Minimum Safety Requirements For ContractorsWorking On CP Property in Canada
Effective January 1, 2012
E-railsafe Canada Safety Orientation
1
Table of ContentsTable of Contents
Introduction
Application
Compliance
Safety Orientation
Safety Job Briefing
Security
Personal Conduct
Personal Protection
2
Table of Contents Cont.Table of Contents Cont.
Protection of Railway Traffic & Property
Railway Track Protection
Train Movements and Working Near Tracks
Equipment, Machinery and Tools
Operation of Highway Vehicles
Hazardous Materials and WHMIS
Emergency Response
Reporting
Conclusion
3
IntroductionIntroduction
At Canadian Pacific, safety is an integral part of the way wedo business. We expect everyone working on CP’s property tobe unconditionally committed to safety. Safety must be given top priority and will take precedence over deadlines, productionschedules, and all other considerations.
4
ApplicationApplication
CP’s Minimum Requirements For Contractors and the contents included within this presentation apply to all contractors and other persons performing work or otherwise providing services on CP property in Canada.
5
ComplianceCompliance
As contractor you are responsible for ensuring: your own safety; the health and safety of others you work with; the health and safety of CP employees you maybe working
With or in proximity to; the protection of the environment; the protection of CP’s property; and your work does not interfere with safe railway operations
In addition, you must: be properly trained and qualified to safely perform the work; be in possession of any required certifications, licenses,
permits, or written authorizations; be in possession of photo identification and any CP required
access pass, badge, certificate or hard hat sticker; be in compliance with CP’s Minimum Requirements For
Contractors and your company’s Contractor SafetyManagement Plan; and comply with all applicable legislation related to health,
safety, security and the environmentCP Approved Contractor
Hard Hat Sticker
6
Compliance Cont.Compliance Cont.
To ensure compliance and the safety of the work,CP reserves the right to:
review your company’s Contractor Safety Management Plan; review your training records; observe, inspect, test and audit all contractor personnel
for compliance; and ask for records and documentation providing evidence
of compliance
Failure of you or your company may result in CP: taking over control of the work; ordering the work to stop; and/or ordering you and/or your company to leave CP property
7
Safety OrientationSafety Orientation
This presentation provides a basic overview of what is required. Forcomplete details refer to a written copy of our Minimum RequirementsFor Contractors Working On CP Property In Canada.
Important -Prior to beginning work, all contractor personnel must participate in an on-site safety briefing presented by the CP Manager-in-Charge or designate that covers the following:
Scope, time, duration, and geographical limits on work being performed;
Identification of any local work place hazards, including any applicable track safety hazards and any hazards generatedby the work processes to be used;
Type of track protection being provided;
Any local safety issues, rules or requirements;
Location of first aid and fire fighting equipment; and
Local emergency contacts, evacuation plans and assembly locations
8
Safety Job BriefingSafety Job Briefing
Contractor Personnel shall: attend all job briefings whenever required; have an understanding of the scope
of work to be performed; be aware of any specific or unusual
hazardous conditions; be alert to hazards that may result from
interaction of work being performed bythe contractor and any CP personnel orother 3rd parties that are in proximity; identify and communicate hazards to their
supervisor and all others who may beaffected; and take interim measures to protect people,
property, equipment and the environmentuntil the hazard can be properly assessedand appropriate corrective actions taken
When CP employees are working with or in proximity to contractor personnel or are assigned to provide track protection, operate track units or other duties, they must be included in the job briefing.
9
SecuritySecurity
Access to CP Property
All Contractor Personnel must have the following identification on their person and ready to present upon request:
photo identification (e.g. driver’s license); proof of employment document or card; authorized decal, badge, certificate, or other proof
of safety orientation issued by CP; Access pass, issued and signed by the CP Manager-
in-Charge, where work requires Contractor Personnelto ride in any locomotive or non-passenger rollingstock; security identification card, where required by CP; and building access pass, where required by CP or by a
3rd party having control of the premises
Note – An e-Railafe Canada issued safety orientation certificate or CP endorsed U.S. security badge will satisfy bullet 3 above.
