E.Clément Novembre 2011 E.Clément GANIL AGATA Days February 2013
AGATA Campaign at GANIL
Setup to be integrated
AGATA@GANIL: Project Organization and Planning
Status of the installation
E.Clément Novembre 2011
Charged particle array for transfer reaction MUST2/TIARA : (d,p) etc … program with SIB and RIB
Charged particle array for prompt tagging : DIAMANT Neutron detector (Nwall) Charged particle array for Recoil Decay Tagging : MUSETT
Scintillator : BaF2 array, LaBr3 Future detector : NEDA (n) , GASPARD ( ?), PARIS (LaBr3)
In G1 coupled to VAMOS (+ EXOGAM2): SIBs, RIBs
AGATA 1p at GANIL : Ancillary devices
At 0° as separator (vaccum/gas-filled)
Angles >10 deg for fission & MNT
E.Clément GANIL AGATA Days February 2013
E.Clément Novembre 2011
VAMOS(disp); 20; 29%
VAMOS(gfm); 15; 21%
VAMOS(foc); 2; 3%
NWALL; 18; 26%
DSSD; 11; 16%
DIAMANT Solo; 2; 3% MUST2; 1; 1% AGATA solo; 1; 1% VAMOS(disp)
VAMOS(gfm)
VAMOS(foc)
NWALL
DSSD
DIAMANT Solo
MUST2
AGATA solo
plunger; 16; 19%
spectro; 70; 81%
plunger
spectro
E.Clément GANIL AGATA Days February 2013
o We have received 47 Letters of Intents
o The equivalent of ~2006 UT are proposed 16048 hours of beam on target (669 days)o 4 main setups
o Vamos in magnetic spectrometero Vamos in gas-filledo Nwall + Diamanto DSSSD
We need to organize sub-campaigns by setup and investigate the technical issues case by case : Working Group, leader to be identified during the workshopPlanning of upgrade of some ancillaries (gas-filled, NWALL, DIAMANT)
AGATA will increase in efficiency during the campaignNot all experiments will benefit from the 1p
E.Clément Novembre 2011
100Mo; 3; 4% 120Sn; 1; 1%164Dy; 2;
3%
170Er; 1; 1%
176Yb; 1; 1%
181Ta; 1; 1%
198Pt; 1; 1%
208,207,206Pb; 1; 1%
238U; 11; 16%
24Mg; 2; 3%28Si; 2; 3%
45Sc; 1; 1%46Ti; 1; 1%
40Ca; 2; 3%48Ca; 3; 4%50Cr; 3; 4%54,56Fe; 2; 3%58Ni; 3; 4%
70Zn; 10; 14%
76Ge; 3; 4%
6,7Li; 2; 3%93Nb; 2; 3%
96,94Zr; 1; 1%
9Be; 3; 4%
H; 3; 4%
150,154Sm; 1; 1% 160Gd; 2; 3% 2; 3%
12C 100Mo
120Sn 164Dy
170Er 176Yb
181Ta 198Pt
208,207,206Pb 238U
24Mg 28Si
45Sc 46Ti
40Ca 48Ca
50Cr 54,56Fe
58Ni 70Zn
76Ge 6,7Li
93Nb 96,94Zr
9Be H
150,154Sm 160GdTarget
208Pb; 4; 6%136Xe; 4; 6%
18,19O; 2; 3%22,26,27Mg;
3; 4%
238U; 13; 18%
25Na; 2; 3%
28Si; 2; 3%
32,36S; 2; 3%33,36,40,44,45Ar; 8; 11%
37Cl; 1; 1%38m,45K; 2;
3%
40,48Ca; 12; 17%
50Ti; 3; 4%
54Fe; 4; 6%
58Ni; 5; 7%
76,78,86Kr; 4; 6% 92Mo; 1; 1%208Pb
136Xe
18,19O
22,26,27Mg
238U
25Na
28Si
32,36S
33,36,40,44,45Ar
37Cl
38m,45K
40,48Ca
50Ti
54Fe
58Ni
76,78,86Kr
92MoBeamE.Clément GANIL AGATA Days February 2013
GANIL cannot produce all of them : Metallic 238U 48Ca target is a challenge Plunger Target Joa’s talk To be discussed within the Working Group
You might be invited to provide expensive isotopes for the accelerator (48Ca, 70Zn…)
GANIL have some limitation for low beam energy40,48Ca and 56Ni beams issues to be discussed in the WG
CSS1; 45; 74%
CSS2; 1; 2%
SPI-RAL1 new;
6; 10%
SPI-RAL1 exis-tant;
9; 15%
CSS1
CSS2
SPIRAL1 new
SPIRAL1 existant
E.Clément Novembre 2011 E.Clément GANIL Scientific Council February 2013
EXOGAM, LaBr3, BaF2 …
AGATA Configurations at GANILE
. Farnea et al, N
uclear Instruments and
Methods in P
hysics Research A
621 (2010) 331–343
See Johan’s talk
E.Clément Novembre 2011
Local organization doneTasks distribution and their detailed description were distributedGANIL project :
Set of spec delivered, detailed planning, resources evaluation, budget, development plan, PBS, WBS distributed
Security/safety : Installation description for DIRC01 :
1st draft released, risk analysis beginning of 2013
The call for tender, to be launched by May 2013 after GANIL management review, are under preparation
Specific infrastructure to be delivered in December 2013
In 2012, ~4 FTE have worked on the project (20 persons involved at GANIL)For 2013-2014, ~80 m.month are evaluated
Organisation
E.Clément GANIL AGATA Days February 2013
E.Clément Novembre 2011
Schedule (assuming that material from GSI arrive on Jan-Feb 2014)
Gas-filled installation expected in mid-2015 if funded in 2013 GANISOL beams available for physics beginning of 2016 No SPIRAL1 beam in 2014-2015
GANIL has requested the host of AGATA until end of 2016
T2-12 T3-12 T4-12 T1-13 T2-13 T3-13 T4-13 T1-14 T2-14 T3-14 T4-14 … T4-16
Mechanics STFC Design
GANIL Impl
IPHC construc
Mounting
Infrastructure det
GANIL Studies
Collecting items
Installation
LN2, AF
GANIL Studies Collecting items
Installation Test
DAQ Hardware
GANIL Studies
Collecting items
Installation Test
DAQ Software
Prep.
