند
قراره المهندسأصدر تارخ االحالة ؟ وما من 84خالل
تسلم اخطارات بذلك
لكل من رب العمل والمقاول اخطار الطرف االخر بنة
اللجوء الى التحكم واخطار المهندس
على هل وجد اعتراض
قرار المهندس خالل
وما من تارخ 70
التسلم
إجراء محاوالت التسوة الودة
وما من تارخ اإلخطار 56خالل
الودة هـل نجحت التسوهتم تنفـذ قرار هـل
المهنـدس؟
نشــوب خــالف
اللجوء الى التحكيم
حسم الخـالف
ال
نعمنعم
نعم
الال
20بند رقم فـض المنازعـــات
12
وقوع الحدث المنشأ للمطالبة
إعداد مذكرة تفصلة
وما من 42خالل
علمه أو وجوب علمه
هل تقدم
بمطالبةالمقاول
وما 28خالل
حقلس للمقاول
له ف أة
تعوضات مدة
أو تكلفة
المهندس رد
أخرى وما 42خالل
عرض األمر
عل مجلس
فض المنازعات
هل توصل
المجلس إل قرار
وما 84خالل
خطر الطرف
المتضرر الطرف
اآلخر برغبته
ف اللجوء إل التحكم
وما 28خالل
هل ارتض الطرفان
محاولة التسوة الودـة
من تارخ القرار وما 56خالل
هل نجحت التسوة
اللجوء إل التحكم
هل ارتض
الطرفان القرار
تمت تسوة
نعمالنزاع
ال
ال
ال
نعم
نعم
نعم
نعم
ال
ال
ال
نعم
1999فيديك
20بند رقم فـض المنازعـــات
13
وقوع الحدث المنشأ للمطالبة
إعداد مذكرة تفصلة
وما من 42خالل
علمه أو وجوب علمه
هل تقدم
بمطالبةالمقاول
وما 28خالل
حقلس للمقاول
له ف أة
تعوضات مدة
أو تكلفة
المهندس رد
أخرى وما 42خالل
عرض األمر
عل مجلس
فض المنازعات
هل توصل
المجلس إل قرار
وما 84خالل
خطر الطرف
المتضرر الطرف
اآلخر برغبته
ف اللجوء إل التحكم
وما 28خالل
هل ارتض الطرفان
محاولة التسوة الودـة
من تارخ القرار وما 56خالل
هل نجحت التسوة
اللجوء إل التحكم
هل ارتض
الطرفان القرار
تمت تسوة
نعمالنزاع
ال
ال
ال
نعم
نعم
نعم
نعم
ال
ال
ال
نعم
1999فيديك
التحكيم الدولى فى المنازعات
Contracting 14
Inst
itu
tio
nal
A
rbit
rati
on
التحكيــــم :
غرف من غرفة أي ف الصادرة القواعد أحد تكون التحكم قواعد
. التحكم قوانن من قانون ألي طبقا أو التحكم
المحكمن تعن .
التحكم إجراءات .
15Contracting
Contracting 16
غرفة التجارة الدولة(ICC)
هئة التحكم األمركة(AAA)
محكمة لندن للتحكم التجارى الدولى(LCIA)
مركز القاهرة اإلقلمى للتحكم التجارى الدولى(CRCICA)
منظمة التجارة العالمة(WTO)
بنك التسوات الدولى(BIS)
هيئات التحكيم الدولية
Dr. Hesham Abdelkhalek 17
Delay Event
Types of Delay
Dr. Hesham Abdelkhalek 20
Types of Delay
Dr. Hesham Abdelkhalek 21
Types of Delay
Dr. Hesham Abdelkhalek 22
Types of Delay
Dr. Hesham Abdelkhalek 23
Types of Delay
Dr. Hesham Abdelkhalek 24
Types of Delay
Dr. Hesham Abdelkhalek 25
Types of Delays and Responsibility
YesNO
Life cycle of construction claims
1. Claim identification
2. Claim notification
3. Claim examination
4. Claim documentation
5. Claim presentation
6. Claim negotiation
Claim Identification
Construction claim identification involves the accurate detection of a construction claim in time. This is the critical and important stage of the claim process.
For example, some very strong deserved construction claims are lost solely due to failure of identifying them.
Claim Notification
Construction claim notification means alerting the other party of a potential problem in a manner that is non adversarial.
This alert (notification) must be done with the Time limit that is mentioned in the contract.
Claim Examination
Construction claim examination means to establish the legal and factual basis on which the claim is to be developed.