10
Security Cont.Security Cont.
Security AwarenessAll Contractor Personnel must have some understanding of the following while working on CP property:
basic understanding of railway security awareness; the importance of monitoring and reporting any
suspicious persons, activities, or objects; and staying alert to the environment
Reporting Security ConcernsYou must report any security concern, security incident, criminal activity (known or suspected), suspicious happenings and/or suspicious persons on CP property to the CP Manager-In-Charge or to CP Polices Service at 1-800-716-9132
In the case of emergency, call 911 (where this service exists); or Local emergency services; and CP Police Service
1111
Personal ConductPersonal Conduct
Entry onto CP property when in possession of, or under the influence ofalcohol, intoxicants, narcotics, or controlled substances is strictly prohibited.
No person working on CP property may be subjected to any form of discrimination or harassment, including sexual harassment.
Acts or threats of violence are unacceptable at all times on CP property.
Horseplay, practical jokes, fighting or any other activity that may create asafety hazard will not be tolerated.
Smoking is only permitted in designated outdoor smoking areas.
Firearms (loaded or empty) and explosives are not permitted on CP propertyexcept when authorized.
Use of personal electronic devices, such as portable audio and video devicessuch as iPods, DVD, CD, MP3 and game players is prohibited except in CP designated areas.
Operating, riding in or on CP rolling stock, equipment and vehicles is notpermitted unless authorized or in the case of emergency.
1212
Personal Conduct Cont.Personal Conduct Cont.
Except in emergency situations or where authorized by CP, use ofelectronic communication devices, including cell phones, Blackberries, PDA’s, Palm Pilots, walkie-talkies, GPS navigation units, portable computers and other similar devices, is prohibited:
while operating a highway vehicle, unless it is stopped and parked in asafe location (hand free devices may be used where permitted by law);
while operating or assisting in the operation of any railway equipmentor mobile equipment;
while operating power tools, equipment or machinery;
when foul of track* for any reason; or
whenever use of such device creates an unsafe condition
*Foul of track – means being in proximity to a track such that the individual or equipment could be struck by a moving train or track unit, or in any case within 4 feet (1.2 m) of the outside of the nearest rail.
13
Personal ProtectionPersonal Protection
You must wear the following PPE that meet CSA standards at all times while working on CP property unless otherwise specified.
Safety footwear (Z195 - Grade 1/Green triangle patch) Recommended your safety footwear has a defined heel, and is
laced and securely tied for increased ankle support
Hard hats (Z94.1) Recommended hard hats have high visibility characteristics which
are not obscured by markings or decals
Safety glasses (Z94.3) with permanently attached side shields Tinted safety eyewear must meet Canadian Military Standards for
red signal recognition if operating railway equipment. Safety glasseswith mirrored lenses are not permitted as they do not meet this standard.
Personal sunglasses are discouraged and not permitted to be worn if operating railway equipment. Transition lenses are discouraged and should be worn with caution
when working in changing light conditions.
High Visibility Apparel (Z96), Class 2 preferred Must not be covered by other clothing or equipment
except where necessary for safety reasons (i.e. whenwearing fall protection equipment). Lime green/yellow high visibility apparel is recommended
when working on, or near railway tracks, or working inproximity to CP personnel.
CP approved PPEis available at
Ackland’s-Grainger
Ask for it…if needed
14
Personal Protection Cont.Personal Protection Cont.
Work Clothing You must wear clothing that meets applicable
legislation and is suitable to perform your work safely, including Nomex or Proban fire-retardantprotective gear when performing TDG work or handling hazardous materials, as required.
Additional PPE
As required by applicable legislation, CSA standard or otherwise required to protect you from injury.
This includes but is not limited to: Fall protection equipment Hearing protection when working in areas:
consistently >84 dBA; exceeding 115 dBA at any time; and any other work areas where posted or so
notified by CP management Respiratory protection Hand protection Additional eye and face protection(i.e. welding goggles and helmets, splash goggles, face shields)
1515
Where the work site is in close proximity to, or is locatedon, above, or below railway tracks, special attention,care and precautions shall be taken to ensure your safety,the safety of CP employees, all other 3rd parties and toprotect CP’s property and railway operations.