Test
Processing Room
Renov Aire Proj AGATA
infra
Detector
Mounting
Source & Commi Expt …
E.Clément GANIL AGATA Days February 2013
E.Clément Novembre 2011
~150 k€
~17k€
Processing room 019Upgrade ~ 102k€
Detector lab infrastructure ~15 k€
Cryogenic upgrade, connection ~25 k€
Total investment cost ~380 k€
Optical fibers links ~70k€
E.Clément GANIL AGATA Days February 2013
E.Clément Novembre 2011
Budget : Total cost investment ~380k€
237 k€ guaranteed by GANIL for 2013 to be completed in the 2014 request
IPHC requested 90k€ from IN2P3-AP for the mechanic
ANR (French Research Funding Agency) request for the gas-filled mode submitted by the Saclay and GANIL group (PI : Ch. Theisen & Ch. Schmitt)
Loan of material from LNL & GSI (cooled cabinet, racks, water distribution, Optical link) under evaluation
E.Clément GANIL AGATA Days February 2013
E.Clément Novembre 2011
Detectors support design done by STFC Daresbury in close collaboration with GANIL GANIL designs the additional platform GANIL takes in charge the integration work Projection T1 -2013 9 months of construction estimated starting by T1-2013
On-going collaboration with the IPHC workshop for the construction of the support
Workshop for the extended platform not yet defined
I. Burrows (STFC) M. Ozille, P. Gangnant (GANIL)
Mechanic
E.Clément GANIL AGATA Days February 2013
E.Clément Novembre 2011 I. Burrows (STFC) M. Ozille (GANIL) G. Gaudiot (IPHC)
Mechanic
First 2D projections have been released in January On-going validation and fine cost estimate Mechanical stress and rigidity calculations validated
E.Clément GANIL AGATA Days February 2013
E.Clément Novembre 2011
M. Ozille, P. Gangnant, G. Fremont (GANIL)
GANIL is in charge of the beam section and target chamber design for most of the experiment
Specific configurations will be treated case by case
Target loader :Detailed design on going by GANILFinal decision will be taken after the workshop
Target loader and beam line
E.Clément GANIL AGATA Days February 2013
VAMOS(disp); 20; 29%
VAMOS(gfm); 15; 21%
VAMOS(foc); 2; 3%
NWALL; 18; 26%
DSSD; 11; 16%
DIAMANT Solo; 2; 3%MUST2; 1; 1%AGATA solo; 1; 1%
E.Clément Novembre 2011
Salle G1
AGATA
EXOGAM Elec.
AGATA Elec.
DSS
300 optical wires
Water cooling 26° 8 bars
27 kW UPS
L. Menager, J. Ropert, JL. Foucher (GANIL)
Integration
Cryogenic distribution
E.Clément GANIL AGATA Days February 2013
E.Clément Novembre 2011
L. Menager, M. Jean , N. Menard (GANIL)
The foreseen room required important investment (refurbishment, electricity, water cooling, air conditioning …)
G1 cave
Integration
E.Clément GANIL AGATA Days February 2013
E.Clément Novembre 2011
Performance simulations : on-going (see Johan’s talk)
Electronic coupling: on-going (several meeting already done, transfer of knowledge in GSI during 2013)
Detector: starting (transfer of knowledge in GSI during 2013)
Data flow, DAQ: on-going (several meeting already done, no problem anticipated)
Mechanic design : on-going (final design review)
Optical link : on-going (Call for tender expected by April)
Data analysis : starting (first meeting on the first week of Dec.)
AutoFill-cryogenic : on-going (definition of the installation, call for tender in April)
Infrastructure : on-going (final design review on going)
E.Clément GANIL AGATA Days February 2013
E.Clément Novembre 2011
Conclusion Physics objectives will be presented at the next CS for evaluation (Campaign definition) Sub-campaigns to be discussed and adjusted with upgrade planning
2014-mid 2015 : AGATA-VAMOS+ “light” ancillary2015 : gas-filled, NWALL2016 : SPIRAL1 beams
The AGATA project at GANIL made progress in all different items with a particular attention on the mechanic and the integration
The transfer of knowledge on detectors and electronic will be organized in 2013 during off and on-beam period at GSI with GANIL technical staff.
Mechanical construction should start soon, delivery by end of 2013
Call for tender are expected to be sent by May 2013 for infrastructure
Data Acquisition and Data analysis preparation will progress over 2013
GANIL technical involvement is already significant
Budget guaranteed by GANIL for 2013 to be completed in the 2014 request
E.Clément GANIL AGATA Days February 2013