This stage involves also an accurate estimation of the potential recovery.
This action has to be investigated by interviewing the staff who will be working in the project. The primary sources for claim examination could deal with project files, video footage, memos, etc., that must be used to prove the time and cost elements of the claim.
Claim Documentation
Construction claim documentation is the collection of the hard facts that give the actual history of a construction claim. A well-prepared defendant quickly demolishes evidence and claim costs that are not supported by accurate records.
The documented facts are the clue that holds the legal framework together. If these are insufficient the claim will not stick.
Claim Presentation
Construction claim presentation should be logically built up, well organized, and factually convincing. Thus, a claim should be written in a format that emphasizes the fact that a contract requirement is breached.
A contractor must then demonstrate the resulting harms which are caused by the owners’ acts. (Cox 1997) has fittingly said that presentation preferred to be separated into two, the entitlement and the quantum.
The former section should have the legal and factual basis while the later should provide the estimated recovery of the claim.
Claim Negotiation
According to (Easton 1989) a structured and proper negotiation preparation includes: ascertaining that all information is current and complete; minimizing the scope of negotiation beforehand so that
insignificant points should not precipitate a violent argument and disrupt progress;
knowing one’s weaknesses and trying to utilize weak points by conceding them in return from the other party;
foreseeing problems; and Anticipating the opposition’s next move. There is a saying that ‘‘it is more important to be prepared
than to be right”
Categories of Delay Analysis
Dr. Hesham Abdelkhalek 42
Dr. Hesham Abdelkhalek 43
Time Impact Analysis – Snapshot Analysis
Dr. Hesham Abdelkhalek 44
Time Impact Analysis – Window Analysis
Dr. Hesham Abdelkhalek 45
Dr. Hesham Abdelkhalek 46
As-Planned versus As-BuiltThis method aims to compare the duration of an as-
planned activity on the program with the as-built duration
for that same activities on the as-built program. The
difference in time between these durations is taken as the
period of delay to which a Contractor is entitled to an
Extension of Time as a result of an excusable delay event.
Dr. Hesham Abdelkhalek 47
Selecting the suitable analysis method
Dr. Hesham Abdelkhalek 48
Accurate baseline
Accurate As-built
Selecting the suitable analysis method
Dr. Hesham Abdelkhalek 49
Accurate baseline and Updates
Accurate baseline and As-built
PEC-EG-11012 51
THERMAL POWER PLANTUNITS 6&7 - 2X650 MW GAS/OIL FIRED UNITS
INTAKE, DISCHARGE AND RELATED WORKS
POSITION PAPER
In respect ofTHE ENTITLEMENT FOR EXTENSION OF TIME
no Event start1 Site Mobilization Allocation and bechmarks 5-Oct-092 Re-rout of gas pipelines 6-Sep-093 Providing Offshore permit 6-Sep-094 Off Site Area 30-Dec-095 protection plane approval for Dewatering 16-Mar-106 permanent cofferdam soil investigation 30-Jun-107 Excavation of Intake Pipes 12-Jul-108 Stopping work due to Petroleum company helicopter runway 29-Sep-10
9 25 Jan force majour 28-Jan-1110 Fuel Shortage (May 2011) 11-May-1111 Site Close Off 15-Jun-1112 Contaminated Discharge Water 21-Jul-1113 Intake Filling Delay 18-Aug-1114 Disturbance of off-shore works 27-Aug-1115 Bad Weather Conditions 10-Dec-1116 Fuel Shortage (Jan 2012) 22-Jan-1217 CP-102 Caused Delays fragmented18 Truck Drivers Strike 9 Dec 11
PEC-EG-11012 52
Major Events
New events marked
Site Mobilization Allocation
Activity Affected:Mobilization activity( 1000000290)
53PEC-EG-11012
Off-site area delivery
Activities Affected
Affect directly on delivery of RCC pipes activity (SUBMT00020& SUBMT00030) which effect directly on Installing ofDischarge pipes (1000001681) in discharge area and StartConstruction of intake basin & inlet pipes (1000000530) inintake area.
54PEC-EG-11012
Re-rout of gas pipelines
Activities Affected Earth work for rough grading activity (SPECS00250)that leads to channel (1-4) diversion activities andcause delay of discharge and intake area.
55
16” gas pipeline
24” gas pipeline
PEC-EG-11012
Providing Offshore permit
Activities Affected
Execution of cofferdam protection (1000000630) andDemolish shoreline protection (1000000940) that lead todelay of channel (1-4) diversion activities.
