Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017

Post on 22-Jan-2018

1.976 views 0 download

Transcript of Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017

EGLINTON CROSSTOWNEglinton-Mount Pleasant Construction Liaison CommitteeJuly 11, 2017

2

Agenda

• Eglinton Station Update

• Mount Pleasant Station Update

3

Eglinton Station Updates

Complete

Demolition of the Salvation Army Community Church

Demolition of the abandoned TTC bus depot

Wet utilities stages 1-3 (of 4)

Toronto Hydro stages 1a, 1b

Summer/Fall 2017

• Water main and sanitary sewer relocation works are ongoing at the Yonge-Eglinton intersection

• Toronto Hydro relocation (2b) ongoing on Duplex to Hillsdale to Yonge

• Shoring is underway at the Salvation Army and TTC bus depot sites and along the south side of Eglinton (Three rigs now in operation)

– This is the major activity of 2017; maps attached for each stage

4

Eglinton Station Shoring Stage 1

5

Eglinton Station Shoring Stage 2a

6

Eglinton Station Shoring Stage 2b

7

Eglinton Station Shoring Stage 3

8

Construction Progress Picture

A third rig mobilized at the bus depot site

Crews building a guide wall for shoring

9

Mount Pleasant Station Construction Update

Complete

Demolition at 280 and 280 Eglinton Ave E to make way for the Secondary Entrance

Demolition at 256-58 Eglinton Ave E to make way for the Main Entrance

Installation of geotechnical monitoring equipment

Long-term closure of Rawlinson Ave for site trailers and laydown area

Shoring at the Main Entrance

Installation of temporary traffic signals

Summer 2017

• Continue hydro utilities relocation

• Commence sewer relocation at the Secondary Entrance site

• Piling in the roadway, beginning on the northwest side of Eglinton Avenue East

• Resume piling at the Secondary Entrance

10

Mount Pleasant Station Lookahead

Year Quarter Construction ActivityApprox.

Duration

2017Q2-Q4

(April-December)

• Implement traffic staging on the north side of

Eglinton Ave E, and commence utilities relocation and

piling

• Implement traffic staging on the south side of

Eglinton Ave E, continue utilities relocation and piling

• 2 months

• 4 months

2018

Q1-Q2

(January-June)

• Shallow excavation and roof slab construction on the

south side of Eglinton Ave E

• 6 months

Q3-Q4

(July-December)

• Shallow excavation and roof slab construction on the

north side Eglinton Ave E

• 6 months

11

Current Construction Staging

Began June 2017 for approximately two (2) months

NO TURNS IN ALL DIRECTIONSMT PLEASANT &

EGLINTON

12

Mount Pleasant Station Concept Aerial View

Main Entrance

Secondary Entrance

*60% rendering

13

Mount Pleasant Station Main Entrance

*60% rendering

14

Mount Pleasant Station Secondary Entrance

*60% rendering

15

Mount Pleasant Station Construction Progress

15

BACK FILLING TRENCH

EXPOSING UTILITIES

16

Mount Pleasant Station Construction Progress

16

HYDRO TRENCHHYDRO POLE

WORK

17

Mount Pleasant Station Construction Progress

17As of May 2017