SUKHOTHAI PRE

Post on 08-Jan-2017

28 views 1 download

Transcript of SUKHOTHAI PRE

SOIL PROTECTION SYSTEM

PROJECT: THE SUKHOTHAI RESIDENCES

SOIL PROTECTION SYSTEM

HIROSE (THAILAND) LTD.

The Sukhothai

Residences

INSTALLATION KING POST & PLATFORM

Installation King Posts & Platforms HIROSE (THAILAND) LTD.

Tip KP -22.00m.

Tip KP -21.00m.

EXCAVATION WORK LAYOUT

EXCAVATIONZONE 2 ZONE 1ZONE 3

BERM 6 m.

ZONE 2 ZONE 3

BRACING LAYOUT PRELOADING METHOD

PRESSURE GUAGE

PRESSURE GUAGEPRESSURE GUAGE

EXCAVATION WORK AND BRACING LAYOUT

COMBINED BRACING & EXCAVATION HIROSE (THAILAND) LTD.

EXCAVATION

2

3

4

5

1

6

1

7

2

3

4

5 6

7

1

2 3

4

5

6

7

8

14

1

2

,INCLINOMETER BUILDING SETTLEMENT

STAND PIPE

STAND PIPE

MONITERING SYSTEM PLAN

10 1

1 12

13

159

INCLINOMETER

1

2

3

4

5

6

7

8

9

10

11

13

14

15

16

17

12

1

2

3

4

5

6

,GROUND SETTLEMENT

12

-21.00,-22.00mH-350x350x12x19

-1.00

DRIVING KING POST

D -WALL

KINGPOST

HIROSE (THAILAND) LTD.

TOP KINGPOST -1.00

-21.00,-22.00m

D -WALL

H-350x350x12x19

-3.00

-1.00 PLATFORM+0.75

2.00

1ST EXCAVATION -3.00 M

HIROSE (THAILAND) LTD.

-21.00, -22.00m

D- WALL

H-350x350x12x19

2.00

-3.00

-1.00 PACKING CONCRETE

-2.50 1ST STRUT ;W35HA(H350X350X12X19)

PLATFORM+0.75

Pre-Load 90TON

INSTALL 1ST BRACING ELEV. -2.50

M.

HIROSE (THAILAND) LTD.

-21.00,22.00m

D - WALL

H-350x350x12x15

-7.00

-1.00 PLATFORM+0.75

1ST STRUT

BERM INCASE EXCAVATION AT THE MIDDLE FIRST HIROSE (THAILAND) LTD.

-2.50m

4.50

6.00

EFFECTIVE LENGTH(BERM)

W

-21.00.-22.00m

D-WALL

H-350x350X12x19

-7.00m

PLATFORM+0.75

1ST STRUT

-1.00m.

2nd EXCAVATION ELEV.-7.00m

HIROSE (THAILAND) LTD.

Pre-Load 90 TON

-21.00,22.00m

D - WALL

H-350x350x12x15

-7.00

-1.00 PLATFORM+0.75

1ST STRUT -2.50

2nd STRUT -6.00

PACKING CONCRETE

INSTALLATION 2ndBRACING -6.00

m.

HIROSE (THAILAND) LTD.

-21.00.-22.00m

D-WALL

H-350x350X12x19

-10.50m

PLATFORM+0.75

1ST STRUT -2.50

-1.00

3rd EXCAVATION ELEV.-10.50m

HIROSE (THAILAND) LTD.

2ND STRUT -6.00

-21.00,22.00m

D - WALL

H-350x350x12x15

-10.50

-1.00 PLATFORM+0.75

1ST STRUT -2.50

INSTALLATION 3rd BRACING -9.50 m.

HIROSE (THAILAND) LTD.

Pre-Load 90 TON

PACKING CONCRETE3rd STRUT -9.50

2nd STRUT -6.00

-21.00 ,22.00m

D - WALL

H-350x350x12x19

-1.00PLATFORM+0.75

1ST STRUT -2.50

2nd STRUT -6.00

-10.50-13.70m

LEAN CONCRETE

4TH EXCAVATION -13.70m HIROSE (THAILAND) LTD.

3rd STRUT -9.50

-21.00 ,-22.00mH-350x350x12x19

-1.00PLATFORM+0.75

1ST STRUT -2.502nd STRUT -6.00

-1.00

FSP3 L=10M

CONTIGUOUS PILE -20.00 M

-14.70

PACKING CONCRETE

LEAN CONCRETE

MAT FOUNDATION

Driving inner sheet pile& 4th layer elev-14.70m

Pre-Load 50TON

-13.70mLEAN CONCRETE

HIROSE (THAILAND) LTD.

3rd STRUT -9.50

-18.00

D-WALL

PACKING CONCRETE

4m.4.20m.

12.0m.

EXCAVATION-15.00m.

-21.00 ,-22.00mH-350x350x12x19

-1.00PLATFORM+0.75

1ST STRUT -2.502nd STRUT -6.00

-1.00

FSP3 L=10MCONTIGUOUS PILE -20.00 M

-14.70

PACKING CONCRETE

Backfill

MAT FOUNDATION

Extract inner sheet pile& remove 4th layer elev-14.70m

-13.70mLEAN CONCRETE

HIROSE (THAILAND) LTD.

3rd STRUT -9.50

-18.00

D-WALL

PACKING CONCRETE

-1.00PLATFORM+0.75

1ST STRUT -2.502nd STRUT -6.00

-1.00

CONTIGUOUS PILE -20.00 M

MAT FOUNDATION

Remove 3rd layer elev.-9.50m

-13.70m

HIROSE (THAILAND) LTD.

3rd STRUT -9.50

-18.00

D-WALL

CONSTRUCT B3 -10.50m.

-1.00PLATFORM+0.75

1ST STRUT -2.502nd STRUT -6.00

-1.00

CONTIGUOUS PILE -20.00 M

MAT FOUNDATION

Remove 2nd layer elev.-6.00m

-13.70m

HIROSE (THAILAND) LTD.

-18.00

D-WALL

CONSTRUCT B3 -10.50m.

CONSTRUCT B2 -7.60m.

-1.00PLATFORM+0.75

1ST STRUT -2.50

-1.00

CONTIGUOUS PILE -20.00 M

MAT FOUNDATION

Remove 1ST layer elev.-2.50m

-13.70m

HIROSE (THAILAND) LTD.

-18.00

D-WALL

CONSTRUCT B3 -10.50m.

CONSTRUCT B2 -7.40m.

CONSTRUCT B1 -4.70m.

-1.00

PLATFORM+0.75

-1.00

CONTIGUOUS PILE -20.00 M

MAT FOUNDATION

Remove platform

-13.70m

HIROSE (THAILAND) LTD.

-18.00

D-WALL

CONSTRUCT B3 -10.50m.

CONSTRUCT B2 -7.40m.

CONSTRUCT B1-4.70m.

CONSTRUCT GROUND FLOOR.0.00

MONITERING MEASUREMENT SYSTEM

• THREE STEPS WARNING• 1) Alarm = 70% allowable front calculation each state of work

-inform everybody who concern-meeting to fix the ploblem

2) Alert = 85% allowable front calculation each state of work- fix the ploblem-meeting result of fixing

3) Action = 90% allowable front calculation each state of work- stop work- fix the ploblem -meeting result of fixing