56PEC-EG-11012
protection plan approval for Dewatering
Activities Affected Mobilization of dewatering equipment activity(1000000900) which is the first activity in DiversionChannel (1-4) on critical path. 57PEC-EG-11012
Stoppage due to petroleum company helicopter runway
• Affect directly on the production all discharge structure activities that starts in (Start Const. of the new Disch& Seal Well) milestone (1000000460).
• After the stoppage ends WDEPC Project instructed AC should reduce its working hours from (63-hours per week) to (31 hours per week) from (Saturday to Thursday).
• Accordingly, AC worked on reduced productivity, based on the work was not continuous.
58PEC-EG-11012
25th January force Majeure.
Full Stoppage: The work at job site was completely suspended from 28th of
Jan 2011 till 16th of Feb 2011.
This suspension affected All in progress activities in February update.
Curfew Effect: The curfew was imposed by the supreme council of the
military after the uprising event.
Impact on supplies: The delivery of earth products as sand, gravel, stones….etc. are usually taken place from late evening to early morning hours.
Curfew Impact from 16 Feb till end of June that made disruption of work
59PEC-EG-11012
Sep 2009Sep 2010
Change order No.20
Project start
8 Periods
Stage 1 Stage 2
Mar 2012Jan 2011
3 Periods
Last Update
Delay Analysis and EOT Entitlement
60
W1 start W1 PCD W1 imp PCD
EOTEntitlement = 47 days
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 6-Sep-09 18-Mar-11
Window
End W2 17-Jan-10 28-Jun-10
Impacted
Programme
(W1 with events – DD is
as W1) 6-Sep-09 4-May-11
47 0 7
Events:
• Off-site area delivery• Re-rout of gas pipelines • Providing Offshore permit• Providing site benchmark• Site Mobilization allocation
Project Duration
Period 1: from Sep 2009 (project start) to Jan 2010
Site Mobilization allocation
61
EOT Entailment = W1 Impacted PCD - W1 PCDMitigation= W1 Impacted PCD – W2 PCD Non Progress = W2 PCD - W1 Impacted PCD
W1 start W1 imp PCD
Non-Progress= 7 days
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 6-Sep-09 18-Mar-11
Window
End W2 17-Jan-10 28-Jun-10
Impacted
Programme
(W1 with events – DD is
as W1) 6-Sep-09 4-May-11
47 0 7
Events:
• Off-site area delivery• Re-rout of gas pipelines • Providing Offshore permit• Providing site benchmark• Site Mobilization allocation
Project Duration
Period 1: from Sep 2009 (project start) to Jan 2010
W2 PCD
Site Mobilization allocation
62
EOT Entailment = W1 Impacted PCD - W1 PCDMitigation= W1 Impacted PCD – W2 PCD Non Progress = W2 PCD - W1 Impacted PCD
W1 start W1 PCD W1 imp PCD
EOTEntitlement = 10
days
Events:
• Off-site area delivery• Re-rout of gas pipelines• Providing offshore permit
Project Duration
Period 2: from Jan 2010 to Feb 2010
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 17-Jan-10 11-May-11
Window
End W2 7-Feb-10 1-Jun-11
Impacted
Programme
(W1 with events – DD is
as W1) 17-Jan-10 21-May-11 10 0 11
Re-rout of gas pipeline
63
EOT Entailment = W1 Impacted PCD - W1 PCDMitigation= W1 Impacted PCD – W2 PCD Non Progress = W2 PCD - W1 Impacted PCD
Events:
• Off-site area delivery• Re-rout of gas pipelines• Providing offshore permit
Period 2: from Jan 2010 to Feb 2010
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 17-Jan-10 11-May-11
Window
End W2 7-Feb-10 1-Jun-11
Impacted
Programme
(W1 with events – DD is
as W1) 17-Jan-10 21-May-11 10 0 11
W1 start W1 imp PCD
Non-Progress= 11 days
Project Duration
W2 PCD
Re-rout of gas pipeline
64
W1 start
W1 PCD
W1 imp PCD
EOTEntitlement = 0
days
Events:
• Off-site area delivery• Re-rout of gas pipelines• Providing offshore permit
Project Duration
Period 3: from Feb 2010 to Mar 2010
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 7-Feb-10 1-Jun-11
Window
End W2 7-Mar-10 18-May-11