You must be made aware of all unique and inherenthazards working near, on, above or below railwaytracks and you must be fully trained and equipped towork safely.
Protection of Railway Traffic & Property
1616
As a general rule 50 feet (15.2 m) on either side ofthe track(s) is CP property and is referred to as the“right-of-way”
Avoid this area at all times unless authorized by CPand you are properly protected, as required.
Your work must be organized and executedin such a manner to ensure no interferencewith the safety of railway operations.
Protection of Railway Traffic & Property Cont.
1717
Prior to starting any work on CP property, authorization, a local safety orientation, and proper protection (if deemed necessary by CP) is required.
CP will determine the type of track protectionrequired through a prior risk assessment based onthe type of work to be performed.
Examples include, but are not limited to: A Canadian Railway Operating Rules (CROR)qualified Flag Person Track Occupancy Permit (TOP) provided under CROR rules Red flag protection provided under CROR rules
indicates that CP employees are working onor foul-of-track, or the track is out of serviceand the movement of trains or other railwayequipment is prohibited
Blue flag protection indicates that CP employees are working on, under,
or between railway equipment
Signs, signals and flags are critical safety devices and may not be obstructed, removed, relocated, disabled or altered without proper CP authorization. Track switches may not be operated without proper CP qualification.
Protection of Railway Traffic & Property Cont.
1818
If a flag person is used to protect your work area youmust ensure clear communication at all times betweenyourself, your co-workers and CP’s flag person.
A safety briefing between the CP flag person and allcontractor personnel must occur before beginning anywork on or foul-of-track.
In addition, you must ensure you are aware of:
flagging distance limits;
time limits; and
any adjacent tracks where movement of railwayequipment may still occur.
You must not assume that a rail equipment movementis being stopped or cleared unless clear communicationis received directly from CP’s flag person.
You must always follow any instructions issued by a CP flag person.
Protection of Railway Traffic & Property Cont.
19
> 0–10 feet (3.01 m) from track centre
No machinery, persons, equipment or parts of equipment are permitted within 10 feet (3.01 m) from track centre or above the track at any time unless authorized and properly protected. One week advance notice is normally required.
Any violation creates a restricted clearance that is hazardous to CP operations. Notify the appropriate Network Management Centre (see slide #45) immediately of any situation that causes an obstruction within this zone without authorization and proper protection in place.
Typical CP Right-of-WayBlack Zone
The diagram and explanations (on the next three slides) outlines the different levels of permission/protection required prior to accessing and working on or above CP property
Railway Track Protection – Mainline and Sidings
20
Typical CP Right-of-Way
10 feet (3.01 m) – 25 feet (7.62 m) from track centre or above trackWritten authorization by CP must be obtained prior to any work taking place within the Red Zone.
Prior risk assessment based on the nature of the work to be performed will determine what type of track protection maybe required to work within this zone. One week advance notice is normally required.
Red Zone
Yellow Zone
25 feet (7.62 m) – 50 feet (15.2 m) from track centre or above track
CP must be advised and you must be authorized prior to working within this zone.
Railway Track Protection – Mainline and Sidings
21
> 50 feet (15.2 m) from track centre
This is outside of the right-of-way and prior CP authorization before starting work and track protection while working is not required by CP.
If in doubt about protection requirements, ask the CP Manager-in-Charge.
Green Zone
Typical CP Right-of-Way
Railway Track Protection – Mainline and Sidings
22
All zones as discussed in the previous three slides appear in yards as well. However, due to decreased distances between track centres (i.e. multiple track yards) the outer zones (i.e. green, yellow, and red) may not be present in all areas.
Remember….
Typical CP Right-of-Way
Railway Track Protection - Yards
Authorization, local safety orientation,and track protection must be providedby CP prior to working near, on, aboveor below any railway tracks.