Impacted
Programme
(W1 with events – DD is
as W1) 7-Feb-10 1-Jun-11 0 14 0
65
Events:
• Off-site area delivery• Re-rout of gas pipelines• Providing offshore permit
Period 3: from Feb 2010 to Mar 2010
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 7-Feb-10 1-Jun-11
Window
End W2 7-Mar-10 18-May-11
Impacted
Programme
(W1 with events – DD is
as W1) 7-Feb-10 1-Jun-11 0 14 0
W1 start W1 PCD
Mitigation= 14 days
Project Duration
W2 PCD
66
EOT Entailment = W1 Impacted PCD - W1 PCDMitigation= W1 Impacted PCD – W2 PCD Non Progress = W2 PCD - W1 Impacted PCD
W1 startW1 PCD
W1 imp PCD
EOTEntitlement = 0
days
Events:
• Off-site area delivery• protection plan approval for
Dewatering
Project Duration
Period 4: from Mar 2010 to Apr 2010
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 7-Mar-10 18-May-11
Window
End W2 11-Apr-10 11-Jun-11
Impacted
Programme
(W1 with events – DD is
as W1) 7-Mar-10 18-May-11 0 0 24
67
Events:
• Off-site area delivery• protection plan approval for
Dewatering
Period 4: from Mar 2010 to Apr 2010
W1 start W1 PCD
Non-progress = 24 days
Project Duration
W2 PCD
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 7-Mar-10 18-May-11
Window
End W2 11-Apr-10 11-Jun-11
Impacted
Programme
(W1 with events – DD is
as W1) 7-Mar-10 18-May-11 0 0 24
68
W1 start W1 PCD W1 imp PCD
EOTEntitlement = 27
days
Events:
• protection plan approval for Dewatering
Project Duration
Period 5: from Apr 2010 to Jun 2010
protection plan approval for Dewatering
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 11-Apr-10 11-Jun-11
Window
End W2 6-Jun-10 28-May-11
Impacted
Programme
(W1 with events – DD is
as W1) 11-Apr-10 8-Jul-11 27 41 0
69
Events:
• protection plan approval for Dewatering
Period 5: from Apr 2010 to Jun 2010
W1 start W1 imp PCD
Mitigation= 41 days
Project Duration
W2 PCD
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 11-Apr-10 11-Jun-11
Window
End W2 6-Jun-10 28-May-11
Impacted
Programme
(W1 with events – DD is
as W1) 11-Apr-10 8-Jul-11 27 41 0
protection plan approval for Dewatering
70
W1 startW1 PCD
W1 imp PCD
EOTEntitlement = 0
days
Events:
• protection plan approval for Dewatering
Project Duration
Period 6: from Jun 2010 to July 2010
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 6-Jun-10 28-May-11
Window
End W2 4-Jul-10 13-Jun-11
Impacted
Programme
(W1 with events – DD is
as W1) 6-Jun-10 28-May-11 0 0 16
71
Events:
• protection plan approval for Dewatering
Period 6: from Jun 2010 to July 2010
W1 start W1 PCD
Non-progress = 16 days
Project Duration
W2 PCD
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 6-Jun-10 28-May-11
Window
End W2 4-Jul-10 13-Jun-11
Impacted
Programme
(W1 with events – DD is
as W1) 6-Jun-10 28-May-11 0 0 16
72
Events:
• protection plan approval for Dewatering
• Excavation of Intake Pipes
Period 7: from July 2010 to Aug 2010
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 4-Jul-10 13-Jun-11
Window
End W2 1-Aug-10 19-Jun-11
Impacted
Programme
(W1 with events – DD is
as W1) 4-Jul-10 13-Jun-11 0 0 6
73
W1 start W1 imp PCD
EOT= 6 days
Project Duration
W2 PCD
Excavation of Intake Pipes
Events:
• protection plan approval for Dewatering
• Excavation of Intake Pipes
Period 7: from July 2010 to Aug 2010
W1 start W1 PCD
Non-progress = 6 days
Project Duration
W2 PCD
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 4-Jul-10 13-Jun-11
Window
End W2 1-Aug-10 19-Jun-11
Impacted
Programme
(W1 with events – DD is
as W1) 4-Jul-10 13-Jun-11 0 0 6
74
W1 start W1 PCD W1 imp PCD
EOTEntitlement = 19
days
Events:
• protection plan approval for Dewatering
• Stoppage due to petroleum company helicopter runway
Project Duration
Period 8: from Aug 2010 to Sep 2010
protection plan approval for Dewatering
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 1-Aug-10 19-Jun-11