Other protection, as required determinedby CP shall be arranged by a qualifiedperson.
2323
Train Movements and Working Near Tracks
You must be aware of and understand how you are being protected from rail equipment movements and comply with the following safety requirements when working foul-of-track or otherwise near railway tracks.
Be alert to train movements and you mustexpect the movement of trains, engines,railway cars, or other mobile railway equipmentat any time, on any track, and in any direction,even if they appear to be stationary or in storagewhether on foot or operating a vehicle or equipment.
This includes, not standing on or between adjacent tracks in multiple track territory and you need to be especially alert within yard and terminal areas as:
locomotives may be pushing railway cars; railway cars may be moving without any
locomotive attached; trains maybe moving remotely; locomotives and railway cars change tracks often; and movements maybe occurring simultaneously on
adjacent tracks
The area between two adjacent tracks isknown as the “Devil’s Strip”. You must treat all tracks as live!
2424
Train Movements and Working Near Tracks Cont.
In addition,
Only qualified contractor personnel who are specifically authorized by CP are permitted to operate, alter or obstruct any track, bridge, structure,or signals and communications equipment.
Be aware that railway pole lines carry electric power and should be treated as any other power lines.
Do not rely on others to protect you from railwayequipment movements.
No work activities are allowed within 50 feet (15.2 m) of the track centreline while trains are passing through the work site unless specifically authorized by CP. All buckets, shovels, and loads on cranes must be lowered to the ground to rest, and cranes without a load must have their load line tightened or retracted to prevent movement.
Do not remain in equipment or machinery that is within 50 feet (15.2 m) of a passing train and step out on the non-live side of the track (where possible).
Stand at least 20 feet (6.10 m) back from the track(s) to prevent possible injury from flying debris or loose rigging and you must observe the train as it passes and be prepared to take evasive action in the event of an emergency.
Ensure you are aware of the location of structures or obstructions where track clearances are close.
2525
Train Movements and Working Near Tracks Cont.
Do not stand on or foul-of-the track in front of an approaching locomotive, railway car or other railway equipment
Never climb on, under, or between railway equipment
Ensure a minimum of 50 feet (15.2 m) separation prior to crossing over tracks between standing railway equipment
Stay at least 15 feet (4.58 m) away from the ends of railway equipment when crossing the track
Look both ways before crossing tracks, and if clear walk at right angle to them
Do not walk, stand or sit on the rails as the rail surface can be extremely slippery. Step over the rails when crossing tracks.
Be aware railway ties can also be slippery and the ballast caneasily shift when walking on it. Maintaining situational awarenessand wearing quality safety footwear properly is important
Stay away from any railway device you are unsure of and be awarethat some track switches are remotely operated and the switch points can move without notice with enough force to crush ballast.
Do not disturb or foul the ballast at any time.Example of a remotely
operated switch
26
Remember…always be alert when working around rail tracks and in yards as there are many different types of vehicles and equipment to watch out for!
Locomotives Mobile Equipment
Rail Cars
Track MobilesHi-rail Equipment
Vehicles
Top LiftEquipment
Track WorkEquipment
Train Movements and Working Near Tracks Cont.
27
Equipment, Machinery and Tools
You must ensure that all equipment, machinery, and tools used:
be in good working order, properly serviced and maintained;
be safe for their proposed use and used only for the purposes as specified by the manufacturer;
not foul-the-track with any equipment or machine without a CP flag person and/or proper track protection;
be in compliance with applicable legislation;
if mobile, must be equipped with appropriate safetydevices (e.g. lights, horns, back-up alarms, safetybeacons, etc.), and prevented from moving when notin use through the use of hand brakes, wheel blocking,wheel chocking and/or a derail where applicable
The use of CP owned tools by contractor personnel is prohibited unless specifically authorized by local CP management.
28
Equipment, Machinery and Tools Cont.
Do not move equipment and machinery acrosstracks except at established road crossings, orunless under the protection and authorization of a CP flag person and only if the job site has beenproperly prepared for such a move.
Tracked equipment will require a CP flag person anytime railway tracks are crossed.
Do not move equipment and machinery across railwaybridges or through tunnels, except as expressly agreedto by CP, and under such conditions as stipulated by,including without limitation, a CP flag person.
29
Equipment, Machinery and Tools Cont.
Unattended Equipment Or Machinery
Equipment, machinery and tools must not be leftunattended at any time or stored on CP property,unless authorized in writing by CP.
If authorized to leave any equipment, machinery,or tools unattended or stored on CP property youmust ensure that:
storage is restricted to the area designatedby CP only;
all equipment is secured in a safe location well clear of all tracks to prevent accidental contact with railway equipment and they do not restrict train crew sightlines; and
as much as possible be stored in locations outof public view
30
Equipment, Machinery and Tools Cont.
Excavations
Before starting any excavation operations it mustbe confirmed there are no underground wires, fibreoptic cables, pipelines, or other utilities which couldbe damaged or, if present that such installations areproperly protected.
Fibre optic cables are present on most segments ofCP’s right-of-way. Prior to starting any excavationyou must contact the proper authority to obtain thenecessary permit and to locate and protect such cablesor other underground utilities.
You must Contact the CP Manager-in-Charge for the location of any CP or public utilities located on or near CP property, and you should always contact your local Call Before You Dig / One Call service prior to starting any excavations.
Excavations must not be left unattended unless they are properly protected and the CP Manager-in-Charge is notified.
31
Equipment, Machinery and Tools Cont.
Lockout – Hazardous Energy Control
You must use follow your own company’s lockout –hazardous energy control program and procedures(providing they meet or exceed applicable legislativerequirements) if you are working completely independentand isolated from CP personnel and the equipment or machinery you have locked out will have no impact on CP employees.
In situations where your work may impact CP employees (i.e. both Contractors and CP employees working on the same or related machine, equipment and/or process or the hazardous energy being controlled could impact CP employees if not controlled properly) the requirements as set forth in CP’s Lockout – Hazardous Energy Control Policy and Code of Practice must be followed.
You must not remove any CP applied lock or tag, including any bad-order equipment tags
CP Bad Order Tag
32
Equipment, Machinery and Tools Cont.
Electrical Safety
In addition, to all lockout–hazardous energycontrol requirements, mentioned on the previousslide, all electrical work must comply with applicablelegislation, CSA standards, Canadian Electrical Code Parts 1/2 and National Fire Protection Association (NFPA) requirements, and
If working on electrical systems in proximity to CPpersonnel you must inform them of the following:
existing or potential electrical hazards; any specific additional PPE that may be required; applicable safe work practices; applicable emergency and evacuation procedures; and apply lockout– azardous energy control procedures
as per the previous slide
Courtesy - Where’s The LineGov’t of Alberta Joint Utility Safety Team
You must not operate or allow cranes or other mobileequipment to approach closer to any live electricalpower line as per local legislative requirements andwhat is permitted by CSA Z150 Mobile Cranes
33
Equipment, Machinery and Tools Cont.
Lifting Devices
All lifting devices including but not limited to jacks, cranes, cables, slings, and hooks must:
meet applicable legislation governing design, inspection,maintenance and operation; be safety certified and tagged with load capacity limitswhere required; have sufficient capacity for the planned lift; and in the case of jacks have sufficient footing or supportarea to properly distribute the load during a lift
Explosive Actuated Tools
You must be qualified and licensed in accordance with applicablelegislation, and authorized by CP, to use any explosives or explosiveactuated tools
Confined Spaces
You must be properly qualified and authorizedas per legislative requirements to enter andwork in a confined space.
34
Welding and Torch Cutting
When welding or torch cutting you must ensurethe following:
you properly trained and qualified;
all closed containers are properly purged;
flames or sparks are directed away from otherworkers, equipment and flammable material;
have a fire extinguisher readily available;
keep compressed gas and oxygen cylinders properly labeled and stored with the regulators removed and the caps applied in a secure, vertical position located in vented cabinets or other designated locations; and
avoid using cutting or welding processes during the last one-half hour of shifts, where possible.