Window
End W2 19-Sep-10 24-Jul-11
Impacted
Programme
(W1 with events – DD is
as W1) 1-Aug-10 8-Jul-11 19 0 16
75
Events:
• protection plan approval for Dewatering
• Stoppage due to petroleum company helicopter runway
Period 8: from Aug 2010 to Sep 2010
W1 start W1 imp PCD
Non-Progress= 16 days
Project Duration
W2 PCD
protection plan approval for Dewatering
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 1-Aug-10 19-Jun-11
Window
End W2 19-Sep-10 24-Jul-11
Impacted
Programme
(W1 with events – DD is
as W1) 1-Aug-10 8-Jul-11 19 0 16
76
Events:
• Complete work suspension from 28th of January to 16th Feb
• Curfew Impact from 16 Feb till end of June
• Fuel Shortage (May 2011)• Site Close Off
Period 9: from Jan 2011 to Jun 2011
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 28-Jan-11 26-May-12
Window
End W2 30-Jun-11 11-May-12
Impacted
Programme
(W1 with events – DD is
as W1) 28-Jan-11 24-Jul-12 59 74 0
77
W1 start W1 imp PCD
Project Duration
Complete work suspension from 28th of January to 16th Feb Curfew Impact from
16 Feb till end of June
EOT =59 days
W2 PCD
Fuel Shortage (May 2011)
Site Close Off
Events:
• Complete work suspension from 28th of January to 16th Feb
• Curfew Impact from 16 Feb till end of June
• Fuel Shortage (May 2011)• Site Close Off
Period 9: from Jan 2011 to Jun 2011
W1 start W1 imp PCD
Project Duration
Complete work suspension from 28th of January to 16th Feb Curfew Impact from
16 Feb till end of June
Mitigation =74 days
W2 PCD
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 28-Jan-11 26-May-12
Window
End W2 30-Jun-11 11-May-12
Impacted
Programme
(W1 with events – DD is
as W1) 28-Jan-11 24-Jul-12 59 74 0
78
Fuel Shortage (May 2011)
Site Close Off
Events:
• Contaminated Discharge Water
• Intake Filling Delay• Disturbance of off-shore works• CP-102 Caused Delays• Truck Drivers Strike
Period 10: from Jun 2011 to Oct 2011
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 30-June-11 11-May-12
Window
End W2 30-Oct-11 15-Jul-12
Impacted
Programme
(W1 with events – DD is
as W1) 30-June-11 11-May-12 0 0 65
79
W1 start W1 imp PCD
Project Duration
EOT =32 days
W2 PCD
• Intake Filling Delay
• CP-102 Caused Delays
• Disturbance of off-shore works
• Contaminated Discharge Water
• Truck Drivers Strike
Period 10: from Jun 2011 to Oct 2011
W1 start W1 PCD
Non-progress = 12 days
W2 PCD
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 30-June-11 11-May-12
Window
End W2 30-Oct-11 15-Jul-12
Impacted
Programme
(W1 with events – DD is
as W1) 30-June-11 11-May-12 0 0 65
80
Events:
• Contaminated Discharge Water
• Intake Filling Delay• Disturbance of off-shore works• CP-102 Caused Delays• Truck Drivers Strike
• Intake Filling Delay
• CP-102 Caused Delays
• Disturbance of off-shore works
• Contaminated Discharge Water
• Truck Drivers Strike
Period 11: from Oct 2011 to Mar 2011
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 30-June-11 11-May-12
Window
End W2 30-Oct-11 15-Jul-12
Impacted
Programme
(W1 with events – DD is
as W1) 30-June-11 11-May-12 0 0 65
81
W1 start W1 imp PCD
Project Duration
EOT =12days
W2 PCD
Events:• Bad Weather Conditions• Fuel Shortage (Jan 2012)
• Fuel Shortage (Jan 2012)
• Bad Weather Conditions
W1 start W1 PCD
Non-progress = 12 days
W2 PCD
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 30-June-11 11-May-12
Window
End W2 30-Oct-11 15-Jul-12
Impacted
Programme
(W1 with events – DD is
as W1) 30-June-11 11-May-12 0 0 65
82
Events:• Bad Weather Conditions• Fuel Shortage (Jan 2012)
Period 11: from Oct 2011 to Mar 2011
• Fuel Shortage (Jan 2012)
• Bad Weather Conditions
83
Total EOT Entitlement
Stage Period EOT
Mitigation Non
Progress Entailment
On
e
1 47 0 7
2 10 0 11
3 0 14 0
4 0 0 24
5 27 41 0
6 0 0 16
7 0 0 6
8 19 0 16
Tw
o
9 59 74 0
10 0 0 65
Sum 162 129 145