Equipment, Machinery and Tools Cont.
35
Operation Of Highway Vehicles
Prior to the operation of any highway vehicle operated on CP property or used to transport CP personnel, you must ensure the following:
all required pre-trip inspections and any required legislated periodic inspections are completed; and
the vehicle is maintained in safe operating conditions at all times and is in compliance with applicable motor vehicle regulations and license requirements.
As an operator of a highway vehicle, you must:
hold a valid driver’s license for the class of vehicle being driven;
strictly comply with all posted signs, signals and all obey applicable legislation;
maintain all required vehicle inspection and driver logs and make these available to the CP Manager-in-Charge upon request;
always wear seat belts if operating or riding in a vehicle equipped with them unless you are actively engaged in inspections on CP property and then only when the vehicle is driven under 25 Km/h (15 mph); and
comply with CP’s Use of Electronic Devices requirements as per Slide #11.
36
Operation Of Highway Vehicles Cont.
While driving on CP property you must:
travel only on designated roadways unless otherwiseinstructed;
keep daytime running lights on (if so equipped);
not exceed 25 Km/h (15 mph) unless otherwise posted;
come to a full stop at all blind corners, rail and roadwaycrossings;
yield the right-of-way to all mobile equipment and allother non-highway equipment or service vehicles;
not drive within 50 feet (15.2 m) of the closest track centre line unless authorized by CP and not park foul-of-track unless on- track protection is provided;
not remain in a vehicle that is within 50 feet (15.2 m) of a passing train unless specifically authorized by CP. Where this not possible, park the vehicle as far away from the tracks as possible and walk to a safe location standing at least 20 feet (6.10 m) from the tracks, where possible.
37
Operation Of Highway Vehicles Cont.
While driving on CP property you must:
not leave vehicles running unnecessarily;
park only in pre-determined or designated areas;
always use the parking brake (or wheels chocks) when leaving an unoccupied vehicle running; and
where safe and practicable, back vehicles into marked parking spaces to avoid reverse collisions when exiting;
ensure all vehicles are properly loaded and all loads are secured in accordance with applicable provincial legislation and required permits, this includes the transportation of dangerous goods.
All contractor personnel who will be operating a highway vehicle or mobile equipment in any CP Intermodal Facility must complete CP’s Intermodal Facility Driver Safety Orientation (DSO) program prior to first entry, and from time-to-time, thereafter, as directed by the CP Manager-in-Charge.
38
Hazardous Materials / Workplace Hazardous Materials Information System (WHMIS)
General Requirements
If at any time your work involves the use, handling, storage or disposal of hazardous materials you must inform the CP Manager-in-Charge.
You must be fully trained in the handling of hazardous materials and be in full compliance with applicable legislation and as directed by the CP Manager-in-Charge.
In addition, you must follow appropriate processes, systems and controls in place to prevent or otherwise mitigate potential environmental, health, safety, and security risks associated with the handling of hazardous materials.
If transporting dangerous goods you must be certified in accordance with federal legislation.
Material Safety Data Sheets (MSDS’s)
Prior to beginning any work that may expose CP personnel to hazardous materials you must:
provide a copy of the respective MSDS to the CP Manager-in-Charge; and keep a copy of the MSDS at the work site and ensure that it
is readily available at all times.
39
Hazardous Material Incident or Spill
In the event of a hazardous material incident or spillyou must:
ensure that no contractor or CP personnel have orwill be exposed;
take all reasonable actions to contain the spill;
respond in accordance with the applicable emergency response plan identified in the local safety briefing; and
notify CP immediately in accordance with theinstructions on Slides # 43-44
Hazardous Materials / Workplace Hazardous
Materials Information System (WHMIS) Cont.
40
Emergency Response
Emergency Response Plan
Your company must maintain a current emergencyresponse plan and make it available to CP onrequest.
As a minimum this plan must include:
contractor reporting procedures in the eventof an incident or spill;
emergency response contacts and phone numbers,including phone numbers for CP incident reportingand local CP managers; and
Note- a sample Emergency Information Sheet template is included as Appendix A within CP’s Minimum Requirement for Contractors
emergency response and/or containment measures to be taken in the event of an incidentor spill
41
Emergency Response Cont.
Initial Response
Initial response to any emergency condition mustfollow the following sequence:
protect the safety and security of all individualsand communities;
provide environmental protection and mitigation;
conduct incident investigation and evidencepreservation; and
restore railway operations
Designated MeetingLocation
First Aid
Your worksite must have sufficient first aid qualifiedpersonnel and the required first aid kit and otherrequired first aid equipment onsite suitable for thecrew size, nature of the work being performed andlocation, all of which, at a minimum must complywith applicable legislation.
42
Fire Protection
Your worksite, including on equipment, machinery and vehicles must have appropriate fire extinguishers, suitable in type, size and quantity appropriate for the nature of the work being performed and meeting applicable legislation at all times.
You must take the necessary precautions to preventfires, including:
smoking in designated areas only;
storing flammable materials in proper containers;
storing and transporting flammable liquids in approved containers only;
proper disposal of flammable materials daily;
preventing the accumulation of static electricity when dispensing or transferring flammable liquids by using proper grounding and bonding techniques.
Emergency Response Cont.
43
Fire Protection
You must take the necessary precautions to preventfires, including:
avoiding using cutting or welding processes during the last one-half hour of shifts, where possible;
taking special precautions when using flares / fusees, ensuring they are completely extinguishedwhen you are finished using them;
promptly advising CP management of any fire onCP property; and
fully extinguishing or providing protection for any fire prior to leaving the work site
Emergency Response Cont.
If you are working on the CP right-of-way where a high risk of fire exists(e.g. during rail grinding, rail welding) you must have:
appropriate fire prevention and suppression plans (including emergencynumbers for CP, local firefighters, and fire control districts); and additional fire fighting equipment and trained contractor personnel on site,as required by applicable legislation
44
Reporting
In the event of an emergency, you must call:
911, where this emergency response system exists, or
the local police, fire or emergency department; and
in all cases, also the CP Police Services Communication Centretoll free at 1-800-716-9132 from any Canadian or US location
When an accident, incident or injury occurs on CP property, you must:
immediately report it to the CP Manager-in-Charge or the appropriateNetwork Management Centre (see next slide);
follow instructions given to protect the scene; and
provide the requested information when prompted, to the best of your knowledge at the time
participate in any CP or government directed investigation
Know where you are working….ensure others will know where you are!!!- specific railway locations are not commonly known by emergency response personnel/call centres- local names and locations (i.e. non-railway) may not be known by CP call in centre personnel
(i.e. Network Management Centre (NMC), CP Police Communications Centre)
45
Reporting Cont.
24/7 Accident, Incident, Injury Reporting
Canada (West of and including Mactier, Ontario) 1-800-795-7851
Canada (East of Mactier, Ontario and Southern Ontario) 1-800-363-3277
For incidents requiring Police Services contact CP Police 1-800-716-9132
46
Conclusion
Please keep in mind this presentation provides a basic overview of what is requiredwhile working on CP property. For complete details please refer to a written copyof our Minimum Safety Requirements For Contractors Working On CP Property InCanada (issued September 15, 2010). Copies are available on e-railsafe Canada, at www.cpr.ca or from your CP Manager-in-Charge.
Important –Prior to beginning work, all contractor personnel must participate in an on-site safety briefing presented by the CP Manager-in-Charge or his designate that covers the following:
Scope, time, duration, and geographical limits on work being performed;
Identification of any local work place hazards, includingany applicable track safety hazards and any hazards generatedby the work processes to be used;
Type of track protection being provided;
Any local safety issues, rules or requirements;
Location of first aid and fire fighting equipment; and
Local emergency evacuation plans and assembly locations
Contractors maybe observed, tested, and audited by CP for safety